b.Peep_final_solicitation.doc
DOC document 494 KB Posted
- Attached to
- Peep Stewardship
- Solicitation number
- AG-04M3-S-11-9000
About this file
B. Solicitation
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment No 2.rtf | RTF text file | |
| Amendment No 1 A.rtf | RTF text file | |
| c.APPENDIX A_work_activity.docx | DOCX document | |
| e.Appendix B_Harvest_Summary_Sheet.xlsx | XLSX spreadsheet | |
| d.Appendix_B_Timber_Specs.doc | DOC document | |
| n.weed_map.PDF | ||
| f.Appendix C_Special_Road_Specs.doc | DOC document | |
| j.Rd_main_drawing_835-2.pdf | ||
| a.quoters_packet.doc | DOC document | |
| k.Road_Maint_Req_ Specs_Table.docx | DOCX document | |
| l.Road_Maint_Req_Summary_Table.docx | DOCX document | |
| o.77-0079_sca.mht | MHT file | |
| h.Rd_main_drawing_801-1.pdf | ||
| i.Rd_main_drawing_834-1.pdf | ||
| m.Peep_StewMap_07212011.pdf |
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Project Name : Peep Stewardship
Project name: Peep Stewardship Solicitation No. AG-04M3-S-11-9000
| SOLICITATION/CONTRACT/ORDER FOR COMMERCIAL ITEMS |
| 1. REQUISITION NUMBER |
| PAGE 1 OF |
| OFFEROR TO COMPLETE BLOCKS 12, 17, 23, 24, & 30 |
| 491718 |
| 60 |
| 2. CONTRACT NO. |
| 3. AWARD/EFFECTIVE |
| 4. ORDER NUMBER |
| 5. SOLICITATION NUMBER |
| 6. SOLICIATION ISSUE |
| DATE |
| AG-04M3-S-11-9000 |
| DATE |
07/28/2011
| a. NAME |
| b. TELEPHONE NUMBER(No collect |
| 8. OFFER DUE DATE/ |
7. FOR SOLICITATION
| calls) |
| LOCAL TIME |
| INFORMATION CALL: |
| Annie Stanbro, Administrative |
| (541) 523-1342 |
| 4:30 PM PST |
| Tom Burry, Technical |
| (541) 962-8537 |
| 08/29/2011 |
| 9. ISSUED BY CODE |
| 10. THIS ACQUISITON IS |
FORMCHECKBOX
UNRESTRICTED OR
FORMCHECKBOX
SET ASIDE: % FOR
FORMCHECKBOX
SMALL BUSINESS FORMCHECKBOX
EMERGING SMALL
BUSINESS
NAICS: FORMCHECKBOX
HUBZONE SMALL
BUSINESS
SIZE STANDARD: FORMCHECKBOX
SERVICE-DISABLED VETERAN- FORMCHECKBOX
8(A)
OWNED SMALL BUSINESS
Wallowa Whitman National Forest
1550 Dewey Avenue/PO Box 907
Baker City, OR 97814
11. DELIVERY FOR FOB DESTINATION UNLESS BLOCK IS MARKED
FORMCHECKBOX
SEE SCHEDULE
| 12. DISCOUNT TERMS |
| FORMCHECKBOX |
13a. THIS CONTRACT IS A RATED
ORDER UNDER DPAS (15 CFR 700)
13b. Rating
14. METHOD OF SOLICITATION
RFQ FORMCHECKBOX
IFB FORMCHECKBOX
RFP
15. DELIVER TO CODE
Wallowa Whitman National Forest – La Grande Ranger District
3502 Highway 30
La Grande, OR 97850
16. ADMINISTERED BY CODE
Same as Block 9
17A. CONTRACTOR/OFFEROR CODE FACILITY
CODE
18a. PAYMENT WILL BE MADE BY CODE
Albuquerque Service Center – Miscellaneous Payments
101B Sun Ave NE
Albuquerque, NM 87109
DUNS:
EMAIL ADDRESS:
TELEPHONE NO:
FORMCHECKBOX
17b. CHECK IF REMITTANCE IS DIFFERENT AND PUT SUCH ADDRESS IN 18b. SUBMIT INVOICES TO ADDRESS SHOWN IN BLOCK 18a UNLESS BLOCK BELOW
| OFFER |
| IS CHECKED |
FORMCHECKBOX
SEE ADDENDUM
| 19. |
| 20. |
| 21. |
| 22. |
| 23. |
| 24. |
| ITEM N0. |
| SCHEDULE OF SUPPLIES/SERVICES |
| QUANTITY |
| UNIT |
| UNIT PRICE |
| AMOUNT |
| PEEP STEWARDSHIP PROJECT |
DISTRICT – LA GRANDE
FOREST – WALLOWA-WHITMAN
(Use Reverse and/or Attach Additional Sheets as Necessary)
25. ACCOUNTING AND APPROPRIATION DATA
26. TOTAL AWARD AMOUNT (For Govt. Use Only)
FORMCHECKBOX
| 27a. SOLICITATION INCORPORATES BY REFERENCE FAR 52.212-1, 52.212-4. FAR 52.212-3 AND 52.212-5 ARE ATTACHED. ADDENDA |
| FORMCHECKBOX |
| ARE |
| FORMCHECKBOX |
ARE NOT ATTACHED
FORMCHECKBOX
| 27b. CONTRACT/PURCHASE ORDER INCORPORATES BY REFERENCE FAR 52.212-4. FAR 52.212-5 IS ATTACHED. ADDENDA |
| FORMCHECKBOX |
| ARE |
| FORMCHECKBOX |
ARE NOT ATTACHED
| 28. CONTRACTOR IS REQUIRED TO SIGN THIS DOCUMENT AND RETURN _________ |
| FORMCHECKBOX |
29. AWARD OF CONTRACT: REF. ________________________ OFFER
COPIES TO ISSUING OFFICE. CONTRACTOR AGREES TO FURNISH AND
| DELIVER ALL ITEMS SET FORTH OR OTHERWISE IDENTIFIED ABOVE AND ON ANY |
| DATED_______________________ , YOUR OFFER ON SOLICITATION |
| ADDITIONAL SHEETS SUBJECT TO THE TERMS AND CONDITIONS SPECIFIED |
| (BLOCK 5), INCLUDING ANY ADDITIONS OR CHANGES WHICH ARE |
SET FORTH HEREIN, IS ACCEPTED AS TO ITEMS:
| 30a. SIGNATURE OF OFFEROR/CONTRACTOR |
| 31a. UNITED STATES OF AMERICA (SIGNATURE OF CONTRACTING OFFICER) |
| 30b. NAME AND TITLE OF SIGNER (Type or print) |
| 30c. DATE SIGNED |
| 31b. NAME OF CONTRACTING OFFICER (Type or print) |
Andrea Stanbro, CO 31c. DATE SIGNED
AUTHORIZED FOR LOCAL REPRODUCTION
STANDARD FORM 1449 (REV.3/2005)
PREVIOUS EDITION IS NOT USABLE
Prescribed by GSA ‑ FAR (48 CFR) 53.212
19.
ITEM NO.
20.
SCHEDULE OF SUPPLIES/SERVICES
21.
QUANTITY
22.
UNIT
23.
UNIT PRICE
24.
Amount
SEE ATTACHED SCHEDULE OF ITEMS
32a. QUANTITY IN COLUMN 21 HAS BEEN
RECEIVED
FORMCHECKBOX
INSPECTED
FORMCHECKBOX
ACCEPTED, AND CONFORMS TO THE CONTRACT, EXCEPT AS NOTED: __________________________
32b. SIGNATURE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32c. DATE
32d. PRINTED NAME AND TITLE OF AUTHORIZED GOVERNMENT
REPRESENTATIVE
32e. MAILING ADDRESS OF AUTHORIZED GOVERNMENT REPRESENTATIVE
32f. TELPHONE NUMBER OF AUTHORZED GOVERNMENT REPRESENTATIVE
32g. E-MAIL OF AUTHORIZED GOVERNMENT REPRESENTATIVE
| 33. SHIP NUMBER |
| 34. VOUCHER NUMBER |
| 35. AMOUNT VERIFIED |
CORRECT FOR
| 36. PAYMENT |
| 37. CHECK NUMBER |
FORMCHECKBOX
PARTIAL FORMCHECKBOX
FINAL
FORMCHECKBOX
COMPLETE FORMCHECKBOX
PARTIAL FORMCHECKBOX
FINAL
| 38. S/R ACCOUNT NUMBER |
| 39. S/R VOUCHER NUMBER |
| 40. PAID BY |
| 41a. I CERTIFY THIS ACCOUNT IS CORRECT AND PROPER FOR PAYMENT |
| 42a. RECEIVED BY (Print) |
| 41 b. SIGNATURE AND TITLE OF CERTIFYING OFFICER |
| 41 c. DATE |
42b. RECEIVED AT (Location)
| 42c. DATE RECD (YY/MM/DD) |
| 42d. TOTAL CONTAINERS |
STANDARD FORM 1449 (REV.3/2005) BACK
SCHEDULE OF ITEMS
B.1
SCHEDULE OF SERVICE ITEMS:
SERVICES AND PRICES
Contractor Name
| Item No. |
| Description |
Base work activities
| Unit |
| Estimated |
Quantity
| Unit Price |
| Total |
| 1 |
| Biomass thinning and fuels treatment |
| Ac |
| 565 |
| $ |
| $ |
| 2 |
| Road Maintenance (contractor work only) |
| LS |
| 1 |
| $ |
| $ |
| Total All Service Items |
| $ |
B.2 TIMBER/PRODUCT REMOVAL PRICE SCHEDULE:
| SPECIES |
| PRODUCT |
| QUANTITY |
| UNIT OF MEASURE |
| MINIMUM ACCEPTABLE OFFER |
| OFFER |
(FLAT)
TOTAL OFFER
| DOUGLAS FIR AND WESTERN LARCH |
| SAW |
CCF
$1.00
| $ |
| $ |
| LODGEPOLE PINE AND OTHER SPECIES |
| SAW |
| 759 |
| CCF |
| $1.00 |
| $ |
| $ |
| LODGEPOLE PINE AND OTHER SPECIES |
| GCvB |
| 3,705 |
| CCF |
| $.25 |
| $ |
| $ |
| **Total – All Products |
| $ |
In addition to the price to be paid by the contractor for timber products to be removed, the contractor shall pay deposits for road use and surface replacement (Roads 5100, 5160, and 5175) in the amount of $7.02 per CCF.
Note: These schedules are for pricing/payment purposes. See Instructions to Offerors for business proposal requirements.
NOTE: Price Proposals MUST be provided on ALL Items in Schedules B-1, Base Work Activities and B-2, Timber or other products Removal Price Schedule.
B.3
LAND MANAGEMENT ACTIVITIES.
Performance of land management activities shall be in accordance with Section C – Project Description and Work Specifications. Payment for Land Management Work Activities in Schedule B-1, will be made in Stewardship Credits in lieu of cash, as defined in Section G. All Base Work Activities shall be performed.
CONTRACT CLAUSES
1.
PROJECT DESCRIPTION
(a) Description of Work- This solicitation and any resultant contract is a stewardship project in accordance with Section 323 of Public Law 108-7 (16 U.S.C. 2104 Note, as revised February 28, 2003 to reflect sec. 323 of J.J. Res. 2 as enrolled), the Consolidated Appropriations Resolution, 2003, amending Public Law 105-277, sec. 347. This is a commercial item acquisition that has been tailored to fit the Government’s method of trading goods for services. Work includes active management within the timbered stands to improve long term forest health conditions, reduce fuel loadings to create defensible space and enhance late old stand structure within the project area. Treatment stands are predominately small diameter providing both a sawlog component suitable for milling as well as biomass material for existing and developing industry utilization.
(b) Resulting Contract – Any resultant contract will be a service contract with provisions for timber removal.
(c) Project Location – This project is located on lands administered by the La Grande Ranger District of the Wallowa-Whitman National Forest. Vicinity maps showing project locations and access are attached and made part of this contract. All township and range locations are predicated upon the Willamette Base Meridian. The project area includes sections 1, 2 and 3 of Township 7 South, Range 35 1/2 East, sections 3, 4, 9, 10, 11, 12, 13, 14, 15, 16, 21, 22, 23, 24, 25, 26, 27, 28, 33, 34, 35, 36 of Township 6 South, Range 35 1/2 East, sections 19, 30 and 31 of Township 7 South, Range 36 East and sections 10, 13, 24 and 25 of Township 6 South, Range 35 East. Location is approximately 15 miles south on Forest Road 5100 from Starkey, Oregon.
2.
SPECIFICATIONS
Specifications for each Stewardship Activity individually described by an item number in Schedule B pages can be found in Appendix A. Specifications for timber or other products removal can be found in Appendix B. Road Maintenance plans and specifications can be found in Appendix C.
3.
CONTRACT AREA MAP
The boundaries of Subdivisions or Payment Units and any cutting units thereof, are as shown on the attached "Contract Area Map," which is made a part hereof, and were, before solicitation, designated on the ground by Forest Service to meet the anticipated needs of the parties. The location of the Subdivisions or Payment Units and their approximate acreage are stated in Division A/AT. Subdivisions or Payment Units may be revised and additional ones may be established only by written agreement of both parties. Where applicable, the following are also identified on Contract Area Map:
(a) Identified claims limiting Contractor's rights;
(b) Boundaries of cutting units;
(c) Areas where leave trees are Marked to be left uncut;
(d) Roads listed
(e) Sources of base course, rock riprap and surface rock;
(f) Roads where log hauling is prohibited or restricted;
(g) Roads and trails to be kept open;
(h) Improvements to be protected;
(i) Locations of known historical sites;
(j) Maximum stump heights when more than one height is listed by areas;
(k) Skidding or yarding methods specified;
(l) Streamcourses to be protected;
(m) Other features required by Appendix B; and
(n) Boundaries of stewardship work activities.
4.
GOVERNMENT-FURNISHED PROPERTY
The Government will provide the following item(s) of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of the "Government Property" FAR clause 52.245-1 as referenced.
1. Seed, see Appendix B for specific information.
2. Product removal permits
5.
CONTRACTOR QUALITY CONTROL INSPECTION SYSTEM
The Contractor shall identify the quality control inspection system it will use to ensure that contract specifications will be achieved. At no time shall the contractor rely upon Government inspections to provide notification of unsatisfactory performance. The Contractor shall produce written inspection records in a format and at times and places satisfactory to the Contracting Officer. Inspection records shall be made available upon request of the Contracting Officer and be maintained until the date of contract closure. The Contracting Officer may observe the Contractor's inspection at any time and shall otherwise have unlimited access to the inspection data.
6.
ACCEPTANCE
The Forest Service shall perform an inspection upon Contractor’s written request and assurance that work has been completed. Request shall be for a reasonable portion of work. Acceptance may be made for all or portions of work.
7.
GOVERNMENT QUALITY ASSURANCE SURVEILLANCE PLAN
Quality assurance plans specific to individual items will be found in Appendix A, B, and C.
8. FAR 52.212-4 Contract Terms and Conditions—Commercial Items (June 2010)
(a) Inspection/Acceptance. The Contractor shall only tender for acceptance those items that conform to the requirements of this contract. The Government reserves the right to inspect or test any supplies or services that have been tendered for acceptance. The Government may require repair or replacement of nonconforming supplies or reperformance of nonconforming services at no increase in contract price. If repair/replacement or reperformance will not correct the defects or is not possible, the Government may seek an equitable price reduction or adequate consideration for acceptance of nonconforming supplies or services. The Government must exercise its post-acceptance rights—
(1) Within a reasonable time after the defect was discovered or should have been discovered; and
(2) Before any substantial change occurs in the condition of the item, unless the change is due to the defect in the item.
(b) Assignment. The Contractor or its assignee may assign its rights to receive payment due as a result of performance of this contract to a bank, trust company, or other financing institution, including any Federal lending agency in accordance with the Assignment of Claims Act (31 U.S.C. 3727). However, when a third party makes payment (e.g., use of the Governmentwide commercial purchase card), the Contractor may not assign its rights to receive payment under this contract.
(c) Changes. Changes in the terms and conditions of this contract may be made only by written agreement of the parties.
(d) Disputes. This contract is subject to the Contract Disputes Act of 1978, as amended (41 U.S.C. 601-613). Failure of the parties to this contract to reach agreement on any request for equitable adjustment, claim, appeal or action arising under or relating to this contract shall be a dispute to be resolved in accordance with the clause at FAR 52.233-1, Disputes, which is incorporated herein by reference. The Contractor shall proceed diligently with performance of this contract, pending final resolution of any dispute arising under the contract.
(e) Definitions. The clause at FAR 52.202-1, Definitions, is incorporated herein by reference.
(f) Excusable delays. The Contractor shall be liable for default unless nonperformance is caused by an occurrence beyond the reasonable control of the Contractor and without its fault or negligence such as, acts of God or the public enemy, acts of the Government in either its sovereign or contractual capacity, fires, floods, epidemics, quarantine restrictions, strikes, unusually severe weather, and delays of common carriers. The Contractor shall notify the Contracting Officer in writing as soon as it is reasonably possible after the commencement of any excusable delay, setting forth the full particulars in connection therewith, shall remedy such occurrence with all reasonable dispatch, and shall promptly give written notice to the Contracting Officer of the cessation of such occurrence.
(g) Invoice.
(1) The Contractor shall submit an original invoice and three copies (or electronic invoice, if authorized) to the address designated in the contract to receive invoices. An invoice must include—
(i) Name and address of the Contractor;
(ii) Invoice date and number;
(iii) Contract number, contract line item number and, if applicable, the order number;
(iv) Description, quantity, unit of measure, unit price and extended price of the items delivered;
(v) Shipping number and date of shipment, including the bill of lading number and weight of shipment if shipped on Government bill of lading;
(vi) Terms of any discount for prompt payment offered;
(vii) Name and address of official to whom payment is to be sent;
(viii) Name, title, and phone number of person to notify in event of defective invoice; and
(ix) Taxpayer Identification Number (TIN). The Contractor shall include its TIN on the invoice only if required elsewhere in this contract.
(x) Electronic funds transfer (EFT) banking information.
(A) The Contractor shall include EFT banking information on the invoice only if required elsewhere in this contract.
(B) If EFT banking information is not required to be on the invoice, in order for the invoice to be a proper invoice, the Contractor shall have submitted correct EFT banking information in accordance with the applicable solicitation provision, contract clause (e.g., 52.232-33, Payment by Electronic Funds Transfer—Central Contractor Registration, or 52.232-34, Payment by Electronic Funds Transfer—Other Than Central Contractor Registration), or applicable agency procedures.
(C) EFT banking information is not required if the Government waived the requirement to pay by EFT.
(2) Invoices will be handled in accordance with the Prompt Payment Act (31 U.S.C. 3903) and Office of Management and Budget (OMB) prompt payment regulations at 5 CFR Part 1315.
(h) Patent indemnity. The Contractor shall indemnify the Government and its officers, employees and agents against liability, including costs, for actual or alleged direct or contributory infringement of, or inducement to infringe, any United States or foreign patent, trademark or copyright, arising out of the performance of this contract, provided the Contractor is reasonably notified of such claims and proceedings.
(i) Payment.—
(1) Items accepted. Payment shall be made for items accepted by the Government that have been delivered to the delivery destinations set forth in this contract.
(2) Prompt payment. The Government will make payment in accordance with the Prompt Payment Act (31 U.S.C. 3903) and prompt payment regulations at 5 CFR Part 1315.
(3) Electronic Funds Transfer (EFT). If the Government makes payment by EFT, see 52.212-5(b) for the appropriate EFT clause.
(4) Discount. In connection with any discount offered for early payment, time shall be computed from the date of the invoice. For the purpose of computing the discount earned, payment shall be considered to have been made on the date which appears on the payment check or the specified payment date if an electronic funds transfer payment is made.
(5) Overpayments. If the Contractor becomes aware of a duplicate contract financing or invoice payment or that the Government has otherwise overpaid on a contract financing or invoice payment, the Contractor shall—
(i) Remit the overpayment amount to the payment office cited in the contract along with a description of the overpayment including the—
(A) Circumstances of the overpayment (e.g., duplicate payment, erroneous payment, liquidation errors, date(s) of overpayment);
(B) Affected contract number and delivery order number, if applicable;
(C) Affected contract line item or subline item, if applicable; and
(D) Contractor point of contact.
(ii) Provide a copy of the remittance and supporting documentation to the Contracting Officer.
(6) Interest.
(i) All amounts that become payable by the Contractor to the Government under this contract shall bear simple interest from the date due until paid unless paid within 30 days of becoming due. The interest rate shall be the interest rate established by the Secretary of the Treasury as provided in Section 611 of the Contract Disputes Act of 1978 (Public Law 95-563), which is applicable to the period in which the amount becomes due, as provided in (i)(6)(v) of this clause, and then at the rate applicable for each six-month period as fixed by the Secretary until the amount is paid.
(ii) The Government may issue a demand for payment to the Contractor upon finding a debt is due under the contract.
(iii) Final decisions. The Contracting Officer will issue a final decision as required by 33.211 if—
(A) The Contracting Officer and the Contractor are unable to reach agreement on the existence or amount of a debt within 30 days;
(B) The Contractor fails to liquidate a debt previously demanded by the Contracting Officer within the timeline specified in the demand for payment unless the amounts were not repaid because the Contractor has requested an installment payment agreement; or
(C) The Contractor requests a deferment of collection on a debt previously demanded by the Contracting Officer (see 32.607-2).
(iv) If a demand for payment was previously issued for the debt, the demand for payment included in the final decision shall identify the same due date as the original demand for payment.
(v) Amounts shall be due at the earliest of the following dates:
(A) The date fixed under this contract.
(B) The date of the first written demand for payment, including any demand for payment resulting from a default termination.
(vi) The interest charge shall be computed for the actual number of calendar days involved beginning on the due date and ending on—
(A) The date on which the designated office receives payment from the Contractor;
(B) The date of issuance of a Government check to the Contractor from which an amount otherwise payable has been withheld as a credit against the contract debt; or
(C) The date on which an amount withheld and applied to the contract debt would otherwise have become payable to the Contractor.
(vii) The interest charge made under this clause may be reduced under the procedures prescribed in 32.608-2 of the Federal Acquisition Regulation in effect on the date of this contract.
(j) Risk of loss. Unless the contract specifically provides otherwise, risk of loss or damage to the supplies provided under this contract shall remain with the Contractor until, and shall pass to the Government upon:
(1) Delivery of the supplies to a carrier, if transportation is f.o.b. origin; or
(2) Delivery of the supplies to the Government at the destination specified in the contract, if transportation is f.o.b. destination.
(k) Taxes. The contract price includes all applicable Federal, State, and local taxes and duties.
(l) Termination for the Government’s convenience. The Government reserves the right to terminate this contract, or any part hereof, for its sole convenience. In the event of such termination, the Contractor shall immediately stop all work hereunder and shall immediately cause any and all of its suppliers and subcontractors to cease work. Subject to the terms of this contract, the Contractor shall be paid a percentage of the contract price reflecting the percentage of the work performed prior to the notice of termination, plus reasonable charges the Contractor can demonstrate to the satisfaction of the Government using its standard record keeping system, have resulted from the termination. The Contractor shall not be required to comply with the cost accounting standards or contract cost principles for this purpose. This paragraph does not give the Government any right to audit the Contractor’s records. The Contractor shall not be paid for any work performed or costs incurred which reasonably could have been avoided.
(m) Termination for cause. The Government may terminate this contract, or any part hereof, for cause in the event of any default by the Contractor, or if the Contractor fails to comply with any contract terms and conditions, or fails to provide the Government, upon request, with adequate assurances of future performance. In the event of termination for cause, the Government shall not be liable to the Contractor for any amount for supplies or services not accepted, and the Contractor shall be liable to the Government for any and all rights and remedies provided by law. If it is determined that the Government improperly terminated this contract for default, such termination shall be deemed a termination for convenience.
(n) Title. Unless specified elsewhere in this contract, title to items furnished under this contract shall pass to the Government upon acceptance, regardless of when or where the Government takes physical possession.
(o) Warranty. The Contractor warrants and implies that the items delivered hereunder are merchantable and fit for use for the particular purpose described in this contract.
(p) Limitation of liability. Except as otherwise provided by an express warranty, the Contractor will not be liable to the Government for consequential damages resulting from any defect or deficiencies in accepted items.
(q) Other compliances. The Contractor shall comply with all applicable Federal, State and local laws, executive orders, rules and regulations applicable to its performance under this contract.
(r) Compliance with laws unique to Government contracts. The Contractor agrees to comply with 31 U.S.C. 1352 relating to limitations on the use of appropriated funds to influence certain Federal contracts; 18 U.S.C. 431 relating to officials not to benefit; 40 U.S.C. 3701, et seq., Contract Work Hours and Safety Standards Act; 41 U.S.C. 51-58, Anti-Kickback Act of 1986; 41 U.S.C. 265 and 10 U.S.C. 2409 relating to whistleblower protections; 49 U.S.C. 40118, Fly American; and 41 U.S.C. 423 relating to procurement integrity.
(s) Order of precedence. Any inconsistencies in this solicitation or contract shall be resolved by giving precedence in the following order:
(1) The schedule of supplies/services.
(2) The Assignments, Disputes, Payments, Invoice, Other Compliances, and Compliance with Laws Unique to Government Contracts paragraphs of this clause.
(3) The clause at 52.212-5.
(4) Addenda to this solicitation or contract, including any license agreements for computer software.
(5) Solicitation provisions if this is a solicitation.
(6) Other paragraphs of this clause.
(7) The Standard Form 1449.
(8) Other documents, exhibits, and attachments.
(9) The specification.
(t) Central Contractor Registration (CCR).
(1) Unless exempted by an addendum to this contract, the Contractor is responsible during performance and through final payment of any contract for the accuracy and completeness of the data within the CCR database, and for any liability resulting from the Government’s reliance on inaccurate or incomplete data. To remain registered in the CCR database after the initial registration, the Contractor is required to review and update on an annual basis from the date of initial registration or subsequent updates its information in the CCR database to ensure it is current, accurate and complete. Updating information in the CCR does not alter the terms and conditions of this contract and is not a substitute for a properly executed contractual document.
(2)(i) If a Contractor has legally changed its business name, “doing business as” name, or division name (whichever is shown on the contract), or has transferred the assets used in performing the contract, but has not completed the necessary requirements regarding novation and change-of-name agreements in FAR Subpart 42.12, the Contractor shall provide the responsible Contracting Officer a minimum of one business day’s written notification of its intention to (A) change the name in the CCR database; (B) comply with the requirements of Subpart 42.12; and (C) agree in writing to the timeline and procedures specified by the responsible Contracting Officer.
The Contractor must provide with the notification sufficient documentation to support the legally changed name.
(ii) If the Contractor fails to comply with the requirements of paragraph (t)(2)(i) of this clause, or fails to perform the agreement at paragraph (t)(2)(i)(C) of this clause, and, in the absence of a properly executed novation or change-of-name agreement, the CCR information that shows the Contractor to be other than the Contractor indicated in the contract will be considered to be incorrect information within the meaning of the “Suspension of Payment” paragraph of the electronic funds transfer (EFT) clause of this contract.
(3) The Contractor shall not change the name or address for EFT payments or manual payments, as appropriate, in the CCR record to reflect an assignee for the purpose of assignment of claims (see Subpart 32.8, Assignment of Claims). Assignees shall be separately registered in the CCR database. Information provided to the Contractor’s CCR record that indicates payments, including those made by EFT, to an ultimate recipient other than that Contractor will be considered to be incorrect information within the meaning of the “Suspension of payment” paragraph of the EFT clause of this contract.
(4) Offerors and Contractors may obtain information on registration and annual confirmation requirements via the internet at http://www.ccr.gov or by calling 1-888-227-2423 or 269-961-5757.
(End of clause)
9. 52.211-10 COMMENCEMENT, PROSECUTION, AND COMPLETION OF WORK (APR 1984)
The Contractor shall be required to (a) commence work under this contract within _10_ calendar days after receipt of Notice to Proceed or Task Order for specific work items, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than _October 31, 2014_. The time stated for completion shall include final cleanup of the premises.
Performance shall be made only as authorized by orders issued in accordance with the Ordering clauses. Except as this contract otherwise provides, the Government shall order all services within the scope that are required by Government activities specified in the Schedule only with the vendor holding this contract for the specified services. Timber or other products removal activities shall be scheduled and carried out in accordance with the Timber or other products Removal Specifications in Appendix B and as approved by the Contracting Officer.
It is estimated that work will begin in the fall of 2011. Actual date is negotiable based upon actual award date, prospective work and weather conditions.
Scheduling of Work may be restricted based on the following:
1. Logging operations are restricted when saturated soil conditions occur. These conditions typically occur outside the period of July 1 to September 30 when frozen ground or adequate snow cover is not present.
2. Hauling operations are restricted when roads are frozen or dry to minimize sedimentation.
3. Operations are to be scheduled so that no more than 2 roads are open and used by the contractor that are tributary to the 5100, 5175 or 5160 at one point in time.
4. Operations are restricted outside the Winter Range Period of December 15 through March 31 when heavy snow cover or low temperatures are likely to occur. This applies to Cutting Units 1, 5, 6, 9 and 22.
5. Operations are restricted within Cutting Unit 9 to the period September 1 through March 15 to protect goshawk nesting site. Operations outside this period may be approved by the Forest Service if the nesting site is found inactive during the annual nesting period.
10. SCHEDULES AND REPORTS
Contractor shall provide the following submittals within _10_ days after issuance of a Notice to Proceed or Task Order for review and/or approval, unless stated elsewhere in the specifications or otherwise mutually agreed:
| ITEM DESCRIPTION |
| COPIES REQUIRED |
| Proposed progress schedule showing starting and completion dates of various phases of the work |
| 2 |
| List of proposed sub-contractors and their intended work. Sub-contractors must have Contracting Officers Written approval prior to starting work on the project. Submit on Standard Form 1413. |
| 2 |
| Soil Erosion and Water Pollution Control Plan |
| 2 |
| Designation of Contractor personnel describing responsibilities and authorities |
| 2 |
| Job-Specific Safety Plan |
| 2 |
| Traffic Control Plan |
| 2 |
All schedules and reports shall be submitted to: COR, Julie Tarvin 11.
PAYMENT
It is anticipated that funds will be exchanged in the performance of this contract because the value of the timber or other products will not completely offset the value of the work to be performed. Payment shall only be made under this clause to the extent that the work performed will not be offset by the timber or other products value during the contract period. When payment is made to the contractor for work performed, it will be made in accordance with FAR 52.232-1 – Payments.
The value of work completed and timber or other products removed will be documented in an Integrated Resource Statement of Account produced by Timber Sale Accounting (TSA) monthly when harvesting operations are underway.
12.
INCIDENTAL PAYMENT ITEMS
The intent of the contract is to provide for the complete performance of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for items shown.
13.
PRODUCT PAYMENT GUARANTEE
To guarantee payment for product in advance of cutting, Contractor may earn Stewardship Credits in advance of cutting, or provide a product payment guarantee in the form of an acceptable surety payment bond, irrevocable letter of credit (ILOC), cash, or a deposit in a Federal Depository negotiable securities of the United States.
Any earned stewardship credits and product payment guarantee together will maintain a minimum unobligated balance equal to the total value of product that has not been paid for from stewardship units released for cutting.
Securities shall be deposited through the Contracting Officer accompanied by a power of attorney and agreement authorizing the bond-approving officer to sell or collect such securities if payment is not made within 15 days of billing by Forest Service. The penal sum of such surety bond or the market value at time of deposit of such negotiable securities shall be the maximum amount of the payment guaranteed.
Product payment guarantee for a single contract shall be provided utilizing Form FS6500-12 Payment Bond.
Blanket Payment Bond:
a. Contractor may furnish an acceptable bond, or deposits securities, to guarantee payment for product from multiple contracts. Contractor shall not start cutting hereunder until this contract receives an allocation that will meet the obligation for product payment guarantee.
b. The amount of such bond or deposited securities shall be allocated to such contracts by the Forest Service. The Contractor shall provide the contact information for the Forest Service representative administering the blanket payment bond to the Contracting Officer. The Forest Service representative administering the blanket payment bond will provide the Contracting Officer with documentation showing the allocation to this contract.
c. When there is to be no product cutting or removal hereunder for 30 days or more and payment of current charges has been made, the allocation to this contract may be reallocated to other contracts at Contractor’s request.
d. Payment guaranteed with acceptable blanket payment bond for multiple contracts shall be provided utilizing Form FS-6500-12a Blanket Payment Bond.
14.
REIMBURSEMENT FOR BOND PREMIUMS
The Contract Price includes the total amount for premiums that the Contractor attributes to the furnishing of the performance and/or payment bonds required by the contract. Reimbursement for bond premiums may be made in stewardship credits or cash.
15.
STEWARDSHIP CREDITS
Stewardship Credits are credits that are earned and established when work listed in the B.1 Schedule of Supplies/Services has been performed and accepted. Stewardship credits shall be earned at the rate as shown in the Schedule. Earned credits may be used to pay for timber or other products value included in Schedule B.2. Unless otherwise indicated in the Schedules, credits will be earned based upon Actual Quantities completed and accepted.
16.
ESTABLISHMENT OF STEWARDSHIP CREDITS
Notwithstanding references to payments in “Payment” clauses or provisions of this contract, payment for Stewardship Activities will be made with Stewardship Credits as indicated in the award document.
Stewardship Credits will be established on a monthly basis. Stewardship credits will be established for the number of units of each activity that have been completed and accepted. Acceptance may be for all, or a reasonable portion of, any specific activity.
Stewardship credits will not be established for work that is in progress that has not been accepted by the Forest Service. No credits will be established for work performed under terms of Schedule B.2.
17.
CONTRACTOR CERTIFICATION
Monthly, as Stewardship Credits are established, the Contractor shall furnish the following certification (Contractor Certification - Earned Stewardship Credits) or credit will not be received.
CONTRACTOR CERTIFICATION - EARNED STEWARDSHIP CREDITS
PEEP STEWARDSHIP PROJECT
I hereby certify, to the best of my knowledge and belief, that--
(1) The amounts requested are only for performance in accordance with the specifications, terms, and conditions of the contract;
(2) Payments to subcontractors and suppliers have been made, and timely payments will be made for the work activities covered by this certification, in accordance with subcontract agreements and the requirements of Chapter 39 of Title 31, United States Code;
(3) This request for progress payments/credits does not include any amounts which the prime contractor intends to withhold or retain from a subcontractor or supplier in accordance with the terms and conditions of the subcontract; and
(4) This certification is not to be construed as final acceptance of a subcontractor's performance.
(Name)
(Title)
(Date) 18.
EXCESS STEWARDSHIP CREDITS
In the event there are excess (unused) established Stewardship Credits when all of the included timber or other products has been cut and removed the Forest Service, at its option, shall either add more timber or other products or make cash payment for the unused credits.
19.
EXCESS TIMBER OR OTHER PRODUCTS VALUE
In the event the value of the included timber or other products exceeds the total value of all of the mandatory activities plus the ordered elective activities, the Contractor shall make cash payment for the excess timber or other products value.
20.
REFUND OF EXCESS CASH
If at any time the credit balance of the Integrated Resource Statement of Account exceeds the charges for timber or other products removed to date and for timber or other products that the Forest Service estimates will be cut within the next 60 calendar days, any portion of such excess from cash in the account shall be refunded if requested by Contractor. If no cutting is planned within the next 60 calendar days, refund of the entire unencumbered cash balance may be made. After a refund, deposits shall be made to meet the requirements of the clause entitled, “PRODUCT PAYMENT GUARANTEE” before additional timber or other products may be cut.
21.
FINAL PAYMENT - RELEASE OF CLAIMS
The Government shall pay the amount due the Contractor under this contract after—
(1) Completion and acceptance of all work;
(2) Presentation of a properly executed voucher; and
(3) Presentation of release of all claims against the Government arising by virtue of this contract, other than claims, in stated amounts, that the Contractor has specifically excepted from the operation of the release.
22.
AGAR 452.215-73 POST AWARD CONFERENCE (NOV 1996)
A post award conference with the successful offeror is required. It will be scheduled within 10 days after the date of contract award. The conference will be held at the La Grande Ranger District, and will include discussion of contract terms and work performance requirements, work progress schedule and fire prevention/suppression and safety plans.
23.
FAR 52.236-4 PHYSICAL DATA (APR 1984)
Data and information furnished or referred to below is for the Contractor's information. The Government shall not be responsible for any interpretation of or conclusion drawn from the data or information by the Contractor.
(a) - The indications of physical conditions on the drawings and in the specifications are the result of site investigations by visual observation.
(b) - Additional informational material made available to contractors including but not limited to: environmental documentation, timber cruise data, timber removal report and appraisal and maps.
24.
AGAR 452.237-74 KEY PERSONNEL (FEB 1988)
(a) The Contractor shall assign to this contract the following key personnel:
Overall Project Manager – responsible to coordinate all activities associated with this contract.
(b) During the first 90 days of performance, the Contractor shall make no substitutions of key personnel unless the substitution is necessitated by illness, death, or termination of employment. The Contractor shall notify the Contracting Officer within 15 calendar days after the occurrence of any of these events and provide the information required by paragraph (c) below. After the initial 90-day period, the Contractor shall submit the information required by paragraph (c) to the Contracting Officer at least 15 days prior to making any permanent substitutions.
(c) The Contractor shall provide a detailed explanation of the circumstances necessitating the proposed substitutions, complete resumes for the proposed substitutes, and any additional information requested by the Contracting Officer. Proposed substitutes should have comparable qualifications to those of the persons being replaced. The Contracting Officer will notify the Contractor within 15 calendar days after receipt of all required information of the decision on substitutions. The contract will be modified to reflect any approved changes of key personnel.
25.
FSAR 4G52.222-701 EMPLOYMENT OF ELIGIBLE WORKERS (DEC 1999)
Section 274A of the Immigration and Nationality Act (8 USC 1324a) makes it unlawful for an employer to hire unauthorized aliens. The Immigration and Naturalization Service (INS) has established the Form I-9, Employment Eligibility Verification Form, as the document to be used for employment eligibility verification (see 8 CFR 274a).
The contractor is required to (1) have all employees complete and sign the I-9 Form to certify that they are eligible for employment; (2) examine documents presented by the employee and ensure the documents appear to be genuine and related to the individual; (3) record information about the documents on the form, and complete the certification portion of the form; (4) retain the form for three years, or one year past the end of employment of the individual, whichever is longer.
It is illegal to discriminate against any individual (other than a citizen of another country who is not authorized to work in the United States) in hiring, discharging, or recruiting because of that individual's national origin or citizenship status.
Compliance with Section 274A of the Immigration and Nationality Act (8 U.S.C. 1324a) is a material condition of the contract. If the contractor employs unauthorized workers during contract performance in violation of section 274A, the Government may terminate the contract, in addition to other remedies or penalties prescribed by law.
For further information on the requirements of the Act, contractors should contact the Employer and Labor Relations Officer of their local INS office.
26.
FSAR 4G52.222-702 LABOR STANDARDS FOR CONTRACTS INVOLVING MIGRANT AND SEASONAL AGRICULTURAL WORKERS (DEC 1999) (a) General. This contract is subject to the Migrant and Seasonal Agricultural Workers Protection Act (MSPA) (29 U.S.C 1801-1872) and to Department of Labor regulations implementing MSPA (see 29 CFR 500). The purpose of MSPA is to eliminate activities that are detrimental to migrant and seasonal agricultural workers, to require registration of farm labor contractors, and to assure necessary protections for the workers. In addition to traditional farm labor activities, the Act applies to predominately manual forestry work including, but not limited to, tree planting, release, precommercial thinning, and site preparation and wildland fire fighting.
(b) Definitions.
"Migrant Agricultural Worker" and "Seasonal Agricultural Worker", as used in this clause, mean individuals employed in agricultural (including forestry) work on a seasonal or temporary basis. A worker who moves from one seasonal activity to another is employed on a seasonal basis even though the worker may continue to be employed during a major portion of the year. Migrant workers are required to be absent overnight from their permanent place of residence. Seasonal workers are not required to be absent overnight from their permanent place of residence. Members of the contractor's immediate family are not considered to be either migrant or seasonal workers. "Immediate family" includes only (1) spouse; (2) children, stepchildren, or foster children; (3) parents, stepparents, or foster parents; and (4) brothers and sisters.
"Farm Labor Contractor", as used in this clause, means an individual who, for any money or other valuable consideration, paid or promised to be paid, performs any recruiting, soliciting, hiring, employing, furnishing, or transporting of any migrant or seasonal agricultural worker.
(c) Registration Requirement. Any contractor who provides or hires migrant or seasonal workers to perform agricultural or manual forestry work shall first obtain a Certificate of Registration from the Department of Labor or an authorized State agency. The contractor shall carry the Certificate at all times while engaged in contract performance, and shall display it upon request. Any of the contractor's employees who also perform any one or more of the activities defined for a "Farm Labor Contractor" in paragraph (b) must have their own Farm Labor Contractor Employee Certificate.
(d) Worker Protections. The contractor shall comply with the following protections and standards related to wage disclosure, recordkeeping, vehicle safety, and housing:
(1) The contractor shall display and maintain at the place of employment the MSPA poster provided by the Department of Labor.
(2) Wage and Payroll Standards
(i) The contractor shall disclose in writing to each worker in a language common to the worker the full terms of their employment, including workers compensation information, at the time they are recruited or hired. The Department of Labor provides an optional form WH-516 for contractor's use in disclosure.
(ii) The contractor must keep the following payroll records for each employee: name, address, social security number, basis for wages (i.e. per hour, per tree, per acre), number of units earned if paid on a per unit basis, hours worked, total pay, withholdings and purpose for each, and net pay. Payroll records shall be retained for three years.
(iii) Payments must be made no less frequently than every two weeks or semi-monthly. At the time of each payment, the contractor shall provide to the employee a written itemization of the information listed above and which shall include the employer's tax identification number.
(iv) If paid on a piece rate basis, the employee's wage must be at least equivalent to the required hourly wage for the hours worked, including overtime differential for time in excess of 40 hours per week.
(3) Motor Vehicle Safety
(i) The contractor must be registered to transport employees, unless employees provide their own transportation or carpool by their own arrangement in one of their own vehicles. The authorization to transport employees must appear on the contractor's certificate. If the contractor directs or requests employees to carpool, the registration requirement is still applicable. Any driver who transports workers for a fee or at the direction of the contractor must be registered as a farm labor contractor or a farm labor contractor employee.
(ii) Any vehicle under the ownership or control of the contractor shall comply with safety standards applicable to that vehicle. Generally passenger vehicles or station wagons must comply with Department of Labor regulations at 29 CFR 500.104. Vehicles other than passenger vehicles or station wagons which are driven more than 75 miles must comply with Department of Transportation Regulations at 29 CFR 500.105. All drivers must have a current, valid State driver’s license.
(iii) Each vehicle under the ownership or control of the contractor which is used to transport any migrant or seasonal agricultural worker shall be covered by vehicle insurance of $100,000 per seat (maximum $5,000,000). A workers compensation policy which covers the workers while being transported plus an additional property damage policy for $50,000 for loss or damage in any one accident to the property of others may be substituted for the vehicle insurance requirement.
(4) Housing
(i) The contractor shall house workers only in a commercial establishment or a facility that has been certified by a health authority or other appropriate agency. The contractor must post the certificate of occupancy at the housing site.
(ii) The authorization to furnish housing, other than commercial lodging, must appear on the contractor's certificate.
(iii) If the contractor is not furnishing worker housing:
Workers on this contract may obtain housing only in a residential accommodation, including a commercial establishment such as a hotel or motel, which meets all applicable state and federal standards for employee housing.
Within 10 days after award, and prior to the issuance of Notice to Proceed, the contractor must notify the Contracting Officer of the planned worker housing site.
If the housing site is located on a National Forest, the Contractor must obtain a permit from the District Ranger for the District on which the housing site is located and the facilities established for the workers must meet the applicable U.S. Department of Labor (USDOL) MSPA standards for such sites.
If the housing site is not located on a National Forest, the site must meet the applicable housing standards in MSPA.
If an exemption from the permit requirement is claimed, the contractor must provide a written statement identifying the law authorizing the exemption, stating the facts constituting an exemption under that law, and identifying a USDOL employee or official who stated or concurred that the accommodations were exempt, citing name, date, and means of communication.
If the housing site is changed after approval by the Contracting Officer, the contractor must provide a new Permit or exemption statement. The above requirements are material conditions of this contract. If the contractor fails to comply, the Government may terminate the contract. In addition, other remedies or penalties prescribed by law may apply
Field Sanitation
In accordance with US Department of Labor Fact Sheet No. ESA 97-28 “Field Sanitation Standards” (Ref. 29CFR 1928.110), employers must provide:
· Potable drinking water, suitably cool and in sufficient amounts, dispensed in single-use cups or by fountains, located so as to be readily accessible to employees.
· Facilities maintained in accordance with public health sanitation practices include upkeep of water quality through daily change or more often if necessary.
· Notification to each employee of the location of the water and allowance of reasonable opportunities during the workday to use them. The employer also must inform the employee of the relevant health hazards in the field and the practices necessary to minimize them.
Employees cannot be made to bear the costs incurred by the employer for providing required facilities.
(e) For further information on the requirements of the Act, contractors should contact their local Wage and Hour Division of the Department of Labor.
27.
FSAR 4G52.222-703 MIGRANT AND SEASONAL AGRICULTURAL WORKER PROTECTION ACT REGISTRATION (DEC 1999) The Migrant and Seasonal…