KRUZOF ISLAND OHV TRAIL RECONSTRUCTION
SUPPLEMENTARY SPECIFICATION
Preface Preface_wo_03_15_2004_m
Delete all but the first paragraph and add the following:
The Forest Service, US Department of Agriculture has adopted FP-03 for construction of National Forest System Roads.
101 - Terms, Format, and Definitions 101.00_nat_us_07_25_2005
101.01_nat_us_01_22_2009
101.01 Meaning of Terms
Delete all references to the TAR (Transportation Acquisition Regulations) in the specifications.
101.03_nat_us_06_16_2006
101.03 Abbreviations.
Add the following to (a) Acronyms:
AFPA
MSHA
NIST
NESC
WCLIB
American Forest and Paper Association Mine Safety and Health Administration National Institute of Standards and Technology National Electrical Safety Code West Coast Lumber Inspection Bureau
Add the following to (b) SI symbols:
mp Milepost ppm Part Per Million
101.04_nat_us_03_29_2007
101.04 Definitions.
Delete the following definitions and substitute the following:
Bid Schedule--The Schedule of Items.
Bridge--No definition.
Contractor--The individual or legal entity contracting with the Government for performance of prescribed work. In a timber sale contract, the contractor is the “purchaser”.
Culvert--No definition.
http://www.nist.gov/�
Right-of-Way--A general term denoting (1) the privilege to pass over land in some particular line (including easement, lease, permit, or license to occupy, use, or traverse public or private lands), or (2) Real property necessary for the project, including roadway, buffer areas, access, and drainage areas.
Add the following:
Adjustment in Contract Price--“Equitable adjustment,” as used in the Federal Acquisition Regulations, or “construction cost adjustment,” as used in the Timber Sale Contract, as applicable.
Change--“Change” means “change order” as used in the Federal Acquisition Regulations, or “design change” as used in the Timber Sale Contract.
Design Quantity--“Design quantity” is a Forest Service method of measurement from the FS-96 Forest Service Specifications for the Construction of Roads and Bridges. Under these FP specifications this term is replaced by the term “Contract Quantities”.
Forest Service--The United States of America, acting through the Forest Service, U.S.
Department of Agriculture.
Neat Line--A line defining the proposed or specified limits of an excavation or structure.
Pioneer Road--Temporary construction access built along the route of the project.
Purchaser--The individual, partnership, joint venture, or corporation contracting with the Government under the terms of a Timber Sale Contract and acting independently or through agents, employees, or subcontractors.
Protected Streamcourse--A drainage shown on the plans or timber sale area map that requires designated mitigation measures.
Road Order--An order affecting and controlling traffic on roads under Forest Service jurisdiction. Road Orders are issued by a designated Forest Officer under the authorities of 36 CFR, part 260.
Schedule of Items--A schedule in the contract that contains a listing and description of construction items, quantities, units of measure, unit price, and amount.
Utilization Standards--The minimum size and percent soundness of trees described in the specifications to determine merchantable timber.
Add Figure 101-1—Illustration of road structure terms:
Figure 101-1—Illustration of road structure terms.
102 - Bid, Award, and Execution of Contract 102.00_nat_us_02_16_2005
102 Bid, Award, and Execution of Contract
Delete Section 102 in its entirety.
103 - Scope of Work 103.00_nat_us_02_16_2005
Deletions
Delete all but subsection 103.01 Intent of Contract.
104 - Control of Work 104.00_nat_us_06_16_2006
Deletions
Delete Sections 104.01, 104.02, and 104.04.
104.06_nat_us_02_17_2005
Add the following subsection:
104.06 Use of Roads by Contractor
The Contractor is authorized to use roads under the jurisdiction of the Forest Service for all activities necessary to complete this contract, subject to the limitations and authorizations designated in the Road Order(s) or described in the contract, when such use will not damage the roads or national forest resources, and when traffic can be accommodated safely.
105 - Control of Material 105.02_nat_us_01_18_2007
105.02 Material Sources.
105.02(a) Government-provided sources.
Add the following:
Comply with the requirements of 30 CFR 56, subparts B and H. Use all suitable material for aggregate regardless of size unless otherwise designated. When required, re-establish vegetation in disturbed areas according to section 625.
105.05_nat_us_05_12_2004
105.05 Use of Material Found in the Work.
Delete 105.05 (a) and (b) and the last sentence of the second paragraph and substitute the following:
Materials produced or processed from Government lands in excess of the quantities required for performance of this contract are the property of the Government. The Government is not obligated to make reimbursement for the cost of producing these materials.
106 - Acceptance of Work 106.07_nat_us_05_11_2004
106.07 Delete
Delete subsection 106.07.
107 - Legal Relations and Responsibility to the Public 107.05_nat_us_05_11_2004
107.05 Responsibility for Damage Claims.
Delete the entire subsection.
107.06_nat_us_06_16_2006
107.06 Contractor’s Responsibility for Work.
Delete the following from the first paragraph.
“except as provided in Subsection 106.07”.
107.09_nat_us_06_16_2006
107.09 Legal Relationship of the Parties.
Delete the entire subsection.
107.10_nat_us_06_16_2006
107.10 Environmental Protection.
Add the following:
Design and locate equipment repair shops, stationary refueling sites, or other facilities to minimize the potential and impacts of hazardous material spills on Government land.
Before beginning any work, submit a Hazardous Spill Plan. List actions to be taken in the event of a spill. Incorporate preventive measures to be taken, such as the location of mobile refueling facilities, storage and handling of hazardous materials, and similar information. Immediately notify the CO of all hazardous material spills. Provide a written narrative report form no later than 24 hours after the initial report and include the following:
• Description of the item spilled (including identity, quantity, manifest number, and other identifying information).
• Whether amount spilled is EPA or state reportable, and if so whether it was reported, and to whom.
• Exact time and location of spill including a description of the area involved.
• Containment procedures.
• Summary of any communications the Contractor had with news media, Federal, state and local regulatory agencies and officials, or Forest Service officials.
• Description of clean-up procedures employed or to be employed at the site including final disposition and disposal location of spill residue.
When available provide copies of all spill related clean up and closure documentation and correspondence from regulatory agencies.
The Contractor is solely responsible for all spills or leaks that occur during the performance of this contract. Clean up spills or leaks to the satisfaction of the CO and in a manner that complies with Federal, state, and local laws and regulations.
108 - Prosecution and Progress 108.00_nat_us_02_16_2005
108 Delete.
Delete Section 108 in its entirety.
109 - Measurement and Payment 109.00_nat_us_02_17_2005
109 Deletions Delete the following entire subsections:
109.06 Pricing of Adjustments.
109.07 Eliminated Work.
109.08 Progress Payments.
109.09 Final Payment.
109.02_nat_us_06_16_2006
109.02 Measurement Terms and Definitions.
(b) Contract quantity.
Add the following:
Contract quantities will be adjusted only when there are errors in the original design of 15% or more.
Change the following:
“(b) Cubic yard” to “(c) Cubic yard”.
Add the following definition:
(p) Thousand Board Feet (Mbf). 1,000 board feet based on nominal widths, thickness, and extreme usable length of each piece of lumber or timber actually incorporated in the job. For glued laminated timber, 1,000 board feet based on actual width, thickness, and length of each piece actually incorporated in the job.
155 - Schedules for Construction Contracts 155.00_nat_us_05_11_2004
155 Delete.
Delete Section 155 in its entirety.
220 – Trail Reconstruction
Description
220.01 Work. Work consist of placing a lift of shotrock (depth as shown on plans) on the original trail.
Materials
220.02 Requirements. Use materials meeting requirements of the following sections of FP03:
Division 200 Earthwork Division 300 Aggregate Courses Section 602 Culverts and Drains
Construction
220.03 Drainage. Install culverts as shown on the plans in the areas to be specified by the C.O.
220.4 Reshaping and Finishing Trail and Backslopes. Provide a firm and uniformly finished trail in accordance with typical shown on the drawings.
Measurement
220.05 Method. Measure the quantities in accordance with Section 220 items listed in the bid schedule according to Subsection 109.02.
Payment
220.06 Basis. The accepted quantities will be paid at the contract price per unit of measurement for the Section 220 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in the Section See Subsection 109.05.
Pay Item Pay Unit
22001 Trail Reconstruction . . . . . . . . . . . . . . . . . . . . . LS
570 – Steel Trail Bridge
570.01 Work.
This work consist of a contractor design/build steel trail bridge, including foundation, bulkhead, rails, curbs, decking excavation, backfill, riprap, removal and disposal of old structure, and approach fills, material haul as shown on the drawings.
Materials
570.02 Requirements. Use materials meeting requirements of the following sections of FP-03:
Division 200 Earthwork Division 250 Slope Reinforcement And Retaining Walls Division 300 Aggregate Courses Division 550 Bridge Construction Division 600 Incidental Construction
Construction
570.03 General. Design and construct bridges as per the project design criteria and the bridge general notes as shown on the plans.
Measurement
570.4 Method. Measure the quantities in accordance with Section 570 items listed in the bid schedule according to Subsection 109.02.
Payment
220.06 Basis. The accepted quantities will be paid at the contract price per unit of measurement for the Section 570 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in the Section See Subsection 109.05.
Pay Item Pay Unit
57001 Install __’ Steel Bridge, Design/Construct . . . . . . . . . . . . . . . . . . . . . LS
640 – Waterbar Construction
640.01 Work.
This work consist of a contractor building waterbars at locations designated by the C.O. The construction shall include all excavation, backfill and compaction as shown on the drawings.
Materials
640.02 Requirements. Use materials meeting requirements of the following sections of FP-03:
Division 200 Earthwork Division 300 Aggregate Courses
Construction
640.03 General. Install waterbars of the types and at the locations shown on the drawings or as designated on the ground.
640.04 Excavation and Embankment. Perform excavation and embankment in accordance with Division 200 Earthwork and Division 300 Aggregate Courses.
Measurement
570.05 Method. Measure the quantities in accordance with Section 640 items listed in the bid schedule according to Subsection 109.02.
Payment
220.06 Basis. The accepted quantities will be paid at the contract price per unit of measurement for the Section 640 pay items listed in the bid schedule. Payment will be full compensation for the work prescribed in the Section See Subsection 109.05.
Pay Item Pay Unit
64001 Waterbar Construction . . . . . . . . . . . . . . . . . . . . . Each
718 - Traffic Signing and Marking Material 718.05_nat_us_08_05_2009
718.05 Aluminum Panels
Delete the third paragraph and replace with the following:
Clean, degrease and properly prepare the panels according to methods recommended by the sheeting manufacturer. Conversion coatings will conform to ASTM B-921 or ASTM B-449.
| kruzof_island_ohv_supplementary_specs.pdf |
| KRUZOF ISLAND OHV TRAIL RECONSTRUCTION |
| SUPPLEMENTARY SPECIFICATION |
| Preface |
| 101 - Terms, Format, and Definitions |
| 101.01 Meaning of Terms |
| 101.03 Abbreviations. |
| 101.04 Definitions. |
| 102 - Bid, Award, and Execution of Contract |
| 102 Bid, Award, and Execution of Contract |
| 103 - Scope of Work |
| Deletions |
| 104 - Control of Work |
| Deletions |
| 104.06 Use of Roads by Contractor |
| 105 - Control of Material |
| 105.02 Material Sources. |
| 105.02(a) Government-provided sources. |
| 105.05 Use of Material Found in the Work. |
| 106 - Acceptance of Work |
| 106.07 Delete |
| 107 - Legal Relations and Responsibility to the Public |
| 107.05 Responsibility for Damage Claims. |
| 107.06 Contractor’s Responsibility for Work. |
| 107.09 Legal Relationship of the Parties. |
| 107.10 Environmental Protection. |
| 108 - Prosecution and Progress |
| 108 Delete. |
| 109 - Measurement and Payment |
| 109 Deletions |
| 109.02 Measurement Terms and Definitions. |
| 155 - Schedules for Construction Contracts |
| 155 Delete. |
| 220 – Trail Reconstruction |
| Description |
| Construction |
| Measurement |
| Payment |
| 570 – Steel Trail Bridge |
| Description |
| Construction |
| Measurement |
| Payment |
| 640 – Waterbar Construction |
| Description |
| Construction |
| Measurement |
| Payment |
| 718 - Traffic Signing and Marking Material |
| 718.05 Aluminum Panels |