amdt_1.doc
DOC document 49 KB Posted
- Attached to
- Rabun Beach Bath House Loop 2
- Solicitation number
- AG-435H-S-09-0009
View the file
Other files
| File | Type | Posted |
|---|---|---|
| information to offerors.doc | DOC document | |
| bid amdt 1.pdf | ||
| LWS_G-102_Revision.pdf | ||
| amdt_2.pdf | ||
| Pre-Bid Meeting Attendees_Bath House.pdf | ||
| Drawings_Rabun Beach Bath House Loop 2.pdf | ||
| RFP_Rabun Beach Bath House Loop 2.doc | DOC document | |
| Specifications_Rabun Beach Bath House Loop 2.pdf | ||
| Vicinity and Site Map_Rabun Beach Bath House Loop 2.pdf | ||
| Technical Proposal Format_Rabun Beach Bath House Loop 2.doc | DOC document | |
| Standard Form 24_Bid Bond.pdf |
Show all 11
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
1. CONTRACT ID CODE
PAGE OF PAGES
AMENDMENT OF SOLICITATION / MODIFICATION OF CONTRACT
| 1 |
| 1 |
| 2. AMENDMENT/MODIFICATION NO. |
| 3. EFFECTIVE DATE |
| 4. REQUISITION/PURCHASE REQ. NO. |
| 5. PROJECT NUMBER (if applic.) |
| 1 |
| 6/30/2009 |
6. ISSUED BY:
USDA Forest Service Chattahoochee-Oconee National Forests 1755 Cleveland Highway Gainesville, GA 30501
7. ADMINISTERED BY (If other than 6.):
8. NAME AND ADDRESS OF CONTRACTOR
| [ x ] |
| 9A. AMENDMENT OF SOLICITATION NUMBER |
AG-435H-C-09-0009
Rabun Beach Bath House, Loop 1
9B. DATED (see item 11)
6/5/2009
| [ ] |
| 10A. MODIFICATION OF CONTRACT/ORDER NUMBER |
10B. DATED (see item 13)
| CODE |
| FACILITY |
11. THIS ITEM APPLIES ONLY TO AMENDMENTS OF SOLICITATIONS
[ X ] The above numbered solicitation is amended as set forth in Item 14. The hour and date specified for receipt of Offers [ ] is extended, [ X ] is not extended. Offers must acknowledge receipt of this amendment prior to the hour and date specified in the solicitation or as amended, by one of the following methods: (a) By completing Items 8 and 15, and returning ___1__ copies of the amendment; (b) By acknowledging receipt of this amendment on each copy of the offer submitted; or (c) By separate letter or telegram which includes a reference to the solicitation and amendment numbers. FAILURE OF YOUR ACKNOWLEDGMENT TO BE RECEIVED AT THE PLACE DESIGNATED FOR THE RECEIPT OF OFFERS PRIOR TO THE HOUR AND DATE SPECIFIED MAY RESULT IN REJECTION OF YOUR OFFER. If by virtue of this amendment you desire to change an offer already submitted, such change may be made by telegram or letter, provided each telegram or letter makes reference to the solicitation and this amendment, and is received prior to the opening hour and date specified.
12. ACCOUNTING AND APPROPRIATION DATA (if applicable)
13. THIS ITEM APPLIES ONLY TO MODIFICATIONS OF CONTRACTS/ORDERS,
IT MODIFIES THE CONTRACT/ORDER NUMBER AS DESCRIBED IN ITEM 14.
| [ ] |
| A. this change is issued pursuant to: |
the changes set forth in item 14 are made in the contract order no. in item 10a.
| [ ] |
| B. the above numbered contract/order is modified to reflect the administrative changes (such as changes in paying office, |
appropriation data, etc.) set forth in item 14, pursuant to the authority of far 43.103(b).
| [ ] |
| C. this supplemental agreement is entered into pursuant to authority of: |
| [ ] |
| D. other (specify type of modification and authority ) |
E. IMPORTANT: Contractor [ ] is, [ ] is not required to sign this document and return copy(s) to the issuing office.
14. DESCRIPTION OF AMENDMENT/MODIFICATION
A non-mandatory pre-proposal meeting and site showing was held June 16, 2009. A list of meeting attendees will be posted to FedBizOpps.
See the folowing page for changes and clarifications.
The time for receipt of proposals is not changed. It remains as 4:30 pm on July 10, 2009
Except as provided herein, all terms and conditions of the document referenced in Item 9A or 10A, as heretofore changed, remain unchanged and in full force and effect.
| 15A. NAME AND TITLE OF SIGNER (type or print) |
| 16A. NAME AND TITLE OF CONTRACTING OFFICER (type or print) |
MARCIA O’CONNOR
| 15B. CONTRACTOR/OFFEROR |
| 15C. DATE SIGNED |
| 16B. UNITED STATES OF AMERICA |
| 16C. DATE SIGNED |
| BY: /s/ Marcia O’Connor |
| 6/30/09 |
(signature of authorized person)
(signature of Contracting Officer)
| NSN 7540-01-152-8070 |
| 30-105 |
| SF 30 (REV. 10/83) |
PRESCRIBED BY GSA/PREVIOUS EDITION UNUSABLE
FAR (48 CFR) 53.243
Solicitation AG-435H-S-09-0009
Rabun Beach Bathhouse, Loop 1
Amendment No. 1
Make the following changes:
Solicitation, page 3. Add to the Item description “including the demolition of two existing bathhouses.”
Specifications Section 01 07 00
Change 3.02 Laying Out The Work, item A, to read “The Contractor shall stake the building location on the ground.”
Specification Section 04 20 00
2.01 Concrete Masonry Units
Add: 3. Color as selected by COR from manufacturer’s full range.
2.02 Mortar and Grout Materials
Add: E. Color as selected by COR from manufacturer’s full range.
3.03 Coursing
C. Concrete Masonry Units
Delete 1 - 3 and replace with: A. Refer to the drawings for bond and strike.
Specification Section 07 61 00
Delete the following:
3.03 Installation – Eave (Ice Dam) Protection
Questions and Answers
How is the brush pile and other slash to be handled?
The existing brush pile will be removed by the Forest Service before work starts. Contractor can grind and chip all stumps and any additional clearing slash created by his operations. Larger non-merchantable material will be scattered below the site.
How shall the grading be done after demolition of Building 1? Is the retaining wall to be removed? Is fill dirt required?
The building, slab and retaining wall are to be removed. The site is to be re-graded to blend into the existing ground. No material is figured to be imported to the site.
Sheet P-1 Plumbing Fixture Schedule lists a drinking fountain, but one is not included in the plumbing schematic.
No drinking fountain is required. The Schedule is a standardized schedule used by the Forest Service; the schematic is specific to this project.
Which type of block is to be used? Sheet A-1 states Split Ribbed but Sheet A-2 states Split Face.
Split Ribbed block shall be used.