808_SPS_F06_TRAFFIC CONTROL.doc
DOC document 32 KB Posted
- Attached to
- Road Maintenance IDIQ Federal contract opportunity
- Solicitation number
- AG-046W-S-09-0025A
About this file
Section J - 808 Traffic Control
View the file
Other files for this federal contract opportunity
| File | Type | Posted |
|---|---|---|
| FBO-Award-Notice.pdf | ||
| AG-046W-S-09-0025A_road-maintenance-amend1a.pdf | ||
| AG-046W-S-09-0025A_road-maintenance-amend1.pdf | ||
| 803_SPS_F06_SNOW REM.doc | DOC document | |
| 872_SPS_F06_SIGN MAINT.doc | DOC document | |
| 851_SPS_F06_HAZ OBSTRUCT REM.doc | DOC document | |
| 813_SPS_F06_SPOT SURF.doc | DOC document | |
| 881_SPS_F06_EQUIP MOB MOVE_pbsc.doc | DOC document | |
| 832_SPS_F06_LOAD-HAUL-PLACE MAT_pbsc.doc | DOC document | |
| AG-046W-S-09-0025A_road-maintenance-idiq.pdf | ||
| 811_SPS_F06_SURF MAINT.doc | DOC document | |
| 801_quantity_measurement_terms.doc | DOC document | |
| 807_SPS_F06_EQUIP RENT.doc | DOC document | |
| 833_SPS_F06_DRAIN STRUCT INST-REPL_pbsc.doc | DOC document | |
| 834_SPS_F06_RDWY DRAIN SYS_MAINT_pbsc.doc | DOC document | |
| 861_SPS_F06_MAINT CTLGRDS-GATES-GRDRLS.doc | DOC document | |
| 841_SPS_F06_VEGETATION TREAT.doc | DOC document | |
| 800_definition_abbreviation.doc | DOC document | |
| 842_SPS_F06_RDWY VEG MAINT.doc | DOC document |
Show all 19
On GovTribe
Work with this file on GovTribe
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
R06F06/SPS 808F06 - WORK AREA MANAGEMENT (2/08)
808.01 Description
This Section establishes Contractor responsibilities for traffic control and equipment requirements in work areas.
808.02 Requirements
A. Traffic Conditions - Unless otherwise provided in the SPECIAL PROJECT SPECIFICATIONS, roads are open to traffic with not more than fifteen (15) minutes maximum delay time.
B. A plan for satisfactory handling of traffic, approved by the Government, is required prior to initiating or performing work which interferes with use of traveled roadways.
C. Traffic Control Devices
1. Provide signs and other devices complying with National Standards as contained in Part VI of the Manual of Uniform Traffic Control Devices (MUTCD). Provide traffic control for occupied work areas that is in accordance with these specifications. All signs and devices remain the property of the Contractor.
2. Keep traffic devices current with maintenance operation and remove upon completion.
3. Use warning signs to control traffic approaching the work area from either direction and also from side accesses having standard Government rectangular or trapezoidal-shaped route markers with horizontal numbering.
4. Required signs may be mounted on portable or temporary mountings. Use standard MUTCD shapes, colors, sizes, and legends.
5. Mark hazards incidental to the work within or on the traveled way, shoulders, or turnouts with hazard identification markers, illuminated beacons, and other MUTCD devices to safely guide road users through the area. Mark work segments not completed on a daily basis appropriately for night travel. Obtain authorization before commencing work at night.
6. Advisory speed plates may be used to control traffic through the work area.
D. Flaggers - Provide properly equipped, trained and certified, flag person(s) where the traffic is required to stop before proceeding. Stop traffic in locations which provide width enough for passage of traffic and reasonable protection for vehicles. When flag control is used, advance warning signs are required.
E. Contractor's Equipment
1. Equip all vehicles and machinery operating on or from the traveled way or road shoulder with flashing lights, strobes, or rotary beacons operated continuously while work is in progress. Use truck headlights at all times while operating. Backup horns are required on all self-propelled equipment in excess of 5½ tons gross weight.
2. Park vehicles and machinery not currently used in the maintenance operation off the traveled way at approved locations to minimize interference with normal use.
808.03 Measurement and Payment
No separate measurement or payment will be made for meeting requirements of this Section. All work and materials are incidental to paid work in this contract.
SPS808F06 - WORK AREA MANAGEMENT (2/28/08) 1