Attch_5_Sample_Task_Order_Work_Descriptions.docx
DOCX document 24 KB Posted
- Attached to
- Marienville RD ATV Heavy Maintenance
- Solicitation number
- AG-24H8-S-16-0009
About this file
Attch 5 Sample Task Order Work Descriptions
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Questions-Answers_041216.docx | DOCX document | |
| Questions-Answers_040416.docx | DOCX document | |
| Attch_1_Specifications.docx | DOCX document | |
| Attch_3_Timberline_Map.pdf | ||
| Attch_6_GovtProvidedTechnicalProposalForms.docx | DOCX document | |
| Attch_4_DBWD_PA160004_021216_PA4_Heavy_and_Highway_McKean.docx | DOCX document | |
| AG-24H8-S-16-0009_Complete.pdf | ||
| Attch_2_Marienville_Map.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Marienville Trail Heavy Maintenance Marienville ATV Trail Rehab Allegheny National Forest
Trail Log - Work Descriptions
Marienville ATV and Timberline ATV Trail Repair Sites
SPECIFIED WORK
a. Description of Work:
Placement of specified stone to 1 site on Marienville ATV Trails and 2 sites on Timberline ATV trails for repairs.
Marienville ATV Trail
Station Trail Log/Work Description
67+00 – 74+00 Trail Reconstruction, dewater deep holes, apply R4 as a base (184 tons) and apply PA2A surfacing (23 tons) This stone is furnished and stockpiled at the stone pit at the end of FR 396.
Timberline ATV Trail “A” Loop
Station Trail Log/Work Description
395+00 – 397+00 Apply 4” PA 2A surfacing (46 tons) This stone is furnished and stockpiled at the end of FR 338A (Sta. 431+55)
396+00 Install 16” x 16’ steel casing, apply 11.5 Tons PA 2A (Stone furnished and stockpiled at the end of FR 338A (Sta. 431+55)
403+60 – 405+60 Apply 4” PA 2A surfacing (46 tons) This stone is furnished and stockpiled at the end of FR 338A (Sta. 431+55)
410+60 – 412+60 Trail Reconstruction in new location, apply R4 as base (46 Tons) and apply PA 2A surfacing (34.5 Tons). Decommission the existing trail. This stone is furnished and stockpiled at the end of FR 338A (Sta. 431+55)
422+00 – 424+00 Apply 4” PA 2A surfacing (46 tons) This stone is furnished and stockpiled at the end of FR 338A (Sta. 431+55)
Timberline ATV Trail “D” Loop
Station Trail Log/Work Description
180+10 – 181+10 Apply 4” PA 2A surfacing (23 tons) This stone is furnished and stockpiled at the intersection of trail and FR 339 (Sta. 180+00)
188+30 – 192+30 Trail Reconstruction,dewater deep holes, apply R4 as base (46 Tons) and apply PA 2A surfacing (92 Tons) This stone is furnished and stockpiled at the intersection of trail and FR 339 (Sta. 180+00)