Amendment1.pdf

PDF 352 KB Posted

Attached to
Recovery - Road Decommissioning -Upper Williams North - Monongahela NF
Solicitation number
AG-4419-S-10-0476
Issued by

About this file

Amendment 1 with new bid schedule and minor changes to other solicitation documents. Please acknowledge with your bid.

View the file

Other files

File Type Posted
J2 - General Notes.doc DOC document
J3 - Project Drawings.pdf PDF
J5 - Vicinity Map.pdf PDF
SF1442 Contractor to complete and return.rtf RTF text file
J4 - Road Log.doc DOC document
J7 - FR1797 Map.pdf PDF
J10 - M174 M151 WR15 WR11 WR12 Map.pdf PDF
J11 - DB Wage Determination.doc DOC document
sf24 bid bond form.pdf PDF
AG-4419-S-10-0476.rtf RTF text file
J1 - Project Details.pdf PDF
J8 - M154 Map.pdf PDF
J9 - M176 Map.pdf PDF
Show all 13

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

AMENDMENT OF SOLICITATION/MODIFICATION OF CONTRACT

1. CONTRACT ID CODE PAGE OF PAGES

1 1

2. AMENDMENT/MODIFICATION NO. 3. EFFECTIVE DATE 4. REQUISITION/PURCHASE REQ. NO. 5. PROJECT NO. (If applicable)

1 04/30/2010

6. ISSUED BY CODE 7. ADMINISTERED BY (If other than Item 6) CODE

North East Acquisition Team Allegheny National Forest 4 Farm Colony Drive Warren, PA 16365

8. NAME AND ADDRESS OF CONTRACTOR (No., street, county, State, and ZIP Code) (X) 9A. AMENDMENT OF SOLICITATION NO.

AG-4419-S-10-0476

9B. DATED (SEE ITEM 11)

03/19/2010

10A. MODIFICATION OF CONTRACT/ORDER NO.

10B. DATED (SEE ITEM 13)

CODE FACILITY CODE

11. THIS ITEM ONLY APPLIES TO AMENDMENTS OF SOLICITATIONS

The above numbered solicitation is amended as set forth in item 14. The hour and date specified for receipt of Offers is extended, is not extended.

Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods:

(a) By completing Items 8 and 15, and returning 1 copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted;

or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.

12. ACCOUNTING AND APPROPRIATION DATA (If required)

13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,

IT MODIFIES THE CONTRACT/ORDER NO. AS DESCRIBED IN ITEM 14.

(X) A. THIS CHANGE ORDER IS ISSUED PURSUANT TO: (Specify authority) THE CHANGES SET FORTH IN ITEM 14 ARE MADE IN

THE CONTRACT ORDER NO. IN ITEM 10A.

B. THE ABOVE NUMBERED CONTRACT/ORDER IS MODIFIED TO REFLECT THE ADMINISTRATIVE CHANGES (such as changes in paying office, appropriation date, etc.) SET FORTH IN ITEM 14, PURSUANT TO THE AUTHORITY OF FAR 43.103(b).

C. THIS SUPPLEMENTAL AGREEMENT IS ENTERED INTO PURSUANT TO AUTHORITY OF:

D. OTHER (Specify type of modification and authority)

E. IMPORTANT: Contractor is not, is required to sign this document and return 1 copies to the issuing office.

14. DESCRIPTION OF AMENDMENT/MODIFICATION (Organized by UCF section headings, including solicitation/contract subject matter where feasible.

UpperWilliams North Road Decommissioning Recovery Project

There are changes to several documents in the solicitation package including a new bid schedule. Please use this revised bid schedule when submitting your offer.

Pre-bid meeting attendees and notes are also attached.

Print and sign this amendment and return with your offer.

Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remains unchanged and in full force and effect.

15A. NAME AND TITLE OF SIGNER (Type or print) 16A. NAME AND TITLE OF CONTRACTING OFFICER (Type or print)

Melissa Conn

15B. CONTRACTOR/OFFEROR 15C. DATE SIGNED 16B. UNITED STATES OF AMERICA 16C. DATE SIGNED

04/30/2010 (Signature of person authorized to sign) (Signature of Contracting Officer)

NSN 7540-01-152-8070

Previous edition unusable

30-105 STANDARD FORM 30 (REV. 10-83)

Prescribed by GSA

FAR (48 CFR) 53.243

ITEM # DESCRIPTION

METHOD OF

MEASUREMENT

PAY UNIT

ESTIMATED

QUANTITY

UNIT COST TOTAL PRICE

151 MOBILIZATION LSQ LUMP SUM 1

211 RECONTOUR DQ LINEAR FOOT 5925

211.01(b) OUTSLOPING DQ LINEAR FOOT 34936

211.01(b) OUTSLOPING WITHOUT DECOMPACTING DQ LINEAR FOOT 9490

211 DECOMPACTION ONLY DQ LINEAR FOOT 281

625 SEED AND MULCH DQ ACRE 32.85

251.04 BARRIER ROCK DQ TON 64

251.05 KEYED RIPRAP DQ SQ FT 39

BASE BID

SUB-TOTAL

ITEM # DESCRIPTION

METHOD OF

MEASUREMENT

PAY UNIT

ESTIMATED

QUANTITY

UNIT COST TOTAL PRICE

211.01(b) OUTSLOPING DQ LINEAR FOOT 4883

625 SEED AND MULCH DQ ACRE 3.4

OPTIONAL BID SUB-

TOTAL

LSQ = Lump Sum Quantity DQ = Design Quantity TOTAL CONTRACT

BID ===>

Schedule of Items

FR1797 Road Decommission for Watershed Restoration (Upper Williams North)

CIM-0921-9R-984-0921-02

Base Bid Items (FR1797, M-176, WR-15, M-151, M-174, WR-10, WR-11, WR-12)

Optional Bid Item 1 (M-154)

Project Drawings

FR1797 Road Decommission for Watershed Restoration (Upper Williams North)

CIM-0921-9R-984-0921-01

Project Drawings Page 1 of 7

OUTSLOPE TYPICAL

(not to scale)

ROAD # TREATMENT START END LENGTH

FR1797 No Excavation 0+00 1+30 130 FR1797 15% Outslope 1+30 42+46 4116 FR1797 Full Recontour 42+46 99+21 5675 FR1797 15% Outslope 99+21 110+62 1141

FR1797

10% Outslope, no decompaction 110+62 205+52 9490 FR1797 39+24A 15% Outslope 0+00 40+00 4000 FR1797 61+85A 15% Outslope 0+00 5+85 585 FR1797 90+87A 15% Outslope 0+00 1+35 135 FR1797 132+71A 15% Outslope 0+00 13+70 1370 FR1797 132+71C 15% Outslope 0+00 1+38 138

M-176 15% Outslope 0+00 3+96 396 M-176 Decompact 3+96 5+19 123 M-176 15% Outslope 5+19 37+75 3256 M-176 Full Recontour 37+75 38+45 70 M-176 15% Outslope 38+45 76+57 3812 M-176 Full Recontour 76+57 76+97 40

M-176 3+30A 15% Outslope 0+00 2+40 240 M-176 15+25A 15% Outslope 10+00 14+70 470 M-176 18+42A 15% Outslope 0+10 7+25 715

M-176 22+00A 15% Outslope 0+00 7+83 783 M-176 22+00B 15% Outslope 0+00 13+35 1335

WR-15 15% Outslope 0+00 12+10 1210 M-151 15% Outslope 0+00 10+84 1084 M-151 Decompact 10+84 11+42 58

Seeding and Mulching

Decompaction

15% Outslope

Existing Roadbed

Existing

Cut Slope

Existing Fill Slope

Project Drawings Page 2 of 7

OUTSLOPE (CONTINUED)

ROAD # TREATMENT START END LENGTH

M-151 Outsloping 11+42 25+70 1428 M-174 15% Outslope 10+00 24+06 1406

M-174 22+76A 15% Outslope 0+00 1+98 198 WR-11 15%Outslope 0+12 26+00 2588 WR-11 Decompact 26+00 27+00 100 WR-11 15% Outslope 27+00 67+50 4050 WR-11 Full Recontour 67+50 68+90 140 WR-12 15% Outslope 0+00 4+80 480 M-154 15% Outslope 0+62 49+45 4883

Project Drawings Page 3 of 7

CHANNEL RESTORATION SITES TYPICAL

ROAD # START END

APPROX.

FLAT

BOTTOM

WIDTH (ft)

APPROX.

CHANNEL

DEPTH

(ft)

APPROX.

FLOODPLAIN

WIDTH (ft)

FR1797 39+24A 26+60 26+80 7 2 20

M-176 3+62 3+96 18 2 36

M-176 13+30 13+57 10 2 27

M-176 13+74 14+09 12 1 24

M-176 14+28 14+51 12 1.5 23

M-176 24+85 25+16 11 1.5 31

M-176 25+66 25+88 10 1 22

M-176 26+06 26+35 17 2 29

M-176 59+35 59+76 12 2 41

M-176 60+21 60+36 6 1 15

M-176 60+50 60+76 11 1 26

M-176 76+32 76+57 12 2 25

WR-11 7+39 7+65 12 0.5 26

WR-11 9+25 9+59 12 0.5 34

WR-11 16+04 16+35 16 2 29

Flat bottom

Width

Floodplain Width

Channel Depth

20’ Mandatory

Straw Mulch

CROSS-SECTIONAL VIEW

Gradient

Existing Road Surface

LONGITUDINAL VIEW

Project Drawings Page 4 of 7

CHANNEL RESTORATION SITES (CONTINUED)

ROAD # START END

APPROX.

FLAT

BOTTOM

WIDTH (ft)

APPROX.

CHANNEL

DEPTH

(ft)

APPROX.

FLOODPLAIN

WIDTH (ft)

WR-11 23+63 23+90 10 1 27

WR-11 46+05 46+33 10 2 28

Project Drawings Page 5 of 7

STREAM CROSSINGS TYPICAL

ROAD # START

FLAT BOTTOM WIDTH

(ft)

FR1797 1+03 25

FR1797 4+35 5

FR1797 4+67 5

FR1797 6+73 20

FR1797 9+08 5

FR1797 17+84 5

FR1797 40+00 5

FR1797 41+16 5

FR1797 42+36 5

FR1797 46+57 5

FR1797 54+00 5

FR1797 54+38 5

FR1797 55+52 5

FR1797 56+75 5

FR1797 88+95 8

FR1797 92+00 10

FR1797 92+20 8

FR1797 92+49 8

FR1797 93+42 10

FR1797 94+94 8

FR1797 95+21 8

FR1797 95+76 10

FR1797 96+00 10

FR1797 97+70 5

FR1797 99+22 8

FR1797 110+54 8

FR1797 135+57 6

Channel

Width

Width

Existing

Grade

Natural slope

Natural slope

20’ Mandatory

Straw Mulch

20’ Mandatory

Straw Mulch

Flat Bottom Width

Project Drawings Page 6 of 7

STREAM CROSSINGS (CONTINUED)

ROAD # START

FLAT BOTTOM

WIDTH (ft)

FR1797 142+68 12

FR1797 144+13 8

FR1797 144+90 20

FR1797 146+10 10

FR1797 146+41 5

FR1797 147+80 5

FR1797 149+09 5

FR1797 150+37 10

FR1797 156+00 8

FR1797 163+10 5

FR1797 166+83 5

FR1797 39+24A 8+25 8

FR1797 39+24A 9+36 6

FR1797 39+24A 10+08 6

FR1797 39+24A 22+32 10

FR1797 39+24A 23+62 6

FR1797 39+24A 25+54 6

FR1797 39+24A 25+85 6

FR1797 39+24A 26+92 5

FR1797 39+24A 27+49 3

FR1797 39+24A 32+68 5

FR1797 39+24A 34+00 10

FR1797 90+87A 0+11 5

FR1797 132+71A 0+62 6

FR1797 132+71A 3+05 5

FR1797 132+71A 3+36 15

FR1797 132+71A 4+60 4

FR1797 132+71A 9+60 5

FR1797 132+71C 0+88 5

M-176 1+66 5 M-176 8+90 4 M-176 14+09 5 M-176 39+43 4 M-176 42+22 48 M-176 53+60 50 M-176 59+82 3 M-176 61+31 4 M-176 68+70 4 M-176 75+41 5 M-176 75+63 59

Project Drawings Page 7 of 7

STREAM CROSSINGS (CONTINUED)

ROAD # START

FLAT BOTTOM

WIDTH (ft)

M-176 18+42A 0+06 4 M-176 18+42A 0+60 10 M-176 18+42A 1+72 4 M-176 22+00A 4+18 6

M-151 1+01 3 M-151 1+21 7 M-151 2+07 6 M-151 9+58 8 M-151 10+38 9 M-151 23+39 7 M-151 25+60 4 M-174 10+23 6 M-174 11+33 9 M-174 11+60 6 M-174 13+50 6 M-174 14+99 11 M-174 19+37 5 M-174 19+53 4

WR-11 0+00 8

WR-11 1+68 5

WR-11 35+80 4

WR-11 44+98 4

WR-11 45+51 10

WR-12 1+60 5

WR-12 2+99 5

M-154 5+42 10 M-154 5+90 5 M-154 7+61 5 M-154 17+69 15 M-154 18+22 5 M-154 21+72 5 M-154 22+07 10 M-154 22+52 5 M-154 27+36 5 M-154 30+91 5 M-154 31+20 10

Road Log

Road Log Page 1 of 10

BASE BID ITEMS

FR 1797

0+00 Start of road: No excavation 0+64 Mine Opening 1+03 Wide stream crossing for mine runoff, 25’ flat bottom 1+30 Begin Outsloping; Mine Opening; No disturbance to pool on North side of road 3+60 Skid Road on fill slope, 3+60A, no excavation 4+35 Stream crossing 5’ flat bottom 4+67 Stream crossing 5’ flat bottom 5+24 Wooden structure, outslope outside of road, no disturbance to structure.

5+90 Continue outsloping entire road (end of wooden structure area) 6+73 Channelized flow from above road segment. Break up flow with wide crossing area, 20’ flat bottom 9+08 Stream crossing, 5’ flat bottom 16+20 Skid road on cut slope, 16+20A, no excavation 17+13 Vernal pool creation 17+33 End of vernal pool, continue outsloping 17+84 Stream/seep crossing, 5’ flat bottom 20+64 Skid road on fill slope to the North, 20+64A, no excavation 31+30 Switchback to the North 39+24 Skid road fill slope side, 39+24A (access to 1796).

39+24A Road Log 0+00 Begin Outsloping

4+32 Skid road, 4+32A, no excavation 8+25 Stream crossing, 8’ flat bottom 9+36 Stream crossing, 6’ flat bottom (will go thru the rd below) 10+08 Stream crossing from 9+36 20+49 Skid road intersection, 20+49A, no excavation 22+32 Stream crossing, 10’ flat bottom 23+62 Stream/seep crossing, 6’ flat bottom 25+54 Stream/seep crossing, 6’ flat bottom 25+85 Stream crossing, 6’ flat bottom 26+60 Channel Restoration Site (7’ flat bottom, 2’ depth, 20’ floodplain) 26+92 Stream crossing 5’ flat bottom 27+49 Stream/seep crossing 3’ flat bottom 29+20 Skid road intersection, 29+20A no excavation 32+68 Stream crossing, 5’ flat bottom 34+00 Stream crossing, 10’ flat bottom; remove 18” CMP 40+00 End-intersection with FR 1796

40+00 Stream crossing, 5’ flat bottom 41+16 Stream crossing, 5’ flat bottom 42+36 Stream crossing, 5’ flat bottom 42+46 End outsloping, begin Full Recontour.

46+57 Stream crossing, 5’ flat bottom 46+98 Large washout; 90% of road bed eroded 47+89 Large washout; 100% across road and 20 feet of road length 51+42 Skid road on fill slope, 51+42A, no excavation

Road Log Page 2 of 10

54+00 Stream crossing, 5’ flat bottom 54+38 Stream crossing, 5’ flat bottom 55+52 Stream crossing, 5’ flat bottom 56+75 Stream crossing, 5’ flat bottom 58+63 Skid road on fill slope, 58+63A, no excavation 60+00 Skid road on cut slope, 60+00A, no excavation 61+85 Skid road on cut slope, 61+85A

61+85A Road Log 0+00 Begin Outsloping 5+85 End of excavation, intersection with FR1797

72+37 Skid road on cut slope, 72+37A, no excavation 78+45 Skid road on cut slope, 78+45A, no excavation 87+87 Skid road on cut slope, 87+87A, no excavation 88+00 Skid road on cut slope, 88+00A, no excavation 88+60 Stream crossing, 8’ flat bottom 89+52 Skid road on cut slope, 89+52A, no excavation 88+95 Stream crossing, 8’ flat bottom; remove 24” CMP 90+87 Skid road on cut slope, 90+87A

90+87A Road Log 0+00 Begin outsloping 0+11 Stream crossing, 5’ flat bottom 1+35 End of excavation, intersection with FR1797

92+00 Stream crossing, 10’ flat bottom 92+20 Stream crossing, 8’ flat bottom 92+49 Stream crossing, 8’ flat bottom 93+42 Stream crossing, 10’ flat bottom 93+72 Remove 24” CMP 94+94 Stream crossing, 8’ flat bottom 95+21 Stream crossing, 8’flat bottom 95+76 Stream crossing, 10’flat bottom 96+00 Stream crossing, 10’flat bottom 97+70 Stream crossing, 5’ flat bottom 98+16 Large washout-90% of road width (20’ wide) 99+21 End of full recontour, begin outslope 99+22 Stream crossing, 8’ flat bottom 99+76 Skid road on cut slope, 99+76A, no excavation 110+54 Stream crossing, 8’ flat bottom 110+62 End standard outsloping prescription, begin outsloping without decompacting 129+34 Skid road on cut slope, 129+34A no excavation 132+71 Skid road on cut slope, 132+71A

132+71A Road Log 0+00 Start Outsloping 0+62 Stream crossing, 6’ flat bottom 3+05 Stream crossing, 5’ flat bottom 3+36 Stream crossing, 15’ flat bottom

4+60 Stream crossing, 4’ flat bottom 6+50 Intersection with skid road, no excavation 7+75 Intersection with skid road, no excavation 8+70 Intersection with skid road 132+71C

Road Log Page 3 of 10

132+71C Road Log

0+00 Start Outsloping 0+88 Stream crossing, 5’ flat bottom 1+38 End of excavation

9+60 Stream crossing, 5’ flat bottom 13+70 End of excavation, intersection with FR1797

135+57 Stream crossing, 6’ flat bottom 142+53 Skid road on cut slope, 142+53A no excavation 142+68 Stream crossing, 12’ flat bottom 144+13 Stream crossing, 8’ flat bottom 144+90 Stream crossing, 20’ flat bottom 146+10 Stream crossing, 10’ flat bottom 146+41 Stream crossing, 5’ flat bottom 147+80 Stream crossing, 5’ flat bottom 149+09 Stream crossing, 5’ flat bottom 150+37 Stream crossing, 10’ flat bottom-place native rock in channel 156+00 Stream crossing, 8’ flat bottom take fill to 156+20 155+75 thru 156+20 Concave crossing, do not put excavated fill on cut slope here, place on either side of this.

157+68 Skid road, 157+68A, no excavation 158+60 Vernal pool creation 158+80 End of vernal pool, continue outsloping 162+00 Skid road on fill slope, 162+00A no excavation 163+10 Stream crossing, 5’ flat bottom 166+83 Stream crossing, 5’ flat bottom; Skid road on cut slope (with erosion channel) 166+83A, no excavation 184+57 Skid road, no excavation 187+47 Skid road on cut slope, 187+47A, no excavation 205+52 End of road; intersection with FR 461

Road Log Page 4 of 10

M-176 0+00 Begin outsloping 1+66 Stream/seep crossing, 5’ flat bottom 3+30 Skid road on cut, 3+30A

3+30A Road Log 0+00 Begin outslope 2+40 End of road, intersection with M-176

3+62 Channel Restoration Site (18’ flat bottom, 2’ depth, 36’ floodplain) 3+96 End outsloping, begin decompact only (colluvium area with large boulders and water running subsurface) 5+19 End decompact only, continue outsloping 8+37 Skid road on cut, 8+37A, no excavation 8+90 Stream crossing, 4’ flat bottom 13+30 Channel Restoration Site (10’ flat bottom, 2’ depth, 27’ floodplain) 13+74 Channel Restoration Site (12’ flat bottom, 1’ depth, 24’ floodplain) 14+09 Stream crossing, 5’ flat bottom 14+28 Channel Restoration Site (12’ flat bottom, 1.5’ depth, 23’ floodplain) 15+25 Skid road of fill slope, 15+25A (connects to 29+50A)

15+25A Road Log 10+00 Begin outslope 14+70 End of road, intersection with M-176

18+42 Skid road on cut, 18+42A

18+42A Road Log 0+00 Start of road 0+06 Stream crossing, 4’ wide 0+10 Start outsloping 0+60 Stream crossing, 10’ flat bottom 1+72 Stream crossing, 4’ flat bottom 7+25 Intersection with M-176

22+00 Skid road on cut, 22+00A

22+00A Road Log 0+00 Start outsloping 0+87 Intersection with 22+00B 4+18 Stream crossing, 6’ flat bottom 7+83 End of road, intersection with M-176

22+00B Road Log

13+35 End of road, intersection with 22+00A

24+85 Channel Restoration Site (11’ flat bottom, 1.5’ depth, 31’ floodplain) 25+66 Channel Restoration Site (10’ flat bottom, 1’ depth, 22’ floodplain) 26+06 Channel Restoration Site (17’ flat bottom, 2’ depth, 29’ floodplain) 27+00 Skid road on cut, 27+00A, no excavation 29+50 Skid road on fill, 29+50A (connects to 15+25A) no excavation 37+75 End outsloping, begin full Recontour

Road Log Page 5 of 10

38+45 End full Recontour, continue outsloping 39+43 Stream/seep crossing, 4’ flat bottom 42+22 Stream crossing, 48’ flat bottom, (wide colluvial area), 59’ flat bottom 53+60 Stream crossing, 50’ flat bottom, (colluvial seep) 54+30 Skid road on fill slope, 54+30A, no excavation 55+55 Skid road on cut slope, 55+55A, no excavation 56+55 Remove 36” CMP 59+35 Channel Restoration Site (12’ flat bottom, 2’ depth, 41’ floodplain), Remove 36” CMP 59+82 Stream crossing, 3’ flat bottom 60+21 Channel Restoration Site (6’ flat bottom, 1’ depth, 15’ floodplain), Remove 18” CMP 60+50 Channel Restoration Site (11’ flat bottom, 1’ depth, 26’ floodplain), Remove 24” CMP 61+31 Stream crossing, 4’ flat bottom. Remove 18” CMP 65+63 Remove 18” CMP 68+70 Stream crossing, 4’ flat bottom. Armor headcut 6’ wide with rock on site. Remove 36” CMP 74+44 Remove 18” CMP 75+41 Stream crossing 5’ flat bottom. Remove 18” CMP 75+63 Stream crossing (wide colluvium area through 76+22) 76+00 Remove 18” CMP 76+32 Channel Restoration Site (12’ flat bottom, 2’ depth, 25’ floodplain) 76+57 End outsloping, begin full Recontour 76+97 End of excavation. Place barrier rocks using native rock on site.

Road Log Page 6 of 10

WR-15

6+15 Skid road on fill slope, 6+15A, no excavation 11+65 Place barrier rocks using native rocks on site 12+10 Intersection with FR86, end of excavation

Road Log Page 7 of 10

M-151

1+01 Stream crossing, 3’ flat bottom 1+21 Stream crossing, 7’ flat bottom 2+07 Stream crossing, 6’ flat bottom 9+58 Stream crossing, 8’ flat bottom 10+38 Stream crossing, 9’ flat bottom 10+84 Skid road to north, 10+84A, no excavation.

Road goes thru large opening, turns 90 degrees south. End outsloping, begin Decompacting only on road tread through this opening.

11+42 End decompacting only, continue outsloping 23+39 Stream crossing 7’ flat bottom 25+60 Stream crossing for road ditch, 4’ flat bottom 25+70 End of excavation 26+00 Intersection with FR86

Road Log Page 8 of 10

M-174 10+00 Begin outsloping 10+23 Stream crossing, 6’ flat bottom 11+33 Stream crossing, 9’ flat bottom 11+60 Stream crossing, 6’ flat bottom 13+50 Stream crossing, 6’ flat bottom 14+99 Stream crossing, 11’ flat bottom 17+70 Large basswood on shoulder, do not disturb 19+37 Stream crossing, 5’ flat bottom 19+53 Stream crossing, 4’ flat bottom 22+76 Skid road on fill slope, 22+76A

22+76A Road Log 0+00 Begin outsloping 1+98 End of excavation, intersection with M-174

24+06 End of excavation, intersection with FR86

Road Log Page 9 of 10

WR-11

0+00 Stream crossing, 8’ flat bottom 0+12 Begin outsloping 1+68 Stream crossing, 5’ flat bottom (construct diagonally across road aiming for existing channel down slope) 7+39 Channel Restoration Site (12’ flat bottom, 0.5’ depth, 26’ floodplain) 9+25 Channel Restoration Site (12’ flat bottom, 0.5’ depth, 34’ floodplain) 16+04 Channel Restoration Site (16’ flat bottom, 2’ depth, 29’ floodplain) 23+63 Channel Restoration Site (10’ flat bottom, 1’ depth, 27’ floodplain) 26+00 End outsloping, begin decompact only (flat area) 27+00 End decompact only, continue outsloping 35+80 Stream crossing 30’ east of road, 4’ flat bottom 37+33 Intersection with 80’ road connecting to WR-11 above switchback. Outslope this 80’ section.

44+98 Stream crossing, 4’ flat bottom 45+51 Stream crossing, 10’ flat bottom, remove all road fill.

46+05 Channel Restoration Site (10’ flat bottom, 2’ depth, 28’ floodplain) 61+85 Intersection with WR-12 on fill slope 67+50 End outsloping, begin full Recontour 68+70 Place barrier rocks using native rocks on site 68+90 End of excavation, intersection with FR86

WR-12

1+60 Stream crossing, 5’ flat bottom. Armor head cut below road(10 sf)and head cut above road (5 sf) 2+99 Stream crossing, 5’ flat bottom 4+80 End of excavation, intersection with WR-11

Road Log Page 10 of 10

OPTIONAL BID ITEM 1

M-154 0+00 Beginning of road at Forest Boundary and unnamed tributary to Day Run 0+62 Begin outsloping 5+42 Stream crossing, 10’ flat bottom 5+90 Stream crossing, 5’ flat bottom 7+61 Stream crossing, 5’ flat bottom 17+69 Stream crossing, 15’ flat bottom (rocky area) 18+22 Stream crossing, 5’ flat bottom 21+72 Stream crossing, 5’ ‘flat bottom 22+07 Stream crossing, 10’ flat bottom (natural channel, minimal work needed) 22+52 Stream crossing, 5’ flat bottom 27+36 Stream/seep crossing, 5’ flat bottom 28+60 Skid road, 28+60A, no excavation 30+91 Stream crossing, 5’ flat bottom 31+20 Stream crossing, 10’ flat bottom 49+45 End outsloping

General Notes

General Notes Page 1 of 3

Governing Specifications

The Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-

03, USDOT, shall be the governing specifications for this project. The contract documents, details and drawings are the governing provisions applicable to this project.

Project Areas

The project area is located in Pocahontas County, West Virginia approximately 8 miles northwest of

Marlinton in the upper Williams River watershed. This contract involves prescribed road decommissioning and road storage treatments for the following roads on the Marlinton Ranger District of the Monongahela National Forest: FR1797, M-176, WR-15, M-151, M-174, WR-11, WR-12, M-154 and all intersecting skid roads.

Project Area Access

Forest Roads 86, 216, 461, 1796, and State Route 17/4 provide access to the project area. Any damages to Forest Service System roads resulting from equipment mobilization must be rehabilitated. Example:

damage to existing road surfaces or drainage features must be repaired.

Base Bid and Optional Bid Items

This contract consists of a Base Bid and 1 Optional Bid Item. Contractors should bid on all items.

Bids should reflect the potential for this contract to be awarded for the Base Bid Item as a minimum award. The Optional Bid Item will be awarded as funding allows.

Other Contracts

Contract work shall not interfere with or inhibit work on other contracts in the area.

Equipment Cleaning

Equipment and vehicles used during the project shall be free of soil, seeds, vegetative debris, or other matter that could contain seeds or plant parts when such equipment arrives on National Forest land. Any necessary cleaning of equipment and vehicles shall not be conducted on National Forest land.

Waste Sites

No waste sites have been identified for this project. Any excess material will be wasted along the road in conjunction with road obliteration activities.

Decompaction of Road Tread

Existing road tread will be decompacted to a minimum depth of 12 inches. This will be completed in areas of outslope, concave areas and decompaction only areas. The cost for this decompaction will be included in items 211.01(b)- Road Obliteration, and in 211- Decompaction.

Outsloping

In areas requiring outsloping, the road will be outsloped to the minimum slope specified (for example, 15%) by removing road fill material and placing it on the cut slope and inside portion of the road. This will be completed in a manner that results in a gradual transition between the newly established grade and the existing slopes immediately adjacent to the treated areas. Where the natural slope above and below the road corridor is less than the degree of outsloping prescribed for the road, the final outslope of

General Notes Page 2 of 3 the road shall match that of the natural grade. Roads segments with a full recontour prescription will require similar actions as other outsloping prescriptions except all the road fill material will be removed and placed on the cut slope to achieve a final slope the reflects the natural slope as much as possible. If material on site is not sufficient to obtain the prescribed degree of outsloping or full recontouring, the greatest degree of outsloping that can be attained with the material on site shall be sufficient. No additional material will be brought in to achieve the outslope prescription. Outsloping at the intersections of two or more roads will reflect a continuous outslope of the excavated intersection.

Areas requiring a concave crossing are included in this item. Concave crossings will be constructed so that fill will be removed from the outside edge of the road, but will not be deposited on the inside edge, therefore achieving a depression across the entire road corridor. The excess material from concave crossings will be wasted along an adjacent outsloped area. See Project Drawings and Project Details for more information.

Channel Restoration Sites

Channels and floodplain areas will be excavated to reflect and blend with more natural conditions found upstream and downstream from the road crossing. See Project Details and Project Drawings for appropriate channel dimensions. The cost for channel crossings will be included in item 211.01(b) of

Road Obliteration actions such as Outsloping and Outsloping without Decompaction.

Stream Crossings

Stream crossings are similar to channel restoration sites, in that they will be excavated to reflect and blend with more natural conditions found upstream and downstream from the road crossing. These are typically smaller than channel restoration sites, and therefore require less excavation. The location and width requirements for stream crossings are identified in the Project Drawings and the Road Log. The cost for stream crossings will be included in item 211.01(b) of Road Obliteration actions such as

Outsloping and Outsloping without Decompaction.

Areas of No Excavation

In areas requiring no excavation, if ruts develop in the road bed during implementation of this project, they shall be removed. Ruts in this context shall be defined as extending deeper than 2 inches into the road bed and extending for greater than 40 feet.

Removal of Existing Drainage Structures

Existing culverts will be removed from the project area and public land, and will become property of the contractor. The road log identifies the locations of culverts. All culverts encountered in areas of outsloping and full recontour shall be removed, even if not specifically identified in road log. The cost for removal shall be included in item 211.01(b) of Road Obliteration actions such as Outsloping and

Outsloping without Decompaction.

Removal of Trees and Vegetation

All trees that need to be felled to facilitate road obliteration will be left on site. They will be evenly scattered throughout the final grade or in stream crossings, as directed by contract administrators. Trees will not be windrowed on the final grade. The contractor will make every effort to avoid disturbing larger trees. The cost for vegetation removal shall be included in item 211.01(b) of Road Obliteration actions such as Outsloping and Outsloping without Decompaction.

General Notes Page 3 of 3

Sediment and Pollution Control

Sediment runoff will be controlled at all stream and water crossings during travel to and from active work site. This may include temporary hay bale placement at outflows.

All equipment shall be equipped with a spill kit in case of fluid leaks or spills. This shall include fluid absorption pads. Any equipment leak or spill shall be reported to contract administrators as soon as possible.

Seeding and Mulching

All disturbed areas shall be seeded and mulched within 7 days of disturbance. Seeding and mulching must be done in a manner that does not leave ruts in or compact the finished grade. See project details for more information.

Barrier Rocks

Boulders will be placed in the locations identified in the Road Logs to help prevent motor vehicle access to roads being treated under this contract. Boulder placement may be directed by the designated contract administrator. Boulders will be approximately 4’ median diameter, be partially buried to inhibit their movement, and be positioned to effectively restrict motor vehicle access (including ATVs). Native rocks may be used if they are available on site and occur within the typical disturbance perimeter of other actions required by this contract.

Waste Materials

All trash in the project area, whether pre-existing or produced as a by-product of activities required in this contract, shall be removed from National Forest Systems lands and disposed of properly.

Final Grade

The final grade of all excavated areas shall be bucket placed to eliminate the potential for soil compaction or rutted surfaces.

Utilities

It is the responsibility of the contractor to contact MISS UTILITY (1.800.245.4848) prior to beginning construction on this contact to determine the need for special precautions related to public utilities.

Upper Williams North Road Decommissioning AG-4419-S-10-0476 Upper Williams South Road Decommissioning AG-4419-S-10-0482

Pre-Bid Meeting Marlinton Ranger Station

April 29, 2010

Attendees:

Name Company and Address Phone Email Lindsey Hayes USFS, PO Box 67, Bartow

WV 24920

304-456-3335 x120 lbhayes@fs.fed.us

Mike Owen USFS, 200 Sycamore St., Elkins WV 26241

304-636-1800 x203 mdowen@fs.fed.us

Angela Abel USFS, PO Box 210, Marlinton WV, 24954

304-799-4334 x29 aaabel@fs.fed.us

Ron Snyder Alan Stone Co., Williamstown, WV

304-375-6484

Ralph Miller Jason Rohr

Rohrco Corp, 154 Clarksburg Rd, Buckhannon WV 26201

304-472-4790

Ben Blair SAGE Inc, 293 Meadow St, PO Box 1505, Waynesville NC 28786

828-507-5166 828-246-9115- fax bensblair@yahoo.com

Camille Ledford Billy Dial

206 Ross Williams Rd.

Lancing, TN 37770

423-965-2272 buckcreek@highland.net

Leondis Gilkerson G.L. Stone, Inc 24 First Street Hamlin, WV 25523

304-824-3800 304-824-3848- fax leondisg@yahooo.com

Ann Wardkiell Eastern Arrow PO Box 4108 Charleston, WV 25364

304-414-0255 easternarrow@hotmail.com

Richard Faulkner RW Faulkner Excavating 409 2nd Ave Marlinton, WV 24954

304-799-6263 Rwfaulkner@exca.com

Claude Cunningham Meadows Stone and Paving PO Box 10 Gassaway, WV 26624

304-364-5151 304-364-5153- fax mailto:lbhayes@fs.fed.us� mailto:mdowen@fs.fed.us� mailto:aaabel@fs.fed.us� mailto:bensblair@yahoo.com� mailto:buckcreek@highland.net� mailto:leondisg@yahooo.com� mailto:easternarrow@hotmail.com�

Q- Do you have to do both contracts at the same time or can you do one then the other?

A- Both contracts have time limits from the issuance of the Notice to Proceed that must be met.

Q- So are you doing away with the roads?

A- Some will be decommissioned and some will be put in a state of storage because we will not need them for awhile. The road prescriptions include full recontour, outslope, decompacting and storage. Refer to the road log for locations.

Q- What do we do with the timber and brush cut? Do we chip it?

A- All vegetation will be left on the finished surface scattered about, not windrowed and not buried in the fill.

Q- How is the overflow spillway paid?

A- The stone is included in the riprap item and the excavation in the outsloping.

Q- Is ATV access allowed?

A- Yes, we are allowing access by ATV and behind gates after 1pm for potential bidders by issuing permits that must be on hand while field reviewing. Bidders must inform the Marlinton Ranger Station when and where they will be.

Q- What is the weight limit on the bridge on FR999?

A- Not sure, although loaded logging trucks travel over it. Contractors would want to look for a turnaround spot up this road, may need to unload before bridge anyway.

Q- What types of streams are available on these roads for hydroseeding?

A- This varies by road. Contractor will need to look at potential water sources and include this as part of their proposal.

Q- Are all of the culverts to be removed metal?

A- Yes, most are corrugated metal pipes and some are steel pipes.

Q- When do you anticipate this project starting?

A- Probably late June, early July. We are planning on having both completed this field season.

Q- Do we need to remove the gate on FR171 and do we get to keep it?

A- It will be removed but left on site. Although the removed culverts become the property of the contractor and must be disposed of properly.

Q- Does our erosion control plan need to be approved by the DEP?

A- No, this will be included as part of your proposal and method to accomplish work.

Q- Will we just bring up the fill and place it on the cut slope to achieve the outslope?

A- Yes, the fill will be placed on the inside of the road bed to accomplish the outslope. All road surfaces must be decompacted to a minimum of 12 inches unless otherwise specified.

Q- If there is a pool below a culvert is that sufficient for a sediment control pond?

A- Yes, if necessary but we would prefer to prevent the sediment reaching the stream to begin with. Sediment should be controlled as soon as possible on the downhill side of the project, generally before a pool. That is good aquatic habitat and we do not want to fill it up with sediment. Any sediment collected down slope from the project should be removed when finished with that site.

Q- Will you be able to drive through the ditch and culvert relief dips?

A- They are not designed that way.

Q- Can the concrete footers to be removed be crushed and left on site?

A- No, they must be removed. It is up to the contractor to remove any waste and dispose of it properly.

Q- What do we do with the allotment?

A- All improvements within the allotment accessing M-171A shall be maintained and left in a state as good as or better than before the project. Cattle will be in the allotment during the project and they must continue to be contained in the allotment throughout construction.

Q- Will we need to bring in rock to armor the stream crossings?

A- No, but if you encounter large rock while excavating down to the stream bottom, we would prefer that it be left in the crossing for armor.

Q- Are we allowed to ATV into the project before 1 pm on Sunday?

A- Yes, that is allowed since there is no hunting on Sundays.

Amendment 1
ScheduleofItems_1797
ProjectDrawings_FR1797
RoadLog_FR1797
GeneralNotes_FR1797
Prebid meeting notes