PROJECT STATEMENT OF WORK

1. CONTRACT PROJECT:

A. Project Title: Install Six Miles of 4-Wire Fence.

B. Project Location: USDA-Agricultural Research Service (USDA-ARS) Central

Plains Experimental Range, near 18908 Weld County Road 114 Nunn, CO.

2. PROJECT CONTACT PERSONS:

A. CONTRACTING OFFICER (CO):

Jeff Ridenour Tel. No.: (309) 363 5914

USDA, ARS, WBSC

1815 North University Street Email: Jeffery.Ridenour@ars.usda.gov Peoria, IL 61604

B. ENGINEERING PROJECT MANAGER (EPM):

Greg Graham Tel. No.: (970) 492-7025 USDA, ARS, WBSC Fax No.: (970) 492-7049 2150 Centre Avenue, Email: Greg.Graham@ars.usda.gov Building D, Suite 310, Fort Collins, CO 80526

C. RESEARCH PROGRAM REPRESENTATIVES (RPR):

Dr. Justin Derner Tel. No.: (307) 772-2433 Director, CPER Cell No.: (307) 631-5928 8408 Hildreth Road Email: Justin.Derner@ars.usda.gov Cheyenne, WY 82009

D. ADMINISTRATIVE OFFICERS (AO):

Donna Martin Tel. No.: (970) 492-7701 Administrative Officer Email: Donna.Martin@ars.usda.gov Center for Agricultural Resources Research (CARR) 2150 Centre Ave., Building D, Suite 330

E. ADMINISTRATIVE CONTRACTING OFFICER (ACO):

Shannon Boyd Tel. No.: (970) 492-7704 Contract Specialist Email: Shannon.Boyd@ars.usda.gov Center for Agricultural Resources Research (CARR) 2150 Centre Ave., Building D, Suite 330

F. SAFETY AND OCCUPATIONAL HEALTH MANAGER (SOHM):

Phil Smith Tel. No.: (979) 260 - 9449 USDA, ARS, WBSC Email: Phil.Smith@ars.usda.gov mailto:Jeffery.Ridenour@ars.usda.gov mailto:Greg.Graham@ars.usda.gov mailto:Justin.Derner@ars.usda.gov mailto:Donna.Martin@ars.usda.gov mailto:Shannon.Boyd@ars.usda.gov mailto:Phil.Smith@ars.usda.gov

1001 Holleman Drive East College Station, TX 77840

3. SCOPE OF WORK:

A. Base Bid is to Install 6 miles of 4-Wire Fence. Installation includes wood post installation, and 4-Wire installation of 3 Barbed Wires, and 1 Smooth.

B. 4-wire Fence with Wood Posts as specified in the attached file “Technical Statement of Work Fence CPER 20161220.pdf”

4. RELEVANT DOCUMENTS

A. Attached Documents: The Consultant shall use all documents marked by an “X” in preparing the required contract documents.

[X] Technical Specifications “Technical Statement of Work Fence CPER 20161220.pdf” [X] Location Maps, Plans, and Photos “CPER Fence Maps Plans Photos 2017 Project.pdf”.

5. PROJECT REQUIREMENTS:

A. The CONTRACTOR shall install Government Furnished Components: Wood Posts, Barbed Wire, Screw-In Deadman Anchors, Braces, and Steel Posts as specified in Technical Statement of Work.

B. The CONTRACTOR shall transport Government Furnished Components from the Storage Yard near the Office to the Fence sites.

6. GENERAL REQUIREMENTS:

A. Coordination and Assistance

1. Coordination and Assistance between the Contractor, Contractor's personnel and Sub-Contractors, Contracting Officer, Administrative Contracting Officer, Contracting Officer's Representative, Location Monitor, and Research Personnel on the following items will keep all appropriate personnel involved to expedite this project for everyone’s benefit.

B. Notice to Proceed

1. Notice to proceed from the Contracting Officer is needed before the

Contractor should incur any costs and before any work is done on site.

C. Correspondence

1. Correspondence between the Contractor, Contracting Officer, Administrative Contracting Officer, and Contracting Officer’s Representative should be dated, logged, and copies kept at the originator’s office.

D. Progress schedule

1. Progress schedule should be completed and submitted to the Contracting

Officer before the Pre-Construction Conference.

E. Pre-Construction Conference.

1. Schedule: The Pre-construction Conference with the Contracting Officer’s Representative.

2. Attendees shall include the Contracting Officer's Representative, the Contractor, Contractor's superintendent, Location Monitor, and others.

3. Agenda shall include the following:

a. Introductions of Attendees, with designation for 24 hour calls, by the

Contracting Officer’s Representative and the Contractor.

b. Facilities normal working hours are 8 to 5.

c. Allowable Contractor’s use of Premises, Office, Work, and Storage areas with safety, housekeeping, and security procedures.

d. Allowable Contractor’s equipment and material deliveries.

e. Contractor’s Progress Schedule and coordination items for any utility outages or hazardous materials.

f. Due to the size of this Project, the Materials, Products, Installation

Procedures, Testing Procedures, etc. shall meet commercial standards and shall be reviewed if requested by the Contractor or the Contracting Officer’s Representative requests a specific item, otherwise review will be at the Final Inspection.

g. Contractor’s Inspection Procedure, including field testing and approvals with a remedial process for any deficiencies.

h. Government’s Quality Assurance Program of random inspections and notifying the Contractor of any noted deficiencies. This does not relieve the Contractor from requirements of the Contract.

i. Procedures for the Contractor to submit Applications for Payment.

4. Safety.

a. Contractor's Safety Competent Person designation will be made at the Pre- Construction Conference.

b. Past safety record will be used as an evaluating factor in future contracts.

c. Request a copy of past 3 yrs OSHA 300A Summary of Work Related

Injuries and Illnesses.

d. Investigate past OSHA safety inspections using the establishment search

(http://www.osha.gov/pls/imis/establishment.html ).

e. Request a copy of any OSHA training course documentation for contractor and his/her employees.

f. Request copy of relevant safety plans.

g. Contractor will be required to hold at least weekly safety meetings.

h. Contractor and his employees will be required to follow all requirements of

29 CFR 1926 OSHA Standards for the Construction Industry.

i. All relevant PPE as dictated by the hazards present must be worn by the contractor and all employees working on the job site.

j. Location Monitor will occasionally walk the site with an eye to safety.

k. Possible Hazards of this Contract are:

1. Fence Wire Stretcher.

2. Fence Post Powered Augers.

3. Loading and Hauling.

http://www.osha.gov/pls/imis/establishment.html

F. Operations and Storage Areas

1. Water, gas, electricity are available on the site.

2. Toilet: Contractor shall supply his or her toilet facilities, wash facilities, drinking water, and all necessary disposable materials, comply with regulations and health codes for the type, number, location, operation, and maintenance of fixtures. The COR can waive this requirement.

G. Cleaning Up

1. Debris and rubbish shall be removed from the site daily. Upon the end of the work day, the entire area of the contract work shall be cleaned of all excess materials, dirt, rubbish, and debris.

2. Transportation of debris shall be in a manner as to prevent spillage on street or adjacent areas.

H. Utilities

1. Utilities are to the office and can be used reasonably.

I. Specifications and Drawings.

1. No scaling. Do not scale drawings for dimensions.

J. Schedules and Coordination.

1. Coordination: Coordinate construction activities with the Contracting

Officer's Representative to be in compliance with the Scheduling Requirements. Coordination meetings shall be held once a week usually, but the COR can change the time period depending on the amount of activity by the Contractor. The agenda shall include accomplishments, problems, and solutions since the previous meeting. The Contractor shall prepare and distribute minutes of progress meetings. No later than 3 days after each meeting, the Contractor shall provide a copy of the minutes to the COR.

2. Monitoring the Progress Schedule: The Contractor or the COR shall inform the CO if the Contractor is behind on the schedule, why and what is planned to get back on schedule, so the CO can take appropriate action if needed.

K. Quality Assurance.

1. Required Submittals will be noted in the Statement of Work or in the

Specification section that is applicable. Contracting Officer can request additional submittals on contract items when needed. A submittal form in Word format, will be provided upon request after contract award.

2. Construction Inspector’s Daily Reports are recommended with the Contractor’s standard form. The Contractor shall complete and submit the daily reports to the COR weekly, on the first working day of the following week. The COR can waive the requirement for daily reports, at their discretion.

L. Protection of Existing Equipment, Utilities, and Improvements.

1. Contractor is responsible for protection and restoration if damage occurs. See

Protection of Existing Vegetation, Structures, Equipment, Utilities, and Improvements (FAR 52.236-9) (APR 1984) in Section H - Special Contract Requirements.

4. RELEVANT DOCUMENTS
1. Coordination and Assistance between the Contractor, Contractor's personnel and Sub-Contractors, Contracting Officer, Administrative Contracting Officer, Contracting Officer's Representative, Location Monitor, and Research Personnel on the following...
a. Introductions of Attendees, with designation for 24 hour calls, by the Contracting Officer’s Representative and the Contractor.
b. Facilities normal working hours are 8 to 5.
c. Allowable Contractor’s use of Premises, Office, Work, and Storage areas with safety, housekeeping, and security procedures.
d. Allowable Contractor’s equipment and material deliveries.