SPECIFICATION_LIST.pdf
PDF 418 KB Posted
- Solicitation number
- AG-04P5-S-16-0010
About this file
Specifications
View the file
Other files
| File | Type | Posted |
|---|---|---|
| StatementofWorkAttach1.pdf | ||
| WageRates.txt | TXT text file | |
| INSTRUCTIONS.pdf | ||
| Solicitation.pdf | ||
| Carpet_andFlooring_Floorplans3.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Specifications
Page | 1
SPECIFICATION LIST
SPECIFICATION NO. DESCRIPTION
Section 01300 Submittals
Section 09650 Resilient Flooring
Section 09680 Carpeting
Page | 2
SECTION 01300
SUBMITTALS
PART 1 – GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.
1.2 SUMMARY
A. This Section includes administrative and procedural requirements for submittals required for performance of the Work, including the following:
1. Contractor’s construction schedule.
2. Product Data.
3. Samples.
4. Quality assurance submittals.
B. Administrative Submittals: Refer to other Division 1 Sections and other Contract Documents for requirements for administrative submittals. Such submittals include, but are not limited to, the following:
1. List of subcontractors.
1.3 DEFINITIONS
A. Coordination Drawings show the relationship and integration of different construction elements that require careful coordination during fabrication or installation to fit in the space provided or to function as intended.
1.4 SUBMITTAL PROCEDURES
A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities. Transmit each submittal sufficiently in advance of performance of related construction activities to avoid delay.
1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.
2. Coordinate transmittal of different types of submittals for related elements of the Work so processing will not be delayed by the need to review submittals concurrently for coordination.
Page | 3
3. Processing: To avoid the need to delay installation as a result of the time required to process submittals, allow sufficient time for submittal review, including time for resubmittals.
B. Submittal Transmittal: Package each submittal appropriately for transmittal and handling. Transmit each submittal from the Contractor to the COR using a transmittal form. The COR will not accept submittals received from sources other than the Contractor.
1. On the transmittal, record relevant information and requests for data. On the form, or separate sheet, record deviations from Contract Document requirements, including variations and limitations. Include Contractor’s certification that information complies with Contract Document requirements.
1.5 CONTRACTOR’S CONSTRUCTION SCHEDULE
A. Prepare a fully developed, horizontal bar-chart-type, Contractor’s schedule. Consult with COR for scheduling conflicts.
1.6 SHOP DRAWINGS
A. N/A.
1.7 PRODUCT DATA
1.8 SAMPLES
A. Submit full-size, fully fabricated Samples cured and finished as specified and physically identical with the material or product proposed. Samples include partial sections of manufactured or fabricated components, cuts or containers of materials, color range sets, and swatches showing color, texture, and pattern.
1. Mount or display Samples in the manner to facilitate review of qualities indicated. Prepare Samples to match the COR’s sample.
a. Product name or name of the manufacturer.
b. Compliance with recognized standards.
1.9 QUALITY ASSURANCE SUBMITTALS
A. Submit quality-control submittals, including design data, certifications, manufacturer’s instructions, manufacturer’s field reports, and other quality-control submittals as required under other Sections of the Specifications.
PART 2 - PRODUCTS
NOT APPLICABLE
Page | 4
PART 3 - EXECUTION
NOT APPLICABLE
END OF SECTION
Page | 5
SECTION 09650
RESILIENT FLOORING
PART 1 - GENERAL
RELATED WORK SPECIFIED ELSEWHERE
Section “Carpeting.”
THIS SECTION INCLUDES THE FOLLOWING:
Vinyl Sheet Flooring
Resilient Wall Base
Resilient Flooring Accessories
QUALITY ASSURANCE
Manufacturer:
Provide each type of resilient flooring (Ninyl Sheet)) and accessories as produced by a single manufacturer, including recommended primers, adhesives, sealants, and leveling compounds.
SUBMITTALS
Submit complete set of manufacturer's samples of each type of floor covering; trim, and base to be used by Contracting Officer’s Representative for selection of colors and patterns.
Submit manufacturer's literature, certification, or other data showing proposed products comply with these Specifications.
Submit 2 copies of manufacturer's recommended maintenance practices for each type of resilient flooring and accessory required.
PROJECT CONDITIONS
Maintain minimum temperature of 70oF (21oC) or more than 95oF (35oC) in spaces to receive resilient flooring for at least 48 hours prior to installation, during installation, and for not less than 48 hours after installation. Store resilient flooring materials in spaces where they will be installed for at least 48 hours before beginning installation.
Subsequently, maintain minimum temperature of 55oF (13oC) in areas where work is completed.
Install resilient flooring and accessories after other finishing operations, including painting, have been completed. Do not install resilient flooring over concrete slab until the latter has been cured and is sufficiently dry to achieve bond with adhesive as determined by resilient flooring manufacturer's recommended bond and moisture test.
Page | 6
PRODUCT DELIVERY AND STORAGE
Deliver materials to project site in manufacturer's original, unopened containers with labels indicating brand names, colors, and patterns, and quality designations legible and intact.
Do not open containers or remove markings until materials are inspected and accepted.
Store and protect accepted materials in accordance with manufacturer's directions and recommendations.
Unless otherwise directed, store materials in original containers at not less than 70oF (2loC) for not less than 24 hours immediately before installation.
APPLICATOR EXPERIENCE
Flooring and related work shall be installed by craftsmen experienced in this trade.
PART 2 - PRODUCTS
VINYL FLOORING
Vinyl Sheet Flooring:
Provide vinyl sheet flooring with filled vinyl plastic wear layer and fibrous backing complying with ASTM F 1303 Type II, Grade 1; ASTM E 84 flame spread 25 or less, ASTM E 662 NBS smoke 450 or less, smoke development 50 or less, and shall be asbestos free.
Thickness: 0.050 inch.
Wearing Surface: Smooth.
Seaming Method: Heat Weld.
Color and Pattern: As selected by Contracting Officer’s Representative from manufacturer’s full range of colors and patterns prepared for vinyl sheet floor covering complying with requirements indicated.
Subject to compliance with requirements, manufacturers offering products which may be incorporated in the work include, but are not limited to, the following:
“Classic Corlon” – Armstrong World Industries
“Foundations” – Congoleum Corporation
“Fields” - Mannington
RESILIENT WALL BASE MATERIALS
Miscellaneous:
Uniform in thickness.
As long as practicable to suit conditions of installation.
Page | 7
Wall Base:
Provide base complying with FS SS-W-40; Type I (rubber) with matching end stops and preformed or molded corner units, and as follows:
Height: 4"
Thickness: 1/8"
Style: Standard top-set cove.
Finish: Matte
Use same material throughout.
Subject to compliance with requirements, manufacturers offering products which may be incorporated in the work include, but are not limited to, the following:
Manufacturers of Rubber Wall Base:
Burke Flooring Products Div., Burke Industries, Inc.
Flexco Div., Textile Rubber Co.
Johnson Rubber Co.
R. C. Musson Rubber Co., Inc.
Roppe Rubber Corp.
ACCESSORIES
Resilient Edge Strips:
1/8" thick, homogeneous vinyl or rubber composition, tapered or bullnose edge, color to match flooring, or as selected by CO from standard colors available; not less than 1" wide.
Thresholds:
Molded or extruded vinyl or rubber.
Lengths as required for dimensions of opening.
Reducers:
Standard vinyl or rubber floor reducer.
Thickness to suit abutting floor covering material by approximately 1 inch wide.
Beveled or tapered edge style.
Adhesives (Cements):
Waterproof, stabilized type as recommended by flooring manufacturer to suit material and substrate conditions.
Leveling and Patching Compounds:
Latex types as recommended by flooring manufacturer.
Page | 8
PART 3 – EXECUTION
DEMOLITION
Remove and furniture and appliances and store for replaceing following flooring installation. Remove existing old flooring and scrape sub-floor surface of any residual adhesive material left behind. Dispose of old flooring properly.
INSPECTION
Require Installer to inspect subfloor surfaces to determine that they are satisfactory. A satisfactory subfloor surface is defined as one that is smooth and free from cracks, holes, ridges, coatings preventing adhesive bond, and other defects impairing performance or appearance.
Concrete Subfloors: Verify that concrete slabs comply with ASTM F 710 and the following:
Slab substrates are dry and free of curing compounds, sealers, hardeners, and other materials that may interfere with adhesive bond. Determine adhesion and dryness characteristics by performing bond and moisture tests recommended by floor covering manufacturer.
Subfloor finishes comply with requirements specified in Division 3 Section “Cast-in-
Place Concrete” for slabs receiving resilient flooring.
Subfloors are free of cracks, ridges, depressions, scale, and foreign deposits.
Do not proceed with installation until unsatisfactory conditions have been corrected.
PREPARATION
Prepare subfloor surfaces as follows:
Use leveling and patching compounds as recommended by resilient flooring manufacturer for filling small cracks, holes and depressions in subfloors.
Remove coatings from subfloor surfaces that would prevent adhesive bond, including curing compounds incompatible with resilient flooring adhesives, paint, oils, waxes and sealers.
Broom clean or vacuum surfaces to be covered, and inspect subfloor.
Apply concrete slab primer, if recommended by flooring manufacturer, prior to application of adhesive. Apply in compliance with manufacturer's directions.
INSTALLATION - GENERAL
Where movable partitions are shown, install resilient flooring before partitions are erected.
Page | 9
Install resilient flooring using method indicated in strict compliance with manufacturer's printed instructions. Extend resilient flooring into toe spaces, door reveals, and into closets and similar openings.
Scribe, cut, and fit resilient flooring to permanent fixtures, built-in furniture and cabinets, pipes, outlets and permanent columns, walls and partitions.
Maintain reference markers, holes, or openings that are in place or plainly marked for future cutting by repeating on finish flooring as marked on subfloor. Use chalk or other non-permanent marking device.
Tightly cement resilient flooring to subbase without open cracks, voids, raising and puckering at joints, telegraphing of adhesive spreader marks, or other surface imperfections. Hand roll resilient flooring at perimeter of each covered area to assure adhesion.
Comply with resilient floor covering manufacturer’s written installation instruction.
INSTALLATION OF SHEET FLOORING
Lay sheet flooring to provide as few seams as possible with economical use of materials.
Match edges for color shading and pattern at seams in compliance with manufacturer's recommendations.
Adhere sheet flooring to substrates using method approved by flooring manufacturer for type of sheet flooring and substrate condition indicated.
Use conventional full spread adhesive method unless otherwise indicated.
Use conventional perimeter bonding adhesive procedures where recommended by flooring manufacturer.
Prepare seams in vinyl sheet flooring in accordance with manufacturer's instructions for most inconspicuous appearance, sealing continuously with fluid-applied sealant or adhesive as standard with manufacturer.
Heat-Welded Seams: Rout joints and heat weld with welding bead, permanently fusing sections into a seamless floor covering. Prepare, weld, and finish seams according to manufacturer’s written instructions and ASTM F 1516 to produce surfaces flush with adjoining floor covering surfaces.
INSTALLATION OF ACCESSORIES
Apply wall base to walls, columns, pilasters, casework and other permanent fixtures in rooms or areas where base is required. Install base in lengths as long as practicable, Page | 10 with preformed corner units, or fabricated from base materials with mitered or coped inside corners.
Tightly bond base to substrate throughout length of each piece, with continuous contact at horizontal and vertical surfaces.
On masonry surfaces, or other similar irregular substrates, fill voids along top edge of resilient wall base with manufacturer's recommended adhesive filler material.
Place resilient edge strips tightly butted to flooring and secure with adhesive. Install edging strips at edges of flooring which would otherwise be exposed.
Apply resilient accessories to stairs as indicated and in strict accordance with manufacturer's installation instructions.
All needed accessories are considered incidental to the Contract and included in the bid price.
CLEANING AND PROTECTION
Perform following operations immediately upon completion of resilient flooring:
Sweep or vacuum floor thoroughly.
Do not wash floor until time period recommended by resilient flooring manufacturer has elapsed to allow resilient flooring to become well-sealed in adhesive.
Damp-mop floor being careful to remove black marks and excessive soil.
Remove any excess adhesive or other surface blemishes, using appropriate cleaner recommended by resilient flooring manufacturers.
Return all furniture and appliances to their original locations prior to installation.
Page | 11
SECTION 09680
CARPETING
PART 1 - GENERAL
DESCRIPTION OF WORK
Extent of each type of carpeting is indicated on drawings, finish schedule and by specifications, and is defined to include tufted carpet, carpet cushion and accessories.
QUALITY ASSURANCE
Static Resistance:
Provide yarn or yarn blend as indicated in carpet construction, and include provisions to comply with static resistance ratings as indicated, either by selection of yarns known to be effective or by inclusion of small percentages of special anti-static yarn know to be effective in achieving indicated static resistance. Where rating is not otherwise indicated, Minimum 2.0 kv resistance for 20 c.r.h. at 70oF
(21oC), AATCC 134.
SUBMITTALS
Submit manufacturers' literature on the proposed carpets and pads.
Color selection, residential type carpet:
Submit a minimum of three textures and 10 earth-tone color samples at least 4"x6" of the manufacturer's carpets available for selection. A maximum of three colors will be selected.
Submit layout plan showing location of all seams. Layout shall conform to the following:
Lay all carpet in same direction.
No seams at doorways that are perpendicular to opening.
Seams occurring at doorways and parallel to doorway shall be directly under the door.
Submit manufacturer's application instructions and recommendations prior to starting work.
Furnish copies of the carpet manufacturers' detailed maintenance recommendations for the care, cleaning, and repair of the type of carpet installed under this contract.
PRODUCT DELIVERY AND STORAGE
Deliver carpeting materials in original mill protective wrapping with mill register numbers and tags attached.
Page | 12
Store inside, in well ventilated area, protected from weather, moisture and soiling.
PART 2 - PRODUCTS
CARPET (RESIDENTIAL)
Carpet shall conform to the following: (Minimums)
Fiber Type: Anso Nylon 6, equal to or better
Pile Density: 2400, equal to or better
Pile Height: 0.375”, or shorter
Face Weight: 48 oz., equal to or higher
Tuft Twist: 6.6, equal to or higher
Anti Stain: R2X, SmartStrand/Triexta, Stainmaster, equal to or better
Carpet shall be free of visual blemishes, streaks, poorly dyed areas, and other physical and manufacturing defects.
CARPET MANUFACTURERS
The following is a list of acceptable carpet manufacturing suppliers, not limited to:
Shaw Industries
Mannington Industries
Mohawk - Karastan
Millliken
Bigelow
Royalty
Camelot
CARPET PAD AND ACCESSORIES
CARPET PAD
Carpet Pad shall be a minimum of 3/8” in thickness.
Carpet Edge Guard, Nonmetallic:
Extruded or molded heavy-duty vinyl or rubber carpet edge guard of size and profile indicated and with minimum 2" wide anchorage flange; colors selected by CO from among standard colors available within the industry (any manufacturer).
Installation Adhesive:
Page | 13
Water-resistant, nonstaining type as recommended by carpet or cushion manufacturer, and which complies with flammability requirements for installed carpet.
Seaming Cement:
Hot-melt seaming adhesive or similar product recommended by carpet manufacturer, for taping seams and buttering cut edges at backing to form secure seams and prevent pile loss at seams.
Miscellaneous Materials:
As recommended by manufacturers of carpet, cushions and other carpeting products;
and selected by Installer to meet project circumstance and requirements.
PART 3 - EXECUTION
PRE-INSTALLATION REQUIREMENTS
Temporarily remove and store any furniture, remove and dispose of old existing carpet, padding and flooring.
Examine substrates for moisture content and other conditions under which carpeting is to be installed. Repair minor holes, cracks, depressions or rough areas using material recommended by carpet or adhesive manufacturer. Notify Contracting Officer’s
Representative of any major conditions detrimental to proper completion of the work.
Do not proceed until unsatisfactory conditions have been corrected.
Clear away debris and scrape up cementitious deposits from surfaces to receive carpeting or vinyl flooring; vacuum clean immediately before installation.
Sequence carpeting with other work so as to minimize possibility of damage and soiling of carpet during remainder of construction period.
INSTALLATION
General:
Comply with manufacturer's instructions and recommendations for seam locations and direction of carpet; maintain uniformity of carpet direction and lay of pile. At doors, center seams under doors; do not place seams in traffic direction at doorways. No seam shall be located to intersect a doorway at a 90 degree angle.
Extend carpet under open-bottomed obstructions and under removable flanges and furnishings, and into alcoves and closets of each space.
Provide cut-outs where required, and bind cut edges properly where not concealed by protective edge guards or overlapping flanges.
Install carpet edge guard where edge of carpet is exposed; anchor guards to substrate.
Page | 14
CLEANING AND PROTECTION
Remove and dispose of debris and unusable scraps.
Vacuum carpet using commercial machine with face-beater element. Remove spots and replace carpet where spots cannot be removed. Remove any protruding face yarn using sharp scissors.
Advise Contracting Officer’s Representative of protection methods and materials needed to ensure that carpeting will be without deterioration or damage at time of final acceptance.
Deliver specified overrun (if any) and usable scraps of carpet to Owner's designated storage space, properly packaged (paper wrapped) and identified. Usable scraps are defined to include roll ends of less than 9'-0" in length, and pieces of more than 3 square feet area and more than 8" wide.
Return to installation after approximately 6 months of occupancy and use; restretch carpet in every space, repair faults in seaming, trim and adjust carpeting at edges.