J2 - General Notes.doc
DOC document 37 KB Posted
- Solicitation number
- AG-4419-S-10-0476
About this file
J2 General Notes
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment1.pdf | ||
| J3 - Project Drawings.pdf | ||
| J5 - Vicinity Map.pdf | ||
| SF1442 Contractor to complete and return.rtf | RTF text file | |
| J4 - Road Log.doc | DOC document | |
| J7 - FR1797 Map.pdf | ||
| J10 - M174 M151 WR15 WR11 WR12 Map.pdf | ||
| J11 - DB Wage Determination.doc | DOC document | |
| sf24 bid bond form.pdf | ||
| AG-4419-S-10-0476.rtf | RTF text file | |
| J1 - Project Details.pdf | ||
| J8 - M154 Map.pdf | ||
| J9 - M176 Map.pdf |
Show all 13
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
General Notes FR1797 Road Decommission for Watershed Restoration (Upper Williams North)
CIM-0921-9R-984-0921-01
Governing Specifications
The Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-03, USDOT, shall be the governing specifications for this project. The contract documents, details and drawings are the governing provisions applicable to this project.
Project Areas
The project area is located in Pocahontas County, West Virginia approximately 8 miles northwest of Marlinton in the upper Williams River watershed. This contract involves prescribed road decommissioning and road storage treatments for the following roads on the Marlinton Ranger District of the Monongahela National Forest: FR1797, M-176, WR-15, M-151, M-174, WR-11, WR-12, M-154 and all intersecting skid roads.
Project Area Access
Forest Roads 86, 216, 461, 1796, and State Route 17/4 provide access to the project area. Any damages to Forest Service System roads resulting from equipment mobilization must be rehabilitated. Example: damage to existing road surfaces or drainage features must be repaired.
Base Bid and Optional Bid Items
This contract consists of a Base Bid and 1 Optional Bid Item. Contractors should bid on all items.
Bids should reflect the potential for this contract to be awarded for the Base Bid Item as a minimum award. The Optional Bid Item will be awarded as funding allows.
Other Contracts Contract work shall not interfere with or inhibit work on other contracts in the area.
Equipment Cleaning
Equipment and vehicles used during the project shall be free of soil, seeds, vegetative debris, or other matter that could contain seeds or plant parts when such equipment arrives on National Forest land. Any necessary cleaning of equipment and vehicles shall not be conducted on National Forest land.
Waste Sites
No waste sites have been identified for this project. Any excess material will be wasted along the road in conjunction with road obliteration activities.
Decompaction of Road Tread
Existing road tread will be decompacted to a minimum depth of 12 inches. This will be completed in areas of outslope, concave areas and decompaction only areas. The cost for this decompaction will be included in items 211.01(b)- Road Obliteration, and in 211- Decompaction.
Outsloping
In areas requiring outsloping, the road will be outsloped to the minimum slope specified (for example, 15%) by removing road fill material and placing it on the cut slope and inside portion of the road. This will be completed in a manner that results in a gradual transition between the newly established grade and the existing slopes immediately adjacent to the treated areas. Where the natural slope above and below the road corridor is less than the degree of outsloping prescribed for the road, the final outslope of the road shall match that of the natural grade. Roads segments with a full recontour prescription will require similar actions as other outsloping prescriptions except all the road fill material will be removed and placed on the cut slope to achieve a final slope the reflects the natural slope as much as possible. If material on site is not sufficient to obtain the prescribed degree of outsloping or full recontouring, the greatest degree of outsloping that can be attained with the material on site shall be sufficient. No additional material will be brought in to achieve the outslope prescription. Outsloping at the intersections of two or more roads will reflect a continuous outslope of the excavated intersection. Areas requiring a concave crossing are included in this item. Concave crossings will be constructed so that fill will be removed from the outside edge of the road, but will not be deposited on the inside edge, therefore achieving a depression across the entire road corridor. The excess material from concave crossings will be wasted along an adjacent outsloped area. See Project Drawings and Project Details for more information.
Channel Restoration Sites Channels and floodplain areas will be excavated to reflect and blend with more natural conditions found upstream and downstream from the road crossing. See Project Details and Project Drawings for appropriate channel dimensions. The cost for channel crossings will be included in item 211.01(b) of Road Obliteration actions such as Outsloping and Outsloping without Decompaction.
Stream Crossings Stream crossings are similar to channel restoration sites, in that they will be excavated to reflect and blend with more natural conditions found upstream and downstream from the road crossing. These are typically smaller than channel restoration sites, and therefore require less excavation. The location and width requirements for stream crossings are identified in the Project Drawings and the Road Log. The cost for stream crossings will be included in item 211.01(b) of Road Obliteration actions such as Outsloping and Outsloping without Decompaction.
Areas of No Excavation
In areas requiring no excavation, if ruts develop in the road bed during implementation of this project, they shall be removed. Ruts in this context shall be defined as extending deeper than 2 inches into the road bed and extending for greater than 40 feet.
Removal of Existing Drainage Structures Existing culverts will be removed from the project area and public land, and will become property of the contractor. The road log identifies the locations of culverts. The cost for removal shall be included in item 211.01(b) of Road Obliteration actions such as Outsloping and Outsloping without Decompaction.
Removal of Trees and Vegetation
All trees that need to be felled to facilitate road obliteration will be left on site. They will be evenly scattered throughout the final grade or in stream crossings, as directed by contract administrators. Trees will not be windrowed on the final grade. The contractor will make every effort to avoid disturbing larger trees. The cost for vegetation removal shall be included in item 211.01(b) of Road Obliteration actions such as Outsloping and Outsloping without Decompaction.
Sediment and Pollution Control Sediment runoff will be controlled at all stream and water crossings during travel to and from active work site. This may include temporary hay bale placement at outflows.
All equipment shall be equipped with a spill kit in case of fluid leaks or spills. This shall include fluid absorption pads. Any equipment leak or spill shall be reported to contract administrators as soon as possible.
Seeding and Mulching
All disturbed areas shall be seeded and mulched within 7 days of disturbance. Seeding and mulching must be done in a manner that does not leave ruts in or compact the finished grade. See project details for more information.
Barrier Rocks
Boulders will be placed in the locations identified in the Road Logs to help prevent motor vehicle access to roads being treated under this contract. Boulder placement may be directed by the designated contract administrator. Boulders will be approximately 4’ median diameter, be partially buried to inhibit their movement, and be positioned to effectively restrict motor vehicle access (including ATVs). Native rocks may be used if they are available on site and occur within the typical disturbance perimeter of other actions required by this contract.
Waste Materials
All trash in the project area, whether pre-existing or produced as a by-product of activities required in this contract, shall be removed from National Forest Systems lands and disposed of properly.
Final Grade The final grade of all excavated areas shall be bucket placed to eliminate the potential for soil compaction or rutted surfaces.
Utilities
It is the responsibility of the contractor to contact MISS UTILITY (1.800.245.4848) prior to beginning construction on this contact to determine the need for special precautions related to public utilities.