Attachment 1 - Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| North Mills Sign in Sheet.pdf | ||
| SF30 - Amendment 2.pdf | ||
| SF30 Amendment 1.pdf | ||
| Exhibit 1 - Drawings.pdf | ||
| Section B1 - SOI Supp Instructions.doc | DOC document | |
| Section A - SF 1442.pdf | ||
| Attachment 2 - Wage Determination.doc | DOC document | |
| Section B - Schedule of Items.pdf | ||
| Sections C thru M - Solicitation.doc | DOC document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
SPECIFICATION INDEX
DIVISION 1 - GENERAL REQUIREMENTS
01010 - Summary of Work 01050 - Field Engineering 01300 - Submittals
DIVISION 2 - SITE WORK
02110 - Clearing 02200 - Building Demolition 02210 - Site Grading 02220 - Structural Excavation 02221 - Trenching, Backfilling and Compaction for Utilities 02250 - Compaction Control and Testing 02400 - Sheeting, Shoring, and Bracing 02530 - Dewatering 02540 - Erosion and Sedimentation Control 02600 – Pavement Repair, Removal & Replacement 02821 - Seeding 02822 - Chain-Link Fence and Gate
DIVISION 3 - CONCRETE
03100 - Concrete Formwork 03200 - Concrete Reinforcement 03300 - Cast-in-Place Concrete 03310 - Concrete from Packaged Dry Mix for Minor Structures
DIVISION 4 - MASONRY
04150 - Masonry Accessories 04220 - Concrete Unit Masonry 04410 - Stone Masonry
DIVISION 5 - METALS
05500 - Metal Fabrications
DIVISION 6 - WOOD AND PLASTICS
06100 - Rough Carpentry 06200 - Finish Carpentry
DIVISION 7 - THERMAL AND MOISTURE
07110 - Membrane Waterproofing 07210 - Building Insulation 07310 – Roof Shingles
DIVISION 8 - DOORS AND WINDOWS
08210 - Metal Doors 08710 - Finish Hardware 08840 - Glazing Plastics
DIVISION 9 - FINISHES
09330 - Floor Tile 09800 - Special Wall Covering 09900 - Painting
DIVISION 10 - SPECIALTIES
10800 - Toilet and Bath Accessories
DIVISION 15 - MECHANICAL
15000 - Prefabricated Steel Wastewater Treatment System 15060 - Pipe and Pipe Fittings 15100 - Building Valves 15146 - Submersible Pumps, Controls & Related 15147 - FRP Potable Water Hydropneumatic Tanks 15170 - Potable Water Meters 15213 - Waterlines 15214 - Disinfection of Waterlines 15254 - Pipe Insulation 15311 - Gravity Sewers 15351 - Wet Well 15352 - Submersible Sewage Grinder Pumps 15460 - Plumbing Fixtures and Trim 15614 - Liquefied Petroleum Gas
DIVISION 16 - ELECTRICAL
16010 - Basic Electrical Requirements 16100 - Basic Materials and Methods 16230 - LP-Gas Power Generator 16402 - Underground Electrical Service 16500 - Lighting
DIVISION 1 - GENERAL REQUIREMENTES
01010 - Summary of Work 01050 - Field Engineering 01300 - Submittals
SECTION 01010
SUMMARY OF WORK
PART 1 - GENERAL
A. The Contractor is to provide the complete construction of the new treatment plant, bath-house, water distribution system, and wellhouse upgrading as specified herein and as shown on the drawings.
B. Storage of Materials
1. The Contractor may store materials and equipment at the work site at his own risk. All materials must be kept in an area designated by the C.O. and be neat and orderly.
2. The Contractor shall install safety fences around all open excavations, storage areas and around the perimeter of the new building sites.
C. Campground Operations
1. The campground will open on April 16th and close on September 10th
(After Labor Day Weekend).
D. Coordination with Others
1. The installation of overhead primary and secondary underground power shall be coordinated with Duke Power Company. Contact person is Eddie Reese
E. Construction Schedule
1. A proposed schedule of work for the project construction shall be submitted to the C.O. for approval 10 days prior to starting construction.
2. Contract time is 365 calendar days and includes inclement weather days.
3. The Contractor will be required to start construction in the following order:
a. Treatment Plant construction including foundation, treatment plant installation, utility lines, MDP, generator and fencing.
b. Complete construction of 8-Unit Bath-House
c. Installation of yard hydrants
d. Partial construction of storage room
e. Remaining Work Items after Campground is closed for the season.
4. The Contractor will be allowed to use two campsites adjacent to the new Bath-House for storage and parking of construction equipment.
F. Existing Facilities
1. The Contractor must furnish a portable toilet after the Campground is closed.
2. The Contractor will be allowed to use electricity free of charge for the construction of this project only.
3. Potable water will be available at the job site for construction only.
G. Safety
1. No trenches will be left open overnight.
2. Electrical switches will be locked in the “OFF ” position.
H. Project Closeout
1. Instruction of Government Personnel in Use of Facilities
It is the responsibility of the Contractor to see that the proper manufacturer's representative, subcontractors, contractor's superintendents, etc., are available at completion of the job and before occupancy to provide instructions in the use of all facilities and equipment and to train personnel in the proper use and maintenance of the building, equipment controls, switches, valves, etc.
2. Operating and Maintenance Manuals
The Contractor shall furnish the following:
a. Instructions for maintenance of all systems.
b. Copies of hardware schedule.
c. Shop drawings and brochures on all special items and equipment.
d. Three copies of the complete operating and maintenance manual for mechanical and electrical equipment. The bound manual shall contain the following:
(1) Word description of the systems.
(2) General operating instructions, including copies of posted specific instructions.
(3) Maintenance instructions, followed by tabulated manufacturer's descriptive literature, shop drawings, performance curves and rating data, spare parts lists, and maintenance manuals.
(4) Warranties.
SECTION 01050
FIELD ENGINEERING
A. The locations of all proposed new work relative to existing features are indicated on the construction drawings. Bench marks for vertical control are to be provided by the C.O.
The project COR shall stake all buildings and shall determine finish floor elevations.
B. Construction staking for the installation of all utilities shall be the responsibility of the Contractor.
Construction Staking by the Contractor shall be approved by the COR prior to commencing construction on that part.
SECTION 01300
SUBMITTALS
A. The Contractor shall be required to furnish the following to the C.O. prior to commencing any work that relates to a respective submittal (three copies of all submittals required).
1. Precast Concrete Wetwells and related.
2. Grinder Pumps and Controls - assembly and operation, pump curves, maintenance, installation, repair, and parts list with drawings. The Contractor shall also submit the name, address, and telephone number of the sales and/or service office closest to the project area for the pump installed. The C.O. shall approve the pumps and controls before field installation.
3. Electrical Generator and Controls
4. Building Submittals:
a. Finish Hardware
b. Floor Tile
c. Mechanical and Plumbing Equipment Data and Drawings.
d. Electrical Equipment Data and Drawings
5. Packaged Sewage Treatment Plant
6. Any other equipment that is a substitute for specified equipment.
B. The Contractor shall obtain approval in writing before installation of equipment.
DIVISION 2 - SITE WORK
02110 – Clearing 02200 – Building Demolition 02210 – Site Grading 02220 – Structural Excavation 02221 – Trenching, Backfilling, and Compacting 02250 – Compaction and Testing 02400 – Sheeting, Shoring, and Bracing 02530 - Dewatering 02540 – Erosion and Sedimentation Control 02600 – Pavement Repair, Removal & Replacement 02720 – Aggregate Base 02821 – Seeding, Fertilizing and Mulching 02822 – Chain-Link Fence and Gate
SECTION 02110
CLEARING
A. Work included in this section covers clearing, grubbing, and removal of all vegetation within the construction area as shown on the drawings or specified herein for the construction of the buildings and installation of new site utilities.
B. Utility line clearing shall be kept to a minimum and shall, in no case exceed 10-foot width.
PART 2 – PRODUCTS
A. None
PART 3 - EXECUTION
A. Clearing and grubbing shall consist of clearing the area of all trees marked to be removed, brush and other vegetation, rubbish and all objectionable material, and shall include grubbing stumps that may interfere with the installation of utility lines or building foundations.
B. All logs, brush, stumps and debris shall become the property of the Contractor and shall be hauled-off
Government land.
1. Brush may be chipped on-site and scattered as directed by the Contracting Officer.
C. Trees shall be felled so as not to damage trees outside of the construction area or trees that are to remain.
D. Trees that are damaged will be painted with tree wound dressing on all cuts and wounds.
SECTION 02200
BUILDING DEMOLITION
PART 1 – GENERAL
Work included in this section covers the removal of the existing treatment plant, flush toilet building and selective building demolition of existing wellhouse.
A. Excess excavation from construction of new plant foundation.
PART 3 – EXECUTION
A. Disconnect electrical service to the buildings prior to demolition.
B. The Forest Service reserves the right to remove and retain ownership of any plumbing and electrical equipment from the buildings prior to the “Notice to Proceed”.
C. The treatment plant tanks containing sewage shall be pumped out by a licensed Septic Tank Service
Company prior to demolition.
D. Dispose of all refuse at a State Approved facility.
E. Do not proceed with demolition until all erosion and sedimentation controls are in place and approved by the COR.
F. Use excess excavation from the new treatment plant foundation to fill old treatment plant pits and to re-grade area.
SECTION 02210
SITE GRADING
A. This section covers all required site grading, including excavation and the placement of interior and exterior fills and the final dressing of the site within the construction area.
PART 2 - PRODUCTS
A. Fill Material
1. The material for the interior and exterior fills shall consist of surplus excavated material or imported fill consisting of a mixture of soil, gravel talus rock, disintegrated granite, semi-gravel, sand, caliche, shale, scoria, clinkers, cinders, or other suitable material.
2. The material shall be free from organic vegetative matter.
3. The maximum size of any particle shall not be greater than 3" in diameter.
4. Oversize material may either be removed or broken down to the specified dimension by any method which accomplishes reduction to that size.
5. The removal or the breakdown of oversize material to the specified size shall be done at the material source.
B. Bedding material under concrete slabs shall be NC DOT approved ABC stone.
PART 3 - EXECUTION
A. The Contractor shall supply all fill material.
B. Excavation shall produce surfaces to line and grade shown on drawings. All excavated areas shall drain.
C. The root structure of all existing trees that are to remain shall not be disturbed. Do not operate heavy equipment within 10' of trees that are to remain.
D. Exterior fills shall be constructed to sections and elevations indicated. Exterior fills shall drain.
E. Compact Earth Fills under all concrete slabs, ramps, and footings.
1. Compaction shall be in accordance with Section 02250, Compaction Control and Testing.
F. When all exterior earthwork is completed, the Contractor shall give the entire site a final dressing to assure that all surfaces are in accordance with the elevations indicated on the drawings.
1. Finish grades adjacent to the building shall be sloped as shown on the drawings to provide surface drainage away from the building walls in all directions.
SECTION 02220
STRUCTURAL EXCAVATION
A. This section consists of the necessary excavation for the buildings, treatment plant, and wetwell foundations and other structures.
PART 2 - PRODUCTS
A. Silt fence in accordance with Section 02540.
B. NC DOT approved #57 Stone.
C. MIRAFI 140 NL filter fabric.
A. Install silt fences or other means of silt entrapment around all structural excavations.
B. Trenches or foundation pits for structures or structure footings shall be excavated to the lines, grades, and elevations as shown on the drawings. They shall be of size to permit the placing of the full width and length of structure footings or tanks as shown on the drawings.
C. Boulders, logs, or other objectional material encountered in excavation shall be removed.
1. All rock or other hard foundation material shall be cleaned of all loose material, cut to a firm surface, either level, and stepped or serrated as shown on plans or specified herein.
2. All seams or crevices shall be cleaned out and grouted with neat cement grout.
3. All loose, disintegrated rock and thin strata shall be removed.
4. When concrete is to rest on a surface other than rock, special care shall be taken not to disturb the bottom of the excavation.
D. After each excavation is completed, the Contractor shall notify the C.O. to that effect. No concrete shall be placed until after the C.O. has approved the depth of the excavation and the character of the foundation material.
SECTION 02221
TRENCHING, BACKFILLING, AND COMPACTING FOR UTILITIES
A. Work included in this section covers all trenching, backfilling, and compacting for the installation of all utility lines.
PART 2 - PRODUCTS
A. Initial Backfill - imported sand.
B. Subsequent Backfill - excavated material free from rock larger than four inches in greatest dimension, clods, and debris.
C. Plastic identification tape shall be Aluminum foil core sandwished between two layers of polyester with a total thickness of 0.005 inch. Text color shall be black and background colors as follows: Electric:
Red, Sewer: Green, Water: Blue, Cable TV: Orange, Natural Gas: Yellow, Telephone: Orange. The tape shall be as manufactured by:
Brady Corporation 6555 W. Good Hope Road Milwaukee, WI 53223 Tel. 1-800-448-8630 or approved equal. All buried utilities shall be identified with appropriate tape.
PART 3 - EXECUTION
A. Trenches shall be excavated through any or all materials regardless of natural substances.
1. A firm, full-length support shall be formed for all underground pipe.
2. If the bottom of any excavation is taken out beyond the elevations shown on the plans, it shall be refilled at the Contractor's expense with initial backfill material compacted to the density of adjacent undisturbed material.
3. Where the excavated material is rock or other unsatisfactory bedding material, the trench shall be excavated below the final grade of the pipe invert a distance of four inches. The trench shall then be backfilled to the grade of the pipe with initial backfill material.
4. The Contractor shall take all precautions to assure that water does not accumulate in trenches while utility lines are being constructed.
5. Any pipe damaged by backfill operations shall be replaced by new pipe.
6. Trenches shall be bedded to the proper elevation for installing the pipe with initial backfill material. All backfill material within six inches of pipe shall be initial backfill material.
7. Initial backfill shall be deposited and compacted to a density equal to or greater than that of the existing soils for all piping. Subsequent backfilling shall not be compacted except for areas within roadways, parking or sidewalks.
8. Compaction shall be accomplished by the use of a mechanical vibrating tamper.
9. All trenches not within roadway areas shall be mounded 4 to 6 inches to allow for settlement.
10. Bury ID Tape 6 inches below ground level. Follow tape manufacturer’s instructions.
B. Backfilling shall not be performed on any section of pipeline without prior approval by the C.O..
C. Areas where utility lines are located within roads, camping sites, or trails shall be dressed and graded to a condition similiar to one prior to the installation of the utility. Restore all drainage structures.
SECTION 02250
COMPACTION CONTROL AND TESTING
A. This section covers all compaction for earth fills under building footings, ramps, slabs, walkways, utility tanks, and other backfill as shown on the drawings and specified herein.
B. Compaction testing shall not be required.
PART 2 - PRODUCTS
A. Material used for fills and backfills shall be as described in Section 02210, Site Grading, and Section 02220 Structural Excavation.
PART 3 - EXECUTION
A. The ground on which the fill or backfill material is to be placed shall be firm, dry, unfrozen, and cleared of all debris.
B. Compacted earth fills under concrete slabs, ramps, footings, and walkways shall be placed in approximately 12" loose lifts and be compacted until all visual settlement ceases.
C. Backfill around structures and supports shall be done in 12" lifts and compacted to a uniform density until no visible settlement occurs.
D. Compaction shall be accomplished by the use of a mechanical compaction equipment.
SECTION 02400
SHEETING, SHORING, AND BRACING
PART 1 - GENERAL
A. Scope: Includes additional support that the sides of a trench or excavation may require to remain stable during construction operations.
PART 2 - PRODUCTS
A. Timber or metal members used by the Contractor shall provide adequate support of the soils during his work. The Contractor shall be responsible for selection of proper materials to maintain adequate support.
A. Excavations and sides of trenches shall be supported with adequate materials as necessary for the safety of personnel and protection of the pipeline or sewerage tanks before backfilling.
B. The installation and removal of all lagging, sheeting, shoring, piling, and bracing shall be such to maintain the required trench or excavated section and to maintain the undisturbed state of the soils at and below the bottom of excavation.
C. Sheet piling and timbers in trench excavations shall be withdrawn in a manner to prevent damage to the pipe or tanks.
D. All sheeting and shoring shall be removed when safe to do so.
SECTION 02530
DEWATERING
A. Scope: Includes requirements for removing water from excavations and trenches and protecting excavated areas from damage by water.
PART 2 – PRODUCTS
A. Pumped groundwater or storm runoff shall be ponded before discharge to any live stream.
PART 3 – EXECUTION
A. The Contractor shall furnish, install, and operate all necessary equipment to keep excavations and trenches free from water during construction; and shall dispose of water without causing damage to public or private property or causing a nuisance to the public.
B. Peculiar or unusual groundwater conditions revealed upon excavation shall be called to the attention of the C.O. before corrective measures are taken.
C. Control of groundwater shall be such that softening of the bottom of excavations or formation of quick conditions or boils shall be prevented. Dewatering systems shall be designed and operated to prevent removal of the natural soils.
D. During installation of pipelines and sewers, excavation shall be kept free of water. The static water level shall be drawn down below the bottom of the excavation to maintain the undisturbed state of the natural soils and allow the placement of backfill to the required density. The dewatering system shall be operated so the groundwater level outside excavation is not reduced to an extent that would damage or endanger adjacent structures or property.
E. The release of groundwater to its static level shall be performed in a manner to maintain the undisturbed state of the natural foundation soils, prevent disturbance of compacted backfill, and prevent flotation or movement of structures, pipelines, and sewers.
F. Ditch lines shall be excavated to protect trenches from surface runoff at all times. Daylight all trenches left open where feasible.
SECTION 02540
EROSION AND SEDIMENTATION CONTROL
A. This work consists of temporary and permanent measures as shown on the drawings and as specified herein, to prevent and control soil erosion and sedimentation.
B. Related Specifications:
1. 02821 – Seeding
A. Silt fences shall be prefabricated with 1-1/2" square, hardwood posts, Mirafi Silt Fence, or approved equal.
B. Standard size hay bales with 2x2 anchoring stakes.
A. Prior to the start of construction, the Contractor shall submit to the C.O. for approval, a schedule for temporary and permanent control work for each phase of work.
B. The Contractor shall monitor the performance of all erosion and sediment control practices and make minor adjustments as needed on a day-to-day basis. Silt fences shall be inspected after each rainfall and sediments deposits must be removed when they reach a maximum of 1/3 the height of the fence.
Deteriorated or damaged fabrics must be replaced immediately.
C. Temporary controls shall be dismantled and disposed of after the disturbed soil has been re-vegetated.
SECTION 02600
PAVEMENT REPAIR, REMOVAL AND REPLACEMENT
A. This section includes repair, removal and replacement of asphalt pavement to the extent required to construct the work shown on the drawings.
A. Backfill shall meet the requirements of Section 02210
B. Replace pavement with material equal in all respects to that removed, but in no case less than 6” of NCDOT ABC stone and 2 inches of Asphalt Concrete Surface Course Type S 9.5B.
A. Place backfill in 12” layers and compact with a mechanical tamper.
B. Saw cut pavement to a neat line prior to removal and backfilling. Keep amount of pavement removed to a minimum.
C. Restore pavement to match existing pavement.
SECTION 02720
AGGREGATE BASE
PART 1 GENERAL
A. WORK INCLUDED
1. This item shall consist of furnishing, hauling, and placing one or more courses of aggregate on an approved sub grade or base.
PART 2 PRODUCTS
A. AGGREGATE
1. Aggregate base course shall be NC DOT approved ABC.
2. The commercial source shall provide a statement from a certified testing facility stating that aggregate from this source meets the requirements of these specifications and the designated gradation.
PART 3 EXECUTION
A. HANDLING & STORAGE
1. Aggregate shall be handled in such a manner as to minimize segregation.
2. Any method of stockpiling aggregate which allows the stockpile to become contaminated with foreign matter or causes excessive degradation of the aggregate shall not be permitted.
B. PREPARATION
1. The sub grade shall conform to the grades and lines shown on the drawings and shall be approved in writing by the COR before placing the base course.
C. MIXING & PLACING
1. Water shall be added to the aggregate in an amount necessary to provide a moisture content suitable for compaction. The moisture content of the aggregate shall be uniform throughout.
2. The aggregate shall be spread in a uniform layer, with no segregation of size, and to a loose depth that shall have the required thickness when compacted. If the required compacted depth of any aggregate base or surface course exceeds 6 inches, it shall be placed in two or more layers of approximate equal thickness.
3. Hauling equipment shall be dispersed over the surface of the previously constructed layer to minimize rutting or uneven compaction.
The surface of each layer shall be bladed during the compaction operations to remove irregularities and produce a smooth even surface that will drain.
4. The thickness of the compacted base shall not vary more than 1/2 inch from the required thickness shown on the drawings. The compacted thickness shall not be consistently below the specified thickness.
5. The aggregate shall be compacted with construction equipment until no visual displacement occurs.
SECTION 02821
SEEDING, FERTILIZING, AND MULCHING
A. This section covers the seeding of all disturbed areas within the construction limits. The work shall include fine grading of the areas, soil preparation, and application of lime, fertilizer, seed, and mulch.
PART 2 PRODUCTS
A. Fertilizers shall be spread on the ground surface at the following rates.
Grade 18/46/0 600 lb/acre
B. Seed shall be spread on the ground surface in the following amounts.
Winter 90 lbs/acre
C. All dates shown are guidelines. If weather conditions are abnormal, the CO shall consult with
Forest Service Soil Scientist and/or Botanist for additional seeding times.
Permanent Seeding – Spring (2/1 to 5/1):
Fungus Free Tall Fescue (Kentucky 31 is not acceptable): 20 lbs/acre Virginia Wild Rye: 10 lbs/acre Creeping Red Fescue: 6 lbs/acre Red Clover: 12 lbs/acre Rye (cereal small grain): 30 lbs/acre
Permanent Seeding – Summer (5/1 to 8/1):
Creeping Red Fescue: 10 lbs/acre Little Bluestem: 10 lbs/acre Indian Grass: 10 lbs/acre Partridge Pea: 6 lbs/acre
Temporary Seeding:
Foxtail (German) Millet: 30 lbs/acre Partridge Pea: 5 lbs/acre
D. Assure that mulch used on the project is certified noxious weed free by the appropriate authority in the jurisdiction of use.
E. Moisten seeding areas before seeding and maintain the moisture until 3 days after germination.
F. Apply fertilizer by the following methods:
1. Dry method. Incorporate the fertilizer into the upper portion of the seedbed before seeding.
2. Apply seed and fertilizer at rates specified.
3. Apply seed by the following methods:
a. Dry method. Apply the seed with approved power driven seeders, drills, or other mechanical equipment. Hand-operated seeding methods are satisfactory on areas inaccessible to mechanical equipment.
4. Apply mulch within 48 hours after seeding by the following methods:
a. Dry method. Spread all mulch material, except wood and grass cellulose fibers, by a mulch spreader utilizing forced air to blow the mulch material onto the seeded area. Apply straw mulch at designated rate. Anchor the mulch material with an approved stabilizing emulsion tackifier or approved mechanical method. Do not mark or deface structures, pavements, utilities, or plant growth with tackifier. Apply wood fiber or grass straw cellulose fiber mulch at the designated rate. Apply bonded fiber matrix hydraulic mulch at the designated minimum rate. Apply so no hole in the matrix is greater than 0.04 inches. Apply so that no gaps exist between the matrix and the soil.
b. Mulch by hand areas inaccessible to mulching equipment.
5. Protect and care for seeded areas including watering when needed until final acceptance.
Repair all damage to seeded areas by reseeding, refertilizing, and remulching. Apply supplemental applications of seed, mulch, fertilizer, lime, or ammonium nitrate.
A. Seeding operations shall be carried out in a timely manner following any and all backfill completion as directed by the COR.
B. All disturbed areas to be seeded shall be graded, leveled, and prepared to receive the grass seed.
C. Application of Lime and Fertilizer - following the grading and leveling operation, lime and fertilizer shall be spread uniformly over the area to be seeded.
D. Seed shall be uniformly sown over the area at the rate specified by hand sowing. The Contractor may use a hydro-seeding method if approved by the COR.
E. Pine straw or hay shall be uniformly spread over the area at the rate specified.
SECTION 02822
CHAIN - LINK FENCES AND GATES
1.01
WORK INCLUDED
A. Fence framework, fabric and accessories.
B. Gates and related hardware
C. Installation
1.02
SCOPE OF WORK
A. Summary: This section covers the work necessary to complete the chain link fence and gate installation.
B. Delivery, Storage, and Handling: deliver material to the site in an undamaged condition. Carefully store material off the ground to provide proper protection against oxidation caused by ground moisture.
1.03
SUBMITTALS, CERTIFICATION, GUARANTEE AND INSPECTION
A. Shop Drawings: Include complete details of fence and gate construction, fence height, post spacing, dimensions, unit weights of framework and footing details.
B. Product Data: Provide manufacturer’s catalog cutes with printed specifications. Manufacturer shall provide certification of compliance with material specifications.
2.01
MATERIAL
A. Pipe shall be straight, true to section and conform to the following weights:
Pipe Size O.D. Weight lbs/ft.
1 - 7/8” 2.01 2 - 3/8” 2.78
C. Fabric:
1. Aluminized fabric shall be manufactured in accordance with ASTM A 491 and coated before weaving with a minimim of 0.4 ounces of aluminum per square foot of surface area. The steel wire shall conform to ASTM A817. Fabirc to be 9 gauge woven in a 2” diamond mesh. Top and bottom selvage to be knuckled unless otherwise specified.
OR
2. Zinc-coated fabric shall be galvanized after weaving with a minimum 1.2 ounces of zinc per square foot of surface area and conform to ASTM A 392, Class 1. Fabric to be 9 gauge wire woven in a 2” diamond mesh. Top selvage and bottom selvage to be knuckled unless otherwise specified.
2.02 COMPONENTS
A. Fence Posts:
B. Swing Gate Posts:
Width Double Gate
Post O.D.
12’
2-7/8”
C. Rails and Braces: 1-5/8” O.D. Group IA or IV
D. Gates: Per ASTM F900 with frame assembly of 1-7/8” O.D. Pipe Group IA or IV with welded joints.
Weld areas are repaired with zinc-rich coating applied per manufacturer’s direction. Fabric is to match fence. Gate accessories, hinges, latches, center stops, keepers an necessary hardware of qulaity required for industrial and commercial application. Latches shall permit padlocking. Vinyl coated system to have pressed steel corner fittings securely rivited to the frame.
E. Fittings: All fittings conform to ASTM F 626
Post Caps – Pressed steel, cast iron or aluminum alloy designed to fit snugly over posts to exclude moisture. Supply dome style caps for terminal posts and loop type for line post.
Rail Brace Ends – Pressed steel, cast iron or cast aluminum alloy, cup-shaped to receive rail and brace ends.
Top Rail Sleeves – Tubular steel, 0.051 thickness x 6” long, expansion type.
Tension Bars – Pressed steel, 14 gauge thickness x ¾ “ wide.
Brace Bands – Pressed steel, 12 gauge thickness x ¾ “ wide.
Truss Rods – Steel rod, 5/16” diameter merchant quality with turnbuckle (take up).
Barbed Wire-Arms – Pressed steel, cast iron or cast aluminum alloy fitted with clips or slots for attaching three strands of barbed wire. Arms shall be set outward on a 45-degree angle and be capable of supporting a 250-pound load at outer barbed wire connecting point without causing permanent deflection.
F. Tension Wire – Marcelled 7 gauge steel wire, galvanized or aluminized per ASTM A 817 and A 824.
G. Tie Wires: As per ASTM F 626 Aluminum, 9 gauge, alloy 1100-H4 or equal.
H. Hog Rings: Steel wire, 12 gauge, with a minimum zinc coating of 0.80 ounces per square foot of wire surface or 9 gauge aluminum per ASTM F 626.
I. Barbed Wire: Commercial quality steel, 12-1/2 gauge, two strand twisted line wire with 4 point barbs at 5 inch spacing. Coating shall consist of a minimum of 0.80 ounces of zinc per square foot of wire surface conforming to ASTM A 121 or a minimum of 0.30 ounces of aluminum per square foot of wire surface conforming to ASTM A 585.
Fabric Line Post Terminal Post Height O.D.
O.D.
6 ft.
1-7/8” 2-3/8”
3.01
INSTALLATION
A. General: installation to conform to ASTM F567.
B. Height; Provide height as indicated on contract drawings.
C. Post Spacings: Space line posts at intervals not exceeding ten feet or as shown on plans.
D. Post Settings: Set terminal, gate and line posts plumb. Depth to be a minimum of 36”. Backfill line posts holes with excavated material and hand tamp. Terminal posts (corners & gate) shall be encased in concrete.
E. Bracing: Brace gate and terminal posts back to adjacent posts with 1-5/8” O.D. horizonal brace rails and 5/16” O.D. galvanized, diagonal, adjustable truss rods.
F. Top Rail: Install through line loop caps connecting sections with sleeves to form a continuous rail between terminal posts. No section to be longer than 21’.
G. Bottom and Mid Rails: Not required.
H. Bottom Tension Wire: if required stretch between terminal posts 6” above grade and fasten to outside of line posts with wire ties.
I. Fabric: Pull fabric taut with bottom selvage 2” above grade. Fasten to terminal posts with tension bars threaded through mesh and secured with tension bands at maximum 15” intervals. Tie to line posts and top rails with tie wires spaced at maximum 12” on posts and 24” on rails. Attach to bottom tension wire with hog rings at maximum 24” intervals.
J. Barbed Wire: Anchor to terminal extension arms, pull taut, and firmly install in slots of line post extension arms. Barbed ratchets or brace bands to be used on end posts.
K. Gates: Install gate plumb, level and secure or full opening with out interference. Anchor center stops and hold open keepers in concrete. Gates to be capable of 90 degree swing.
L. Fasteners: Install nuts for fittings, bands, and hardware bolts on inside of fence.
DIVISION 3 - CONCRETE
03100 - Concrete Formwork 03200 - Concrete Reinforcement 03300 - Cast-in-Place Concrete 03310 - Concrete from Packaged Dry Mix for Minor Structures
SECTION 03100
CONCRETE FORMWORK
A. This section covers all formwork, expansion joints, and related accessories.
PART 2 - PRODUCTS
A. Forms shall be wood, plywood, hardboard, or metal and shall be approved by the C.O..
B. Form oil shall be nonstaining type.
C. Expansion joint filler shall be pressure treated Southern Yellow Pine boards. Treatment shall be
0.21bs/cf of treatment (ground contact).
PART 3 - EXECUTION
A. Forms shall be built tight, in proper alignment and adequate to resist the stresses of concrete placement without deformation.
B. Forms shall be constructed to produce the required concrete surface.
C. Expansion and contraction joints shall be formed as indicated on the drawings.
D. Control joints shall be saw cut at the locations shown on the drawings. Joints shall be 1/5 the depth of the slab.
SECTION 03200
CONCRETE REINFORCEMENT
A. This section covers all concrete reinforcement and its accessories.
B. The latest editions of the following specifications and codes shall govern.
1. ACI 301, Specifications for Structural Concrete for Buildings.
2. ASTM A615
3. ASTM A185
PART 2 - PRODUCTS
A. Reinforcing steel shall comply with ASTM A615, intermediate grade 40, unless otherwise shown.
B. Reinforcing mesh shall comply with STM A185 and shall be gauge and mesh indicated.
PART 3 - EXECUTION
A. Reinforcement bars and mesh shall conform to the sizes and spacings as shown.
B. Field bending and cutting will be permitted if performed in accordance with above listed code.
C. Reinforcement shall be free from dirt, oil, paint, grease, mill scale, and loose or thick rust when concrete is placed.
D. Woven wire mesh shall be hooked and/or supported during the placement of concrete slabs to ensure proper embedment as detailed.
E. Anchorage and accessories shall be accurately placed as shown and held rigidly in position during placing of concrete.
F. Depth of cover, radius of bends, and deformations shall be in accordance with ACI 318.
SECTION 03300
CAST-IN-PLACE CONCRETE
A. This section covers cast-in-place concrete, including curing and finishing of concrete.
B. The latest editions of the following specifications and recommended practices shall govern:
1. ACI 301 - Specifications for Structural Concrete for Buildings.
2. ACI 306 - Recommended Practice for Winter Concrete
3. ACI 305 - Recommended Practice for Hot Weather Concrete
C. Notify C.O. 48 hours prior to placing concrete.
PART 2 - PRODUCTS
A. Aggregate shall conform to the requirements of Federal Specification SS-A-281, Classes 1 and 2, and shall be well graded from fine to coarse within designated limits.
B. Portland, Cement, shall comply with ASTM C150, Type 1. Supplier shall provide mill certification of compliance with specification.
C. Water shall be clean, fresh, and free from injurious amounts of minerals or foreign substances.
D. Additives, air entrainment agents shall comply with ASTM C-260.
E. Concrete Mix Design
1. All concrete shall have a minimum "compressive strength" of 3000 psi at 28 days.
2. Concrete shall be air-entrained and shall contain not less than 3% and not more than 6% entrained air determined by test procedure AASHTO T 152.
3. The design of the concrete mixture shall be the responsibility of the Contractor.
F. Slump shall not exceed 3 inches for vibrated concrete or 5 inches for non-vibrated concrete.
PART 3 - EXECUTION
A. "Ready-Mixed Concrete" may be employed if the time interval between mixing at the plant and discharge into the form does not exceed 1-1/2 hours.
B. All concrete shall be placed within 1-1/2 hours from the time of mixing.
1. No concrete shall be placed after it has started its initial set.
2. No concrete with a temperature above 90ºF shall be placed.
C. Concrete shall be placed in such a manner as to avoid segregation of the mixture.
1. Concrete shall be spread in horizontal layers when practicable.
2. No concrete shall be freely dropped more than 5 feet.
3. Depositing a large quantity of concrete and flowing or working it along the forms will not be permitted.
D. Mechanical vibrators shall be used for consolidation of concrete.
1. Concrete shall be consolidated within 15 minutes after placement.
2. If consolidation of concrete with mechanical vibrators is impractical, hand tamping, rodding, and spading will be permitted.
3. A minimum of two vibrators, in working order, shall be on the job during concrete placement.
E. Concrete shall be placed and protected as specified for temperature conditions.
F. Concrete plant standards and truck mixer and agitator standards shall be as recommended by the
National Ready Mix Association.
G. Finishing
1. All finishes shall be made without use of cement or other dusting materials.
2. Concrete shall be struck to proper grade and surface finished with float trowels.
3. At all exposed form surfaces, remove all ties, fill all form tie holes and imperfections (i.e., "honeycombing") with dry cement mortar, remove all lines, and then "sack" or finish to match adjacent surfaces.
4. Interior floors shall be steel trowel finished. Slope all interior floors to positively slope towards the drains.
5. Exterior sidewalks shall be light broom finished.
H. Concrete shall be protected against rapid drying and kept moist for seven days by covering with curing paper with edges sealed.
I. Sampling and Testing
1. Sampling and testing shall be the responsibility of the Contractor, through an approved Testing
Laboratory. The Contractor shall test for strength, air content and slump.
2. Sampling and testing shall be done in accordance with the following test methods:
--Sampling Fresh Concrete....................................AASHTO T-141 --Making and Curing Concrete Compression Test Specimens.............................AASHTO T-23 --Compressive Strength of Concrete Cylinders.....AASHTO T-22 --Percent Entrained Air (Pressure Method)...........AASHTO T-152 --Consistency (Slump) of Concrete.......................AASHTO T-119
3. Testing frequency shall be one sample or test per every 10 c.y. or truck load.
1. Submit copy of test results to Contracting Officer.
2. Sampling and Testing applies to building foundations and slabs only.
SECTION 03310
CONCRETE FROM PACKAGED DRY MIX FOR MINOR STRUCTURES
A. Consists of constructing small concrete structures requiring one-half cubic yard or less in accordance with the details shown on the drawings and in conformance with the requirements of this specification.
A. Forms: Plywood, hardboard, wood, metal or other approved material to yield the required finish.
B. Dry Mix: The prebagged concrete mix shall be made using a dry preportioned blended mix meeting the requirements of ASTM C-387 for 28 days, 3,500 psi concrete.
C. Water: Water shall be clean and free from alkali and other deleterious materials. Water shall be added to each bag as recommended by the manufacturer.
D. Welded Wire Fabric: AASHTO M-32 and M-55.
PART 3 - EXECUTION
A. Job Mixing: The dry concrete mix and water shall be thoroughly mixed as recommended by the manufacturer. Mixing must be done in either a mechanical mixer or in a wheelbarrow. Concrete shall be mixed and placed while fresh. Any concrete in which initial set has begun shall be wasted. In any case, the elapsed time from placement of the first batch to placement of the last batch necessary to complete a specific concrete item shall not exceed one hour.
B. Placing and Finishing: The fresh concrete shall be placed in the forms and rodded as necessary to remove the air pockets. The exposed surfaces of the concrete shall receive a medium trowel finish.
C. Protection from Cold: The Contractor shall ensure that the air surrounding the fresh concrete be kept at a temperature above 50 degrees F for a period of five days after the concrete is placed.
D. Curing: If determined necessary by the C.O., exposed surfaces shall be covered with plastic sheeting after the concrete has taken its initial set.
DIVISION 4 - MASONRY
04150 - Masonry Accessories 04220 - Concrete Unit Masonry 04410 - Stone Masonry
SECTION 04150
MASONRY ACCESSORIES
A. This section covers all masonry accessories as shown on the drawings and as specified herein.
PART 2 - PRODUCTS
A. Vertical and horizontal reinforcing steel shall be of sizes and configuration shown on drawings.
1. Reinforcing steel shall comply with ASTM Designation A-615, intermediate grade 40.
B. Horizontal joint reinforcement shall be Dur-O-Wall, conforming to requirements of ASTM A-82.
1. 8" concrete block - #8 Dur-O-Wall Truss.
2. 6” concrete block - #6 Dur-O-Wall Truss.
3. 4" concrete block - #4 Dur-O-Wall Truss.
C. Anchor bolts shall be of the size and type shown on the drawings.
PART 3 - EXECUTION
A. Reinforcing steel shall be installed as shown on the drawings. All concrete block cells containing reinforcing steel shall be filled solid with concrete.
B. Horizontal masonry reinforcement shall be installed in accordance with manufacturer's recommendations.
SECTION 04220
CONCRETE MASONRY UNIT
A. Work included in this section covers concrete block masonry and related items.
B. References
1. Standards of the Concrete Masonry Association, latest edition.
2. Concrete Masonry Handbook, Portland Cement Association
PART 2 - PRODUCTS
A. Mortar shall comply with ASTM C-270, Type M.
B. Concrete Masonry Units shall be stream-cured hollow loadbearing units meeting
ASTM C-90.
1. Faces shall be uniform in texture and free of defects which would impair finished appearance.
2. Units shall not vary from designated size more than 1/6".
3. Typical units 7-5/8" high x 15-5/8" long x 3-5/8”, 5-5/8”, and 7-5/8" wide, two or three cell type.
4. All blocks shall be Grade A units made with expanded slag or shale aggregate.
A. All masonry walls shall be true and plumb and built to dimensions, bond, and pattern as indicated on the drawings.
1. Joints shall be 3/8" wide.
B. Provide all bond beams and special blocks where required or shown on the drawings.
C. Cores that contain vertical reinforcing steel shall be cleaned through the top of the cell by hand and filled with concrete.
1. The concrete shall be vibrated or rodded.
D. Reinforcing bars shall be installed in the cores and bond beams and anchored into concrete as shown on the drawings.
1. Cores with reinforcing steel and bond beams shall be filled with concrete.
E. All blocks shall be "buttered" on all contact surfaces with mortar.
1. Tight full mortar joints shall be placed between concrete and masonry.
2. There shall be full mortar coverage of the block face shells in both horizontal and vertical joints.
F. All exposed wall surfaces shall be kept clean and free of mortar or concrete splotches.
1. Wall and all joints shall be pointed and masonry cleaned.
2. Completed walls shall be cleaned with a detergent cleaner containing no muriatic acid.
G. No placing of masonry shall be done in freezing weather (below 40 degrees F.) unless a heated tent is placed over the entire structure and kept for a minimum of 2 days after finishing laying block
H. I n hot or dry weather, the masonry shall be protected from the sun and shall be kept wet for a period of three days after completion.
SECTION 04410
STONE MASONRY
A. General
1. This section shall consist of furnishing and installing all stone masonry as called for on the plans or specified herein. The masonry shall be constructed on the prepared foundation in accordance with these specifications and in conformity with the lines, grade, sections, and dimensions shown on the drawings.
PART 2 - MATERIALS
A. Field Stone shall be 1½ to 2½ inches thick, “Tennessee” Field Stone (8-Unit Bath-house).
B. Rock veneer to match existing wellhouse.
PART 3 - EXECUTION
A. Prior to commencing stone work, the Contractor shall confer with the C.O. and shall erect a small sample wall approximately 4'0" long x 3'0" high for the C.O.'s approval as to color, size, texture, joints, and pattern. This work shall not be a part of the structure, and the final approved sample shall remain in place until the structure is completed and accepted at which time it shall be torn down and removed from site.
B. Schedule deliveries to avoid delays and to greater accumulations than can be suitably stored at site.
C. Store stone on wood supports clear of ground. Protect edges and exposed faces from damage and from staining. Stack stone in same position as intended position in finished work.
D. Arrange storage in approximate order of use to avoid excessive rehandling.
E. Mortar
1. Non-staining Cement: (Approved by C.O.)
2. Fine Aggregate: ASTM C 144, natural, pass 6 mesh screen. Sand for pointing mortar, pass No.
12 sieve.
3. Water: Potable quality
4. Hydrate Lime: ASTM C 207, Type S.
F. Workmanship
1. Placing Stone
When the masonry is to be placed on a prepared foundation bed, the bed shall be firm and normal to, or in steps normal to, the face of the wall before any stone is placed. When it is to be placed on foundation masonry, the bearing surface of this masonry shall be cleaned thoroughly and wetted immediately before the mortar bed is spread.
All masonry shall be constructed by qualified Masons with a minimum of 5 years experience.
Care shall be taken to prevent the bunching of small stones or stones of the same size. Large stones shall be used for the bottom courses and the number of large selected stones shall decrease in the corners. In general, the stones shall decrease in size from the bottom of the top of work.
All stones shall be cleaned thoroughly and wetted immediately before being set, and the bed which is to receive them shall be cleaned and moistened before the mortar is spread. They shall be laid with their longest faces horizontal in full beds of mortar, and the joints shall be flushed with mortar. The exposed faces of individual stones shall be parallel to the faces of the walls in which the stones are set.
At least 80% of the face area of the finished wall shall consist of stones laid on a horizontal bed so that a stable and horizontal appearance results. Stones shall be laid in a full bed of mortar.
Care shall be exercised to keep exposed faces free of mortar. The maximum and minimum projections of rock faces beyond the surface plane shall not vary from each other by more than 2 inches.
The stones shall be so handled as not to jar or displace the stones already set. Suitable equipment shall be provided for setting stones larger than those that can be handled by two men.
The rolling or turning of stones on the wall will not be permitted. If a stone is loosened after the mortar has taken initial set, it shall be removed, the mortar cleaned off, and the stone relaid with fresh mortar.
2. Bed and Joints
Bed surfaces of face stone shall be approximately normal to the faces of the stones for about 2 inches and from this point may depart from a normal plane not to exceed 2 inches in 12 inches.
Beds for face stone may vary from 1/2 to 2-1/2 inches in thickness. They shall not extend in an unbroken line thru more than five stones. Joints may vary from 1/2 to 2-1/2 inches in thickness.
They may be at angles with the vertical from 0 to 45 degrees. Face stone shall bond at least 6 inches longitudinally and 2 inches vertically. At no place shall corners of four stones be adjacent to each other. The stone shall be hammer dressed to remove any thin or weak portions. Face stones shall be dressed to provide bed and joint lines that do not vary more than 1-1/2 inches from true lines and to insure the meeting of bed and joint lines without the rounding of the corners of the stones in excess of 1-1/2 inches in radius.
3. Headers at Corners
Headers shall be distributed uniformly throughout the walls of structures so as to form at least one-fifth of the exposed faces. They shall be of such lengths as to extend from the front face of the wall into the backing at least 12 inches. When a wall is 18 inches in thickness, the headers shall extend entirely thru from front to back face.
4. Pointing
Both bed and vertical joints shall be filled with mortar and struck off with a rounded wooden tool so as to leave a round depression in the mortar from one-half to three fourths of an inch in width and from one-fourth to three-eights of an inch in depth.
5. Coping
Copings, if called for, shall be as shown on the plans. Where copings are not called for, the top of the wall shall be furnished with stones wide enough to cover the top of the wall. Stone shall be laid in such a manner that the top course is an integral part of the wall.
6. Weather Limitations
No placing of stone shall be done in freezing weather except by written permission from the C.O.
and then only by the use of such methods as he may prescribe fro preparing the materials and protecting the work after laying. Such permission and the use of the methods prescribe shall not, however, release the Contractor from his obligation to build a satisfactory structure. All work damaged by cold weather shall be removed and replaced. In hot or dry weather the masonry shall be satisfactorily protected from the sun and shall be kept wet for a period of at least three days after completion.
DIVISION 5 - METALS
05500 - Metal Fabrications
SECTION 05500
METAL FABRICATIONS
A. Work in this item includes all structural and miscellaneous metal and other related items.
PART 2 - PRODUCTS
A. I-beams, posts, steel straps, steel angles and other miscellaneous steel shall conform to
ASTM A-36.
B. Block vents shall be as shown on the drawings.
C. Metal primer shall be PRO-CRYL Universal Acrylic Primer by Sherwin Williams.
D. Finish coat shall be PRO INDUSTRIAL Industrial Enamel 100 by Sherwin Williams.
PART 3 - EXECUTION
A. The Contractor shall provide all framing and falsework necessary for the erection.
B. At final attachment, all miscellaneous metal and other items shall be rigid and secure.
C. After erection, touch up field connections and abraded places on all steel with shop paint.
D. All black steel items shall be shop primed. Finish coat on exposed steel shall be as specified on the
E. Apply two finish coats of industrial enamel to the pipe hangers.
DIVISION 6 - WOOD AND PLASTICS
06100 - Rough…