Appendix D
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| Revised_Nelli_Schedule_of_Items.pdf | ||
| Nelli_Amendment_0002.pdf | ||
| Nelli_Stew_amendment_001.pdf | ||
| Attachment_1_Nelli_Stew_Appendix_A.docx | DOCX document | |
| Attachment_4_Service_Wage_Determination_77-0209.txt | TXT text file | |
| Attachment_1_Nelli_Stew_Appendix_C.docx | DOCX document | |
| Attachment_1_Nelli_Stew_Appendix_B_Tree_Measurement.docx | DOCX document | |
| Attachment_3_fire_clauses_r6-fs-6300-52.doc | DOC document | |
| Nelli_IRSC_RFP_Construction.pdf | ||
| Attachment_2_NelliStewardshipContractAreaMap.pdf | ||
| Attachment_4_Construction_General_Decision_WA1.txt | TXT text file |
Show all 11
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Forest Service Supplimental Specification List Page 1 of 2
1600 1600 1600 1600 1600 1601 1601 1603 1611
REV DATE 000 212 216 217 281 000 232 000 000
X X X X X X X X X
101 01 Meaning of Terms 1/22/2009 X X X X X X X X X
101 01 Meaning of Terms 1/22/2009 X X X X X X X X X
101 03 Abbreviations and Symbols 6/16/2006 X X X X X X X X X
101 04 Symbols 3/29/2007 X X X X X X X X X
101 04 Definitions 11/6/2007 X X X X X X X X X
X X X X X X X X X
102 00 Delete 102 in its entirety 2/16/2005 X X X X X X X X X
X X X X X X X X X
103 00 Intent of Contract 2/16/2005 X X X X X X X X X
X X X X X X X X X
104 00 Deletions to 104 6/16/2006 X X X X X X X X X
104 03 Specifications and Drawings. 1/22/2009 X X X X X X X X X
104 03 Specifications and Drawings 2/22/2005 X X X X X X X X X
104 06 Use of Roads by Contractor 2/17/2005 X X X X X X X X X
X X X X X X X X X
105 02 Material Sources 1/18/2007 X X X X X X X X X
105 05 Use of Material Found in the Work 5/12/2004 X X X X X X X X X
X X X X X X X X X
106 01 Conformity with Contract Requirements 7/31/2007 X X X X X X X X X
106 07 Partial and Final Acceptance 5/11/2004 X X X X X X X X X
X X X X X X X X X
107 02 Protection and Restoration of Property and Landscape 2/17/2005 X X X X X X X X X
107 05 Responsibility for Damage Claims 5/11/2004 X X X X X X X X X
107 06 Contractor Responsibility for Work 6/16/2006 X X X X X X X X X
107 08 Sanitation, Health & Safety 3/29/2005 X X X X X X X X X
107 09 Legal Relationship of the Parties 6/16/2006 X X X X X X X X X
107 10 Environmental Protection 6/16/2006 X X X X X X X X X
107 11 Protection of Forests, Parks, and Public Lands 2/17/2005 X X X X X X X X X
X X X X X X X X X
108 00 Delete Section 108 in entirety 2/16/2005 X X X X X X X X X
X X X X X X X X X
109 00 Deletions 2/17/2005 X X X X X X X X X
109 02 Measurement Terms and Definitions 6/16/2006 X X X X X X X X X
X X X X X X X X X
151 03 Payment 8/5/2005 X X X X X X X X X
155 00 Contractor Quality Control Plan, Records 5/11/2004 X X X X X X X X X
156 00 Complete specification 4/17/2007 X X X X X X X X X
ROAD NUMBER
NELLI STEWARDSHIP
SECTION NO & TITLE
101 - Terms, Format, and Definitions
102 - Bid, Award, and Execution of Contract
151 - Mobilization
155 - Schedules for Construction Contracts
156 - Public Traffic
104 - Control of Work
105 - Control of Material
106 - Acceptance of Work
107 - Legal Relations and Responsibility To the Public
108 - Prosecution and Progress
109 - Measurement and Payment
103 - Scope of Work
All specifications not included in the specification listing, but included by reference, are applicable. "X" denotes applicable standard and/or supplemental specifications. The supplemental shown on the specification list are physically attached."
Forest Service Supplimental Specification List Page 2 of 2
1600 1600 1600 1600 1600 1601 1601 1603 1611
REV DATE 000 212 216 217 281 000 232 000 000
ROAD NUMBER
NELLI STEWARDSHIP
SECTION NO & TITLE
170 00 Complete Specification 3/30/2005
201 00 Deletions 8/5/2009 X X X X X X X X X
201 01 Description 2/18/2005 X X X X X X X X X
201 04 Clearing 2/22/2005 X X X X X X X X X
201 06 Disposal 2/18/2005 X X X X X X X X X
203 01 Description 2/25/2005 X X X X X X X X X
203 04 Removing Material 2/18/2005 X X X X X X X X X
203 05 Disposing of Material 2/18/2005 X X X X X X X X X
203 05 Disposing of Material 2/18/2005 X X X X X X X X X
203 05 Disposing of Material 12/18/2004 X X X X X X X X X
203 05 Disposing of Material 2/24/2005 X X X X X X X X X
203 08 Payment 2/24/2005 X X X X X X X X X
204 00 Complete Specification 3/26/2009 X X X X
209 10 Backfill 10/23/2007 X X
209 11 Compacting 2/24/2005 X X
251 03 General 8/5/2009 X
303 01 Description 3/2/2005 X X X X X X X X
303 06 Aggregate & Asphalt Surface Reconditioning 8/5/2008 X X X X X X X X
303 07 Roadway Reconditioning 3/2/2005 X X X X X X X X
303 11 Measurement 3/29/2005 X X X X X X X X
322 00 Complete Specification 10/14/2011 X X X
602 03 General 3/17/2010
607 04 Cleaning Culverts in Place 5/1/2013 X X X X X X
635 03 General 5/13/2004 X X X X X X X X X
703 05 Subbase, Base, & Surface Course Aggregate 8/14/2009 X X X
703 07 FLH FP-03 Correction metric uscu 3/2/2005 X X X
703 10 Flakiness Index and Adherent Coatings 4/11/2011 X X X
705 02 Riprap Rock 8/5/2009 X
718 02 Protective Overlay Film and Edge Film 3/2/2005 X X X X X X X X X
718 05 Aluminum Panels 8/5/2009 X X X X X X X X X
322 - Minor Aggregate Courses
602 - Culverts and Drains
170 - Develop Water Supply and Watering
201 - Clearing and Grubbing
203 - Removal of Structures and Obstructions
204 - Excavation and Embankment
209 - Structure Excavation and Backfill
251 - Riprap
303 - Road Reconditioning
607 - Cleaning, Reconditioning, and Repairing Existing Drainage Structures
635 - Temporary Traffic Control
703 - Aggregate
705 - Rock
718 - Traffic Signing and Marking Material
All specifications not included in the specification listing, but included by reference, are applicable. "X" denotes applicable standard and/or supplemental specifications. The supplemental shown on the specification list are physically attached."
Table of Contents
Table of Contents
Preface
101.01 Meaning of Terms
101.01 Meaning of Terms
101.03 Abbreviations
101.04 Definitions
101.04 Definitions
102 - Bid, Award, and Execution of Contract
102 Bid, Award, and Execution of Contract
103 - Scope of Work
Deletions
104 - Control of Work
Deletions
104.03
104.06 Use of Roads by Contractor
104.07 Other Contracts
105 - Control of Material
105.02 Material Sources
105.02(a) Government-provided sources
105.02(a) Government Provided Sources
105.02(a) Government Provided Sources
105.02 Material Sources
105.02(a) Contractor-provided sources
105.05 Use of Material Found in the Work
106 - Acceptance of Work
106.01 Conformity with Contract Requirements
106.07 Delete
107 - Legal Relations and Responsibility to the Public
107.05 Responsibility for Damage Claims
107.06 Contractor’s Responsibility for Work
107.08 Sanitation, Health, and Safety
107.09 Legal Relationship of the Parties
107.10 Environmental Protection
108 - Prosecution and Progress
108 Delete
109 - Measurement and Payment
109 Deletions
109.02 Measurement Terms and Definitions
155 - Schedules for Construction Contracts
155 Delete
156 - Public Traffic
170 - Develop Water Supply and Watering
201 - Clearing and Grubbing
201.01 Description
201.04 Clearing. (c)
201.06 Disposal
203 - Removal of Structures and Obstructions
203.01 Description
203.04 Removing Material
203.05 Disposing of Material
203.05 Disposing of Material
204 - Excavation and Embankment
209 - Structure Excavation and Backfill
209.10 Backfill
209.11 Compacting
Table 209-1 Sampling and Testing Requirements
251 - Riprap
251.03 General
303 - Road Reconditioning
303.01 Work
303.06 Aggregate Surface Reconditioning
303.06 Asphalt and Aggregate Surface Reconditioning
303.07 Roadway Reconditioning
303.10 Measurement
322 - Minor Aggregate Courses
602 - Culverts and Drains
602.03 General
607 - Cleaning, Reconditioning, and Repairing Existing Drainage Structures
607.04 Cleaning Culverts in Place
635 - Temporary Traffic Control
635.03 General
703 - Aggregate
703.05 Subbase, Base, Surface Course, and Screened Aggregate
Table 703-2 Correction
703.10(e) Flakiness Index
703.10(i) Adherent Coating
705 - Rock
705.02 Riprap Rock
718 - Traffic Signing and Marking Material
718.05 Aluminum Panels
Preface
Preface_wo_03_15_2004_m
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of
National Forest System Roads.
101 - Terms, Format, and Definitions
101.00_nat_us_07_25_2005
101.01_nat_us_01_22_2009
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.01_nat_us_01_22_2009
101.01 Meaning of Terms
Delete all references to the FAR (Federal Acquisition Regulations) in the specifications.
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association
Mine Safety and Health Administration
National Institute of Standards and Technology
National Electrical Safety Code
West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
mp Milepost ppm Part Per Million
101.04_nat_us_03_29_2007
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
http://www.nist.gov/
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition
Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or
“design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96
Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S.
Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the
Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36
CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
101.04_nat_us_11_06_2007
101.04 Definitions.
Delete the following definitions:
Contract Modification
Day
Notice to Proceed
Solicitation
102 - Bid, Award, and Execution of Contract
102.00_nat_us_02_16_2005
102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work
103.00_nat_us_02_16_2005
Deletions
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work
104.00_nat_us_06_16_2006
Deletions
Delete Sections 104.01, 104.02, and 104.04.
104.03_nat_us_02_22_2005
104.03 Drawings and Specifications
Delete subsection 104.03
104.03_nat_us_01_22_2009
104.03 Specifications and Drawings.
Delete 104.03.
104.06_nat_us_02_17_2005
Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
104.07_nat_us_02_17_2005
Add Subsection.
104.07 Other Contracts.
Example: The Federal Highway Administration is administering and is intending to award a contract for the reconstruction of 3 1/2 miles of Salmon la Sac Road approximately 5 miles north of this project. Schedule activities to assure no delays or interference to the operations of the
Federal Highway Administration contract.
105 - Control of Material
105.02_nat_us_01_18_2007
105.02 Material Sources.
105.02(a) Government-provided sources.
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.02_nat_us_02_17_2005
105.02(a) Government Provided Sources.
If the Contractor elects to obtain material from (Material Source Number or name) the following applies:
(a)
(b)
(c)
105.02_nat_us_02_17_2005
105.02(a) Government Provided Sources.
(a) Government-provided sources. Add the following:
Government-provided sources for this project are identified as follows:
(1) Government-provided mandatory sources.
Rock slough material from road 1611000 MP 0.67 & 0.74
Obtain material for use as Pit Run Aggregate, Paid for under pay item 20429 End Haul to be used on 1601232 road at MP 0.20 and 0.23 on the fillslope, and in the production of aggregates under Sections (301/401/411/etc.)
105.02_nat_us_03_08_2007
105.02 Material Sources.
105.02(a) Contractor-provided sources.
All material (e.g., soil, gravel, sand, borrow, aggregate, etc.) transported onto National Forest
System land or incorporated into the work will be weed-free. The Contracting Officer may request written documentation of methods used to determine the weed-free status of any and all materials furnished by the contractor. Contractor-provided expertise and methods to establish weed-free status must be appropriate for the weeds of concern in the local area. The following applies to this contract:
A Forest Service weed specialist will inspect proposed sources to determine weed-free status.
Provide the Contracting Officer written notification of proposed material sources _____ days prior to use. Written approval of the specific source will be provided to the contractor. If weed species are present in the proposed source, appropriate mitigation measures may allow conditional use of the source as required by the Contracting Officer.
105.02_nat_us_02_17_2005
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work
106.01_nat_us_07_31_2007
106.01 Conformity with Contract Requirements.
Delete Subsection 106.01 and substitute the following:
References to standard test methods of AASHTO, ASTM, GSA, and other recognized standard authorities refer to the methods in effect on the date of solicitation for bids.
Perform all work to the lines, grades, cross-sections, dimensions, and processes or material requirements shown on the plans or specified in the contract.
Incorporate manufactured materials into the work according to the manufacturer’s recommendations or to these specifications, whichever is more strict.
Plan dimensions and contract specification values are the values to be strived for and complied with as the design values from which any deviations are allowed. Perform work and provide material that is uniform in character and reasonably close to the prescribed value or within the specified tolerance range. The purpose of a tolerance range is to accommodate occasional minor variations from the median zone that are unavoidable for practical reasons.
When standard manufactured items are specified (such as fence, wire, plates, rolled shapes, pipe conduits, etc., that are identified by gauge, unit mass, section dimensions, etc.), the identification will be considered to be nominal masses or dimensions. Unless specific contract tolerances are noted, established manufacturing tolerances will be accepted.
The Government may inspect, sample, or test all work at any time before final acceptance of the project. When the Government tests work, copies of test reports are furnished to the Contractor upon request. Government tests may or may not be performed at the work site. If Contractor testing and inspection is verified by the Government, the Contractor’s results may be used by the
Government to evaluate work for acceptance. Do not rely on the availability of Government test results for process control.
Acceptable work conforming to the contract will be paid for at the contract unit bid price. Four methods of determining conformity and accepting work are described in Subsections 106.02 to
106.05 inclusive. The primary method of acceptance is specified in each Section of work.
However, work may be rejected at any time it is found by any of the methods not to comply with the contract.
Remove and replace work that does not conform to the contract, or to prevailing industry standards where no specific contract requirements are noted, at no cost to the Government.
(a) Disputing Government test results. If the accuracy of Government test results is disputed, promptly inform the CO. If the dispute is unresolved after reasonable steps are taken to resolve the dispute, further evaluation may be obtained by written request. Include a narrative describing the dispute and a proposed resolution protocol that addresses the following:
(1) Sampling method;
(2) Number of samples;
(3) Sample transport;
(4) Test procedures;
(5) Testing laboratories;
(6) Reporting;
(7) Estimated time and costs; and
(8) Validation process.
If the evaluation requires additional sampling or testing be performed, mutually agree with the Government on witnessing procedures and on sampling and testing by a third party laboratory. Use a third party laboratory accredited by the AASHTO accreditation program.
Provide proof of the laboratory’s accreditation for the test procedures to be used. Do not use the same laboratory that produced the disputed Government test results or that produced the test results used as a basis for the dispute.
The CO will review the proposed resolution protocol and may modify it before final approval and execution.
The Government will use the approved resolution protocol test results to determine the validity of the disputed testing. If the Government test results are validated, the Contractor will be responsible for all costs associated with developing and performing the resolution protocol. If the Government test results are not validated, the Government will be responsible for all costs associated with developing and performing the resolution protocol.
If the validity of the Government test results cannot be determined, the Contractor and
Government will equally share all costs associated with developing and carrying out the resolution protocol.
(b) Alternatives to removing and replacing non-conforming work. As an alternative to removal and replacement, the Contractor may submit a written request to:
(1) Have the work accepted at a reduced price; or
(2) Be given permission to perform corrective measures to bring the work into conformity.
The request must contain supporting rationale and documentation. Include references or data justifying the proposal based on an evaluation of test results, effect on service life, value of material or work, quality, aesthetics, and other tangible engineering basis. The CO will determine disposition of the nonconforming work.
106.07_nat_us_05_11_2004
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public
107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.08_nat_us_03_29_2005
107.08 Sanitation, Health, and Safety
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
107.10_nat_us_06_16_2006
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
Exact time and location of spill including a description of the area involved.
Containment procedures.
Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
108 - Prosecution and Progress
108.00_nat_us_02_16_2005
108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment
109.00_nat_us_02_17_2005
109 Deletions
Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02_nat_us_06_16_2006
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
155 - Schedules for Construction Contracts
155.00_nat_us_05_11_2004
155 Delete.
Delete Section 155 in its entirety.
156 - Public Traffic
156.00_nat_us_04_17_2007
Delete Section 156 in its entirety and replace with the following:
Description
156.01 This work consists of controlling and protecting public traffic adjacent to and within the project.
Material
156.02 Conform to the MUTCD and the following Sections and Subsections:
Construction sign panels 633
Retro-reflective sheeting 718.01
Temporary concrete barrier 618
Temporary plastic fence 710.11
Temporary traffic control devices 718.22
156.03 General. Unless otherwise provided for in Table 156-1, keep existing roads open to all traffic during road improvement work, and maintain them in a condition that will adequately accommodate traffic. Delays may not exceed 60 minutes at any one time followed by an open period of no less than 120 minutes.
Perform no work that interferes or conflicts with traffic or existing access to the roadway surface until a traffic control plan has been approved. Post construction signs and traffic control devices in conformance with MUTCD. All required signs will be in place and approved prior to beginning work on project.
If the Contractor agrees in writing to allow public traffic to use a new road being constructed prior to completion, it will be considered an existing road for traffic control purposes.
156.04 Temporary Traffic Control. Install and maintain temporary traffic control devices adjacent to and within the project as required by the approved traffic control plan and the
MUTCD. Install and maintain traffic control devices as follows:
(a) Furnish and install traffic control devices before the start of construction operations.
(b) All detours outside of clearing limits will be approved in writing by the Contracting
Officer as part of the traffic control plan.
(c) Install only those traffic control devices needed for each stage or phase.
(d) Relocate temporary traffic control devices as necessary.
(e) Remove devices that no longer apply to the existing conditions.
(f) Immediately replace any device that is lost, stolen, destroyed, or inoperative.
(g) Keep temporary traffic control devices clean.
(h) Remove all temporary traffic control devices upon contract completion or when approved.
(i) When required, use flaggers certified by the American Traffic Safety Services
Association, the National Safety Council, the International Municipal Signal
Association, a state agency, or other acceptable organization. Perform the work described under MUTCD Part 6. Use type III, VII, VIII, or IX retroreflective sheeting on flagger paddles. Do not use flags. Flaggers must wear high visibility safety apparel as required by MUTCD 6E.02.
156.05 Temporary Closures. Road segments may be closed as shown in Table 156-1. The maximum consecutive days of closure shall be followed by a minimum number of consecutive days open to traffic as shown. Maintain traffic control devices during closure period(s).
Appropriate barricades and signs will be erected and maintained as shown in the traffic control plan or as otherwise designated.
Prior to closing roads during construction, give written notice to the Contracting Officer at least
10 days in advance.
Table 156-1
Temporary Road Closures
Road
Number
From
Terminus
To
Terminus
Maximum
Consecutive
Days of
Closure
Minimum
Consecutive
Days Open
156.06 Acceptance. Public traffic work will be evaluated under Subsection 106.02.
Measurement and Payment
156.07 Do not measure Public Traffic for payment. Compensation is made as an indirect payment.
170 - Develop Water Supply and Watering
170.00_nat_us_03_30_2005
Description
170.01 This work consists of developing an acceptable water supply, furnishing, hauling, and applying water.
Materials
170.02 Conform to the following subsection.
Water 725.01.
Construction Requirements
170.03 Development of Supply & Access. Develop water supplies and access to the water supplies as required. Use designated water sources or other approved water sources. Before using non-designated water sources, obtain all necessary permissions, water rights, and permits.
170.04 Equipment. Provide mobile watering equipment with watertight tanks of known capacity. Provide for positive control of water application from the driver’s position.
170.05 Application. Apply water uniformly without ponding or washing.
170.06 Acceptance. Developing water supplies and watering will be evaluated under
Subsections 106.02 and 106.04.
Measurement
170.07 Measure the Section 170 items listed in the bid schedule according to Subsection
109.02.
Payment
170.08 The accepted quantities will be paid at the contract price per unit of measurement for the
Section 170 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in this Section. See Subsection 109.05.
201 - Clearing and Grubbing
201.01_nat_us_02_18_2005
201.01 Description
Replace with the following
This work consists of clearing and grubbing within clearing limits and other designated areas.
201.04_nat_us_02_22_2005
201.04 Clearing. (c)
Delete paragraph (c) and replace with the following:
(c) In areas outside the excavation, embankment, and slope rounding limits, cut stumps to within 12 inches or one-third of the stump diameter of the ground, whichever is higher, measured on the side adjacent to the highest ground. For timber sales, stump heights will meet the requirements of the Timber Sale contract.
201.04 Clearing.
Delete subsection (d) and replace with the following:
(d) Do not cut vegetation less than 3 feet tall and less than 3 inches in diameter, that is within the clearing limits but beyond the roadway and not in a decking area, and that does not interfere with sight distance along the road.
Add the following:
(e) Trim branches of remaining trees or shrubs to give a clear height of 14 feet above the roadbed unless otherwise indicated. Trim tree limbs as near flush with the trunk as practicable.
(f) Remove brush from log decks. Deck logs so that logs are piled parallel to one another; can be removed by standard log loading equipment; will not damage standing trees; will not interfere with drainage, and will not roll. Keep logs in log decks free of brush and soil.
201.06_nat_us_02_18_2005
201.06 Disposal.
Delete the first sentence of this subsection and substitute the following:
Dispose of merchantable timber designated for removal according to the provisions of the timber sale contract.
201.06_nat_us_11_09_2005
201.06 Disposal
Delete the first sentence of this paragraph and substitute the following:
Limb and deck logs that meet utilization standards at locations approved by the CO or otherwise designated. Deck logs according to 201.04 (f).
203 - Removal of Structures and Obstructions
203.01_nat_us_02_25_2005
203.01 Description.
Delete and replace with the following:
This work consists of disposing of construction slash and debris, salvaging, removing, and disposing of buildings, fences, structures, pavements, culverts, utilities, curbs, sidewalks, and other obstructions.
203.04_nat_us_02_18_2005
203.04 Removing Material.
Replace the fourth and fifth paragraphs with the following:
Where part of an existing culvert is removed, remove the entire culvert upstream from the removal. The remaining downstream culvert may be left in place if no portion of the culvert is within 12 inches of the subgrade, embankment slope, or new culvert or structure; and the culvert ends are sealed with concrete.
Remove structures and obstructions in the roadbed to 12 inches below subgrade elevation.
Remove structures and obstructions outside the roadbed to 12 inches below finished ground or to the natural stream bottom.
203.05_nat_us_02_24_2005
203.05 Disposing of Material.
Add the following:
(e): Scattering. Scatter pieces of wood less than 3 inches in diameter and 3 feet in length within the clearing limits. Do not place construction slash in lakes, meadows, streams, or streambeds.
Immediately remove construction slash that interferes with drainage structures.
203.05_nat_us_02_18_2005
203.05 Disposing of Material.
Add the following:
(e) Windrowing Construction Slash. Place construction slash outside the roadway in neat, compacted windrows approximately parallel to and along the toeline of embankment slopes. Do not permit the top of the windrows to extend above subgrade. Use construction equipment to matt down all material in a windrow to form a compact and uniform pile. Construct breaks of at least 15 feet at least every 200 feet in a windrow. Do not place windrows against trees. Obtain approval for pioneer roads. A pioneer road may be constructed to provide an area for placement of windrows, provided the excavated material is kept within the clearing limits and does not adversely affect the road construction.
(f) Scattering. Scatter construction slash outside the clearing limits without damaging trees.
Limb all logs. Place logs and stumps away from trees, positioned so they will not roll, and are not on top of one another. Limb and scatter other construction slash to reduce slash concentrations.
(g) Chipping or Grinding. Use an approved chipping machine to grind slash and stumps greater than 3 inches in diameter and longer than 3 feet. Deposit chips or ground woody material on embankment slopes or outside the roadway to a loose depth less than 6 inches. Minor amounts of chips or ground woody material may be permitted within the roadway if they are thoroughly mixed with soil and do not form a layer.
(h) Debris Mat. Use tree limbs, tops, cull logs, split stumps, wood chunks, and other debris to form a mat upon which construction equipment is operated. Place stumps upside down and blend stumps into the mat.
(i) Decking Firewood Material. Remove brush from decks. Limb and deck logs that do not meet Utilization Standards according to Subsection 201.04 as directed by the CO. Cut logs to lengths less than 30 feet. Ensure that logs stacks are stable and free of brush and soil.
(j) Removal to designated locations. Remove construction slash to designated locations.
(k) Piling. Pile construction slash in designated areas. Place and construct piles so that if the piles are burned, the burning will not damage remaining trees. Keep piles free of dirt from stumps. Cut unmerchantable logs into lengths of less than 20 feet.
(l) Placing Slash on Embankment Slopes. Place construction slash on completed embankment slopes to reduce soil erosion. Place construction slash as flat as practicable on the completed slope. Do not place slash closer than 2 feet below subgrade. Priority for use of available slash is for: (1) through fills; (2) insides of curves; and (3) ditch relief outlets.
(m) Hydrological Sensitive Placement. Where required use this method in combination with other designated methods to dispose of material to reduce erosion and to aid in re-vegetation:
1. Place windrow segments on contours, wrap in type I geotextile.
2. Place logs as log erosion barriers on contours. Place logs so that 80% of their length is on the ground surface.
3. Scatter slash on bare or disturbed areas within or outside the clearing limits as directed.
4. Scatter chips or ground woody material on bare or disturbed areas within or outside the clearing limits as directed.
Place stumps in swales or on sites to form planting pockets. Place windrow segments on contours, wrap in type I geotextile.
203.08_nat_us_02_24_2005
203.08 Payment
Add the following:
Disposal of construction slash will be compensated under the designated pay item in Section
201.
204 - Excavation and Embankment
204.00_nat_us_03_26_2009
Replace Section 204 in its entirety with the following:
204.01 This work consists of excavating material and constructing embankments. This includes furnishing, hauling, stockpiling, placing, disposing, sloping, shaping, compacting, and finishing earthen and rocky material.
204.02 Definitions.
(a) Excavation. Excavation consists of the following:
(1) Roadway excavation. All material excavated from within the right-of-way or easement areas, except subexcavation covered in (2) below and structure excavation covered in Sections 208 and 209. Roadway excavation includes all material encountered regardless of its nature or characteristics.
(2) Subexcavation. Material excavated from below subgrade elevation in cut sections or from below the original groundline in embankment sections. Subexcavation does not include the work required by Subsections 204.05, 204.06(b), and 204.06(c).
(3) Borrow excavation. Material used for embankment construction that is obtained from outside the roadway prism. Borrow excavation includes unclassified borrow, select borrow, and select topping.
(b) Embankment construction. Embankment construction consists of placing and compacting roadway or borrow excavation. This work includes:
(1) Preparing foundation for embankment;
(2) Constructing roadway embankments;
(3) Benching for side-hill embankments;
(4) Constructing dikes, ramps, mounds, and berms; and
(5) Backfilling subexcavated areas, holes, pits, and other depressions.
(c) Conserved topsoil. Excavated material conserved from the roadway excavation and embankment foundation areas that is suitable for growth of grass, cover crops, or native vegetation.
(d) Waste. Excess and unsuitable roadway excavation and subexcavation that cannot be used.
204.03 Conform to the following Subsections:
Backfill material 704.03
Select borrow 704.07
Select topping 704.08
Topping 704.05
Unclassified borrow 704.06
Water 725.01
204.04 Preparation for Roadway Excavation and Embankment Construction. Clear the area of vegetation and obstructions according to Sections 201 and 203.
204.05 Reserved.
204.06 Roadway Excavation. Excavate as follows:
(a) General. Do not disturb material and vegetation outside the construction limits.
Incorporate only suitable material into embankments. Replace any shortage of suitable material caused by premature disposal of roadway excavation. Dispose of unsuitable or excess excavation material according to Subsection 204.14.
At the end of each day's operations, shape to drain and compact the work area to a uniform cross-section. Eliminate all ruts and low spots that could hold water.
Retrieve material deposited outside of the clearing limits as directed by the CO. Place unsuitable material in designated areas.
(b) Rock cuts. Blast rock according to Section 205. Excavate rock cuts to 6 inches below subgrade within the roadbed limits. Backfill to subgrade with topping or with other suitable material. Compact the material according to Subsection 204.11
(c) Earth cuts. Scarify earth cuts to 6 inches below subgrade within the roadbed limits.
Compact the scarified material according to Subsection 204.11.
(d) Pioneer Roads. Road pioneering, slash disposal, and grubbing of stumps may proceed concurrently with excavation. Conduct excavation and placement operations so material to be treated under Section 201 will not be incorporated into the roadway unless specified in the slash treatment method. Maintain drainage during pioneering operations.
Remove snow and ice in advance of the work and deposit beyond the roadway limits in a manner that will not waste material or generate sediment. Do not incorporate snow and ice into embankments. Place snow or ice in a manner to prevent resource damage.
204.07 Subexcavation. Excavate material to the limits designated by the CO. Take cross-sections according to Section 152. Prevent unsuitable material from becoming mixed with the backfill. Dispose of unsuitable material according to Subsection 204.14. Backfill the subexcavation with topping, or other suitable material. Compact the material according to
Subsection 204.11.
204.08 Borrow Excavation. Use all suitable roadway excavation in embankment construction.
Do not use borrow excavation when it results in excess roadway excavation. Deduct excess borrow excavation from the appropriate borrow excavation quantity.
Obtain borrow source acceptance according to Subsection 105.02. Develop and restore borrow sources according to Subsection 105.03. Do not excavate beyond the established limits. When applicable, shape the borrow source to permit accurate measurements when excavation is complete.
204.09 Preparing Foundation for Embankment Construction. Prepare foundation for embankment construction as follows:
(a) Embankment less than 4 feet high over natural ground. When designated, remove topsoil and break up the ground surface to a minimum depth of 6 inches by plowing or scarifying. Compact the ground surface according to Subsection 204.11.
(b) Embankments over an existing asphalt, concrete, or gravel road surface. Scarify gravel roads to a minimum depth of 6 inches. Scarify or pulverize asphalt and concrete roads to 6 inches below the pavement. Reduce all particles to a maximum size of 6 inches and produce a uniform material. Compact the surface according to Subsection 204.11.
(c) Embankment across ground not capable of supporting equipment. Dump successive loads of embankment material in a uniformly distributed layer to construct the lower portion of the embankment. Limit the layer thickness to the minimum depth necessary to support the equipment.
(d) Embankment on an existing slope steeper than 1V:3H. Cut horizontal benches in the existing slope to a sufficient width to accommodate placement and compaction operations and equipment. Bench the slope as the embankment is placed and compacted in layers. Begin each bench at the intersection of the original ground and the vertical cut of the previous bench.
204.10 Embankment Construction. Incorporate only suitable roadway excavation material into the embankment. When the supply of suitable roadway excavation is exhausted, furnish unclassified borrow to complete the embankment. Obtain written approval before beginning construction of embankments over 6 feet high at subgrade centerline. Construct embankments as follows:
(a) General. At the end of each day's operations, shape to drain and compact the embankment surface to a uniform cross-section. Eliminate all ruts and low spots that could hold water.
During all stages of construction, route and distribute hauling and leveling equipment over the width and length of each layer of material.
Compact embankment side slopes flatter than 1V:1.75H with a tamping type roller or by walking with a dozer. For slopes 1V:1.75H or steeper, compact the slopes as construction of the embankment progresses.
Where placing embankment on one side of abutments, wing walls, piers, or culvert headwalls, compact the material using methods that prevent excessive pressure against the structure.
Where placing embankment material on both sides of a concrete wall or box structure, conduct operations so compacted embankment material is at the same elevation on both sides of the structure.
Where structural pilings are placed in embankment locations, limit the maximum particle size to 4 inches.
(b) Embankment within the roadway prism. Place embankment material in horizontal layers not exceeding 12 inches in compacted thickness. Incorporate oversize boulders or rock fragments into the 12-inch layers by reducing them in size or placing them individually as required by (c) below. Compact each layer according to Subsection 204.11 before placing the next layer.
Material composed predominately of boulders or rock fragments too large for 12-inch layers may be placed in layers up to 24 inches thick. Incorporate oversize boulders or rock fragments into the 24-inch layer by reducing them in size or placing them individually according to (c) below. Place sufficient earth and smaller rocks to fill the voids. Compact each layer according to Subsection 204.11 before placing the next layer.
(c) Individual rock fragments and boulders. Place individual rock fragments and boulders greater than 24 inches in diameter as follows:
(1) Reduce rock to less than 48 inches in the largest dimension.
(2) Distribute rock within the embankment to prevent nesting.
(3) Place layers of embankment material around each rock to a depth not greater than that permitted by (b) above. Fill all the voids between rocks.
(4) Compact each layer according to Subsection 204.11 before placing the next layer.
(d) Embankment outside of roadway prism. Where placing embankment outside the staked roadway prism, place material in horizontal layers not exceeding 24 inches in compacted thickness. Compact each layer according to Subsection 204.11.
204.11 Compaction. Compact the embankment using one of the following methods as specified:
(a) Compaction A. Use AASHTO T 27 to determine the amount of material retained on a
Number 4 sieve. If there is more than 80 percent retained on the No. 4 sieve use procedure (1).
If there is 50 to 80 percent retained on the No. 4 sieve use procedure (2). If there is less than 50 percent retained on the No. 4 sieve use procedure (3).
(1) Adjust the moisture content to a level suitable for compaction. Fill the interstices around rock with earth or other fine material as practical. Use compression-type rollers at speeds less than 6feet per second and vibratory rollers at speeds less than 3 feet per second.
Compact each layer of material full width with one of the following and until there is no visible evidence of further consolidation.
(a) Four roller passes of a vibratory roller having a minimum dynamic force of
40,000 pounds impact per vibration and a minimum frequency of 1000 vibrations per minute.
(b) Eight roller passes of a 20-ton compression-type roller.
(c) Eight roller passes of a vibratory roller having a minimum dynamic force of
30,000 pounds impact per vibration and a minimum frequency of 1000 vibrations per minute.
Increase the compactive effort for layers deeper than 12 inches as follows:
For each additional 6 inches or fraction thereof, increase the number of roller passes in (a) above by four passes.
For each additional 6 inches or fraction thereof, increase the number of roller passes in (b) and (c) above, by eight passes.
(2) Use AASHTO T 99 to determine the optimum moisture content of the portion of the material passing a No. 4 sieve. Multiply this number by the percentage of material passing a No. 4 sieve, and add 2 percent to determine the optimum moisture content of the material.
Adjust the moisture content of material classified A-1 through A-5 to a moisture content suitable for compaction. Adjust the moisture content of material classified A-6 and A-7 to within 2 percent of the optimum moisture content.
Use compression-type rollers at speeds less than 6 feet per second and vibratory rollers at speeds less than 3 feet per second. Compact each layer of material full width according to
(1) above.
(3) Classify the material according to AASHTO M 145. For material classified A-1 or A-
2-4, determine the maximum density according to AASHTO T 180, method D. For other material classifications, determine the optimum moisture content and maximum density according to AASHTO T 99, method C.
Adjust the moisture content of material classified A-1 through A-5 to a moisture content suitable for compaction. Adjust the moisture content of material classified A-6 and A-7 to within 2 percent of the optimum moisture content.
Use compression-type or vibratory rollers. Compact each layer of material full width to at least 95 percent of the maximum density. Determine the in-place density and moisture content according to AASHTO T 310 or other approved test procedures. When required, use AASHTO T 224 to correct for coarse particles.
(b) Compaction B. Place material by end dumping to the minimum depth needed for operation of spreading equipment. Adjust the moisture content of the material to obtain a mass that will not visibly deflect under the load of the hauling and spreading equipment. Operate compaction equipment over the full width of each layer until there is no visible evidence of further consolidation or, if when a sheepsfoot roller is used, the roller “walks out” of the layer.
Make at least three complete passes.
(c) Compaction C. Place material by end dumping to the minimum depth needed for operation of spreading equipment. Level and smooth each embankment layer before placing the next layers. Operate hauling and spreading equipment uniformly over the full width of each layer. Construct a solid embankment with adequate compaction by working smaller rock and fines in with the larger rocks to fill the voids, and by operating hauling and spreading equipment uniformly over the full width of each layer as the embankment is constructed.
204.12 Ditches. Slope, grade, and shape ditches. Remove all projecting roots, stumps, rock, or similar matter. Maintain all ditches in an open condition and free from leaves, sticks, and other debris.
Form furrow ditches by plowing or using other acceptable methods to produce a continuous furrow. Place all excavated material on the downhill side so the bottom of the ditch is approximately 18 inches below the crest of the loose material. Clean the ditch using a hand shovel, ditcher, or other suitable method. Shape to provide drainage without overflow.
204.13 Sloping, Shaping, and Finishing. Complete slopes, ditches, culverts, riprap, and other underground minor structures before placing aggregate courses. Slope, shape, and finish as follows:
(a) Sloping. Leave all earth slopes with uniform roughened surfaces, except as described in (b) below, with no noticeable break as viewed from the road. Except in solid rock, round tops and bottoms of all slopes including the slopes of drainage ditches. Round material overlaying solid rock to the extent practical. Scale all rock slopes. Slope rounding is not required on tolerance class D though M roads.
If a slide or slipout occurs on a cut or embankment slope, remove or replace the material, and repair or restore all damage to the work. Bench or key the slope to stabilize the slide. Reshape the cut or embankment slope to an acceptable condition.
(b) Stepped slopes. Where required by the contract, construct steps on slopes of 1⅓V:1H to
1V:2H. Construct the steps approximately 18 inches high. Blend the steps into natural ground at the end of the cut. If the slope contains nonrippable rock outcrops, blend steps into the rock.
Remove loose material found in transitional area. Except for removing large rocks that may fall, scaling stepped slopes is not required.
(c) Shaping. Shape the subgrade to a smooth surface and to the cross-section required. Shape slopes to gradually transition into slope adjustments without noticeable breaks. At the ends of cuts and at intersections of cuts and embankments, adjust slopes in the horizontal and vertical planes to blend into each other or into the natural ground.
(d) Finishing. Finish the roadbed to be smooth and uniform, and shaped to conform to the typical sections. Remove unsuitable material from the roadbed and replace it with suitable material. Finish roadbeds to the tolerance class shown in table 204-2.Ensure that the subgrade is visibly moist during shaping and dressing. Scarify to 6 inches below the bottom of low sections, holes, cracks, or depressions and bring back to grade with suitable material. Maintain proper ditch drainage.
For surfaced roads, remove all material larger than 6 inches from the top 6 inches of the roadbed.
For unsurfaced roads, use one of the following methods to finish the roadbed:
(1) Method A. Remove all material larger than 6 inches from the top 6 inches of the roadbed and replace with suitable material.
(2) Method B. Use a vibratory grid roller or approved equal with a minimum weight of 10 tons.