Questions and Answers.pdf
PDF 43 KB Posted
- Attached to
- RECOVERY MASSABESIC EXPERIMENTAL FOREST ON THE NORTHERN RESEARCH STATION, WHITE MOUNTAIN NATIONAL FOREST
- Solicitation number
- AG-4419-S-10-0002
About this file
Question and Answer
View the file
Other files
| File | Type | Posted |
|---|---|---|
| SF 1442 2 .pdf | ||
| Phase II q a.docx | DOCX document | |
| Pre-Bid Meeting.pdf | ||
| Updated Questions and Answers.pdf | ||
| SOW.pdf | ||
| SF30.pdf | ||
| Wage Determination.htm | HTM file | |
| Revision Pages 3 through 9.pdf | ||
| Solicitation Documents.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
QUESTIONS & ANSWERS FOR RFP #AG-4419-S-10-0002
Road & Watershed Restoration
Massabesic Experimental Forest
Below are the current Questions and Answers for the above mentioned solicitation received to date:
1. The solicitation does not define a Period of Performance (POP). Will the Government provide a POP for the project or will the schedule be based upon the bidders proposed schedule? A - A proposed schedule is in the
Scope of Work, additionally the anticipated period of performance is on the SF 1442, Section 11. We have reasonable flexibility on the schedule, will need to evaluate when the season comes and as part of eval process.
2. As defined in the solicitation, the bidder is responsible for all permitting requirements. Will the Government define which permits are required under this contract (e.g., NPDES, MEDEP, USACE), or, is it the bidders responsibility to comply with all applicable and relevant permitting requirements? A - It is the bidder's responsibility.
3. Are there any special requirements associated with threatened and/or endangered species (flora and fauna) within the limits of work? A - None were identified, there is seasonal construction windows shown for restricting access into live streams.
4. Are the forest access roads maintained/cleared during the Winter? If not, are the roads closed during the winter season and what date do they typically re-open? A - No. Roads are closed seasonally based on the weather. When snow covered, the roads are normally open to snowmobiles.
5. No pricing line item is provided for cutting/excavating of unsatisfactory road subgrade material. Should bidders assume that all existing material is suitable for overlay with new material? A - It is expected that suitable excavation and embankment is self-balanced along the roadways.
6. The scope of work references USGS monuments. Will the Government provide the coordinates (x,y,z) for all
USGS monuments within the limits of work? A - USGS monuments are not identified near the project, the surveyor should tie to monuments only if they are known and it is practical.
7. Is there a Government cost estimate for the project? If so, can it be provided to prospective bidders to evaluate whether the work can be completed for a reasonable cost? If no estimate has been prepared, will the
Government provide the amount of ARRA funds secured for the project? The Government Estimate cannot and shall never be provided. It is your responsibility to propose a reasonable price. The Construction Cost Range is provided, however, on page 4 of 4 on the SF1442. The design fee should never exceed 6% of the construction
Cost proposed.
8. The pricing schedule is divided into five (5) sub-projects. Does the Government intend on awarding all five
(5) projects to a single firm? A - Yes, we intend to award to one contractor.
9. In the event that not all five (5) subprojects are awarded, how will the Government establish the lowest-cost provider? That is, will lowest cost be based on the total sum for all five (5) projects or will it be based on fewer projects assuming not all projects can be completed within appropriated funding? If based upon individual projects, will the Government provide a priority for each sub-project? A - I recommend evaluating proposals based on sum of all Base Items.
File details come from the government source that posted it. Updated .