Specs.pdf

PDF 13 KB Posted

Attached to
Warren Tract #49340 Culvert Replacement Federal contract opportunity
Solicitation number
AG-3395-S-09-0036
Issued by
Department of Agriculture Forest Service R9-Eastern Region

About this file

Special Project Specifications

View the file

Other files for this federal contract opportunity

Other files attached to Warren Tract #49340 Culvert Replacement, newest first.
File Type Posted
1985RDSPECS.pdf PDF
Short_Set.pdf PDF
Solicitation_AG-3395-S-09-0036 Warren Tract Culvert.pdf PDF
Plans.pdf PDF
VA13.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Special Project Specifications

GWJ105.1 (8/94)

105.03 First paragraph, change the first sentence to read:

Sampling

& Testing "For the contractor-furnished source(s) listed below, the contractor shall submit weight tickets which state Virginia Department of Transportation (VDOT) gradation and are in compliance with same Quality Assurance Program. This requirement constitutes aggregate source certification for sampling and testing in accordance with AASHTO requirements through the VDOT sampling and testing program. However, the VDOT quality assurance program shall not relieve the contractor of the responsibility for furnishing material which conforms to the specifications and may be rejected as non-compliant in whole or part.

GWJ106.1 (1/87)

106.02 Add: "The tonnage for aggregate weighed for payment may be reduced, if

Determination moisture content in excess of 12 percent.

of Quantities

603.5 (9/85)

603.08 Delete the last sentence of the second paragraph and add:

Backfilling

"The density shall be Method A, B, or C as shown in the SCHEDULE

OF ITEMS."

Add the following method after Method B.

"Method C. Backfill density shall be that obtained by compacting each layer with mechanical equipment designed for this purpose.

Compaction shall continue until visual displacement of each layer ceases."

GWJ625.1 (1/98)

625.03 In the second sentence, after the word "frozen" add the words "or snow

Seeding covered."

Seasons

Add the following: "All disturbed areas shall be seeded and mulched either temporarily or permanently within 7 months of disturbance. The Contractor shall notify the COR at least 24 hours prior to all seeding."

625.05 Add: "The seed mixture shall be uniformly applied as follows:

Application

Methods for

Seed, Fertilizer, & Limestone Seed Mixture

Material Quantity/Acre

Perennial Rye Grass

(Manhatten, Pennfire, or Linn)

40 lb.

*Flatpea (Lathco) 30 lb.

*White Dutch Clover 4 lb.

Creeping Red Fescue 10 lb.

Annual Ryegrass 10 lb.

Fertilizer (10-10-10) 1500 lb.

Agricultural Lime 3000 lb.

Mulch

Wood or Cellulose Fiber or Recycled Paper or

Hay or Straw

2000 lb.

4000 lb.

*To be innoculated per manufacturer. Germination plus hard seed must be equal to or greater than 75% and the percentage of hard seed no greater than 15%.

When seeding from October 15 to March 1, 50 lb/acre of Cereal Rye (Abruzzi) shall be added to the mixture."