Section B - Schedule.pdf
PDF 13 KB Posted
- Attached to
- RECOVERY* Cradle Roof Replacement - Pisgah National Forest - National Forests in North Carolina
- Solicitation number
- AG-4419-S-10-0053
About this file
Section B - Schedule of Items
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
9/28/2009
ITEM NO. DESCRIPTION
METHOD OF
MEASURE UNIT Quantity Unit Price TOTALS
1 Mobilization LSQ LS 1 $________ $________
Demolition of existing shingle roof and underlayment (contractor to dispose all materials legally off National Forest Lands)
LSQ LS 1 $________ $________
Additional Nailing Strips (1x4 or match existing) - Scenck's Office
LSQ LS 1 $________ $________
Roof Replacement - Cedar Shakes Premium Grade - certi-split - hand split western red cedar. Certi-Last - Impregnated preservative treatment
AQ SF 3,100 $________ $________
6 Clean & Prep Building LSQ LS 3 $________ $________
7 Roof - Flasing AQ SF 150 $________ $________
Felt Underlayment: 30lb asphalt saturated felts - ASTM D 226
AQ SF 3,100 $________ $________
9 Chinking - Shenck's Office Building Complete LSQ LS 1 $________ $________
Wood Gutters per details (Cantrell Creek Lodge & School House)
AQ LF 66 $________ $________
Remove & Replace Existing Guttering Front Porch - King House approx.33 LF
LSQ LS 1 $________ $________
Remove and Replace Bottom Sill (8x8) on three sides of Shenck's Office (Right, Left and Back of Building) Dove tailed ends required
LSQ LS 1 $________ $________
Remove and Replace existing porch sills on Commissary. Existing sill is 2x12 mittered on ends. Also
LSQ LS 1 $________ $________
Schoolhouse - Demolition of existing shingle roof and underlayment (contractor to dispose all materials legally off National Forest Lands)
LSQ LS 1 $________ $________
Schoolhouse - Felt Underlayment: 30lb asphalt saturated felt - ASTM D 226
AQ SF 1,300 $________ $________
Schoolhouse Roof Replacement - Cedar Shakes Premium Grade - certi-split - hand split western red cedar. Certi-Last - Impregnated preservative treatment
AQ SF 1,300 $________ $________
$________ TOTAL ALL:
TOTAL:
BID ALTERNATE
CRADLE ROOF REPLACEMENTS
SCHEDULE OF ITEMS
SOI-197