007-StatementofWork.pdf
PDF 452 KB Posted
- Solicitation number
- AG-0489-S-10-0481
About this file
007-STATEMENT OF WORK
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Amendment 1_SF30 Cape.doc | DOC document | |
| 002-Drawings2of4.pdf | ||
| 008-GeotechnicalReport.pdf | ||
| 011-ContractorPerformanceDataSheet.doc | DOC document | |
| 004-Drawings4of4.pdf | ||
| 003-Drawings3of4.pdf | ||
| 009-Fire Protection.pdf | ||
| 006-Specifications2of2.pdf | ||
| 001-Drawings1of4.pdf | ||
| AG-0489-S-10-0481.pdf | ||
| 005-Specifications1of2.pdf | ||
| 010-OR55Bldg.pdf |
Show all 12
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
STATEMENT OF WORK
Siuslaw National Forest, Central Coast Ranger District Cape Perpetua Recreational Area, Water and Wastewater System Upgrades, 2010
PART 1 – GENERAL
1.01 CURRENT CONDITIONS:
A. The Cape Perpetua Recreational Area is part of a scenic area on the Central Oregon Coast located approximately three miles south of Yachats, Oregon in the Siuslaw National Forest. The recreational area includes the Devil’s Churn Wayside, the Cape Perpetua Campground, and a Visitor’s Center. The year round scenic area is especially attractive to hikers, nature lovers, and whale watchers.
B. The water system for the recreational area consists of a well/pump, chlorination system, a storage tank, water distribution system, and pressure tanks at the wayside and Visitor’s Center. The well and well house are located at the eastern end of the campground with the water tank above the campground. The water tank consists of a 20,000 gallon, concrete tank. The distribution system route begins at the tank and follows the well line back down to the campground. The waterlines run east and west through the campground. Where the campground water main extends out to US Highway 101, it splits north and south and feeds water to Devil’s Churn and the Visitor’s Center.
C. The wastewater from the Visitor’s Center and the campground flows by gravity to the wastewater treatment plant (WWTP) at the west end of the campground. The wastewater from the Devil’s Churn Wayside flows to a small pump station near the Devil’s Churn comfort station and is pumped to the WWTP. The WWTP consists of a settling/aerations basin, a pump station, a chlorine contact chamber, and effluent pumps. The effluent pumps pump the wastewater to a spray field (called Land Assimilation system in the Water Pollution Control Facilities Permit) south of the Visitor’s Center.
D. The Devil’s Churn rest stop is the only roadside rest stop on Highway 101 for several miles in each direction. As a consequence it receives a high amount of tourist and traveler traffic. The rest stop has 15 parking spaces. The onsite buildings include a combination information center and concession stand and restroom facilities. This site also includes an information kiosk and a viewing platform.
E. The Cape Perpetua Campground is southeast of the Devil’s Churn Wayside.
The campground has 40 overnight camping spaces with water services to the majority of the sites. The Campground is situated from west (entrance off of Highway 101) to east in a small valley with Cape Creek on the south side of the campground and a hillside to the north. The campground includes comfort stations, an RV dump site, and a day use area.
F. The Cape Perpetua Visitor’s Center is southwest of the campground on the east side of Highway 101. The Visitor’s Center includes a main building and a comfort station with a staff area in the basement of the comfort station.
AG-0489-S-10-0481
Siuslaw National Forest Central Coast RD, Cape Perpetua
There is vehicle and RV parking at the center. The center offers whale watching views, information about the Oregon Coast and the surrounding area, sales of books and maps, and access to hiking trails.
G. Forest Service hired an Architect and Engineering Firm (Cascade Design) to design upgrades to the water and wastewater systems at the Cape Perpetua Recreational Area. Design work was completed in March 2010.
H. Implementation of the design work for the water and wastewater treatment systems at this recreational area will initiate in 2010.
1.02 PROJECT SUMMARY: This work consists of providing construction services for
Water and Wastewater Systems Upgrades at the Cape Perpetua Recreational Area. Work consists of, but is not limited to the following:
A. Comply with all applicable Federal, State, and local regulations, including but not limited to Environmental Protection Agency, Oregon Occupational Safety and Health Administration, Oregon Bureau of Labor and Industries, Oregon Department of Transportation, and Oregon Department of Environmental Quality.
B. Comply with the most current version of the Oregon Administrative Rules (OARs), applicable to Drinking Water and Wastewater Systems.
C. Contractor shall provide transportation, construction materials, labor, equipment, services, facilities (except as otherwise specified), technical expertise, and all incidentals to comply with the Statement of Work.
D. Work on site consists of (see Section 01 11 00, Summary of Work):
1. Decommissioning an existing wastewater lagoon and an RV dump station. Installation of two new septic tanks.
2. Installing a new wastewater treatment package plant.
3. Pressure testing of existing effluent piping. Providing a new effluent piping as an optional bid item.
4. Replacing a potable water distribution system from the storage reservoir throughout the campground to Highway 101, to Devil’s Churn Wayside and to the Visitor’s Center, the latter two being optional bid items in the contract.
5. Replacing a potable water supply line from the well house to the storage reservoir.
6. Installing a new modular well house with piping and controls (with chlorine treatment) adjacent to the existing well house.
E. Construction work shall be performed in accordance with the Statement of Work, and Drawings and Specifications stated in this contract (see Specifications and Drawings attached to this contract).
F. Contractor shall deliver to Contracting Officer (CO) Site Specific Safety Plans for both, the Water and Wastewater Projects, prior to commencement of field work.
G. Contractor shall preserve existing roads, buildings and facilities, underground utilities, landscapes, and campground landmarks that are not designated for abandonment or removal.
AG-0489-S-10-0481
Siuslaw National Forest
H. A “Major Alteration Permit” with the Oregon Department of Environmental Quality (DEQ) has been initiated, and plans and specifications have been submitted. Fees to Oregon DEQ have been covered by the USDA Forest Service. Contractor shall follow-up with other Oregon DEQ requirements.
This cost shall be indirectly included under mobilization.
I. A “Plan Review” with the Department of Human services-Public Health Division will have to be submitted by the Contractor. This cost shall be indirectly included under mobilization.
J. Contractor shall work directly with the State regulatory agencies regarding notification, permits, authorizations, follow-ups, and final inspection related to work associated with this project.
K. Contractor shall submit to the Forest Service a copy of all paper work submitted to or received by the regulatory agencies.
L. RESTRICTION: Work for the Water System Upgrades at Cape Perpetua Campground shall not commence before September 7, 2010.
1.03 SPECIFICATIONS AND DRAWINGS:
A. Technical specifications and drawings, from the Engineering Firm “Cascade Design”, are attached to this contract. The set of specifications and drawings for the improvements of the water and wastewater systems shall be used in this contract in order to comply with the Statement of Work (see “Technical Specifications; Cape Perpetua, Water & Wastewater System, March 31, 2010; Prepared by Cascade Design” and Drawings “Cape Perpetua, Water and Wastewater System, March 31, 2010, by Cascade Design”).
B. All information in the package shall be taken into account as a guidance and reference for the planning and construction phases.
END OF SECTION
AG-0489-S-10-0481