Performance Requirements Summary
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF 1449 AG-4419-S-10-0131.pdf | ||
| SF 1449 AG-4419-S-10-0131.pdf | ||
| Non-motorized Trails Maintenance IDIQ Q and A.docx | DOCX document | |
| Statement of Work.docx | DOCX document | |
| Drawings.pdf | ||
| MINI_IDIQ.docx | DOCX document | |
| Lake Conssauga Trails.doc | DOC document | |
| 74-1218_sca.txt | TXT text file | |
| Copy of Attachment 2 Smith Creek T2.docx | DOCX document | |
| State of Georgia.pdf | ||
| Copy of Attachment 3 Lake Conasauga T2.docx | DOCX document | |
| smithcreekmap_stim1_09.doc | DOC document | |
| 52.212-5 ARRA.doc | DOC document | |
| Copy of Attachment 1 Aska T2.docx | DOCX document | |
| Aska Trail Area Pg 2.pdf | ||
| Non-motorized Trail maintenance IDIQ Pay Items.doc | DOC document | |
| Design Parameters for Non-Motorized Trails.doc | DOC document |
Show all 17
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
PERFORMANCE REQUIREMENTS SUMMARY
| Requirement |
| Quality Standards |
| Acceptable Quality Level |
| Means of Measurement |
| Incentives/Disincentives |
| Trail Restoration |
| Trail Tread is firm, smooth and maintained at appropriate width based on Design Parameters and as stated in the task order. |
Target cross slope is consistent with Design Parameters and as stated in the task order.
Protrusions are allowed or removed based on Design Parameters and as stated in the task order.
Obstacles are allowed or removed based on Design Parameters and as stated in the task order.
For all tasks:
100% to standard; no deviation For all tasks:
Visual walk-through, random inspection by COR or Inspector.
For all tasks:
One rework allowed, at no cost to the Government, if standard is not met.
Additional reworks at Contractors expense, plus payment of actual costs incurred by the Government for additional reworks (e.g., inspection costs).
Past performance report, at the end of the contract(interim at the option of the Government)
| Drainage |
| Existing drainage structures (waterbars, grade dips, etc.) are cleared of debris and sediment. Drainage is reshaped as needed in order to function properly. |
| Slide Maintenance |
| Slide Maintenance- The trailbed finish shall be uniform, firm, and with proper drainage. |
| Logging Out |
| Removal of brush, logs, and down trees. |
Clearing is maintained according to Design Parameters and as stated in the task order.
| Hazard Tree Removal |
| Trailway is clear of fallen, dead, or leaning hazardous trees. No trees marked for removal remain |
| Closing Non-system Trails |
| Non-system (user created) trails are made unusable. |
| Silt Fence |
| Silt Fence is Properly installed, maintained, and retaining erosion debris. |
If not properly installed and maintained, the contractor will not be paid for the item and may not be awarded another task order.
| Bridge Construction |
| Bridges are constructed as specified in the contract requirements and according to drawings. |
| Bridge Restoration |
| Bridges are restored or installed as staked on the ground and are safe to use. |
| Seeding and Mulching |
| The seeding, mulch, and fertilizers are applied at the rates and mixtures specified in writing and provided by the COR. |
If the incorrect mixtures are applied, the Contractor will not be paid for the application and will have reseed, fertilize and mulch with the correct mixtures and rates at his own expense. The Contractor may not be awarded another task order.