808_SPS_F06_TRAFFIC CONTROL.doc

DOC document 32 KB Posted

Attached to
Road Maintenance IDIQ Federal contract opportunity
Solicitation number
AG-046W-S-09-0025A
Issued by
Department of Agriculture Forest Service R6-Pacific Northwest Region

About this file

Section J - 808 Traffic Control

View the file

Other files for this federal contract opportunity

Other files attached to Road Maintenance IDIQ, newest first.
File Type Posted
FBO-Award-Notice.pdf PDF
AG-046W-S-09-0025A_road-maintenance-amend1a.pdf PDF
AG-046W-S-09-0025A_road-maintenance-amend1.pdf PDF
803_SPS_F06_SNOW REM.doc DOC document
872_SPS_F06_SIGN MAINT.doc DOC document
851_SPS_F06_HAZ OBSTRUCT REM.doc DOC document
813_SPS_F06_SPOT SURF.doc DOC document
881_SPS_F06_EQUIP MOB MOVE_pbsc.doc DOC document
832_SPS_F06_LOAD-HAUL-PLACE MAT_pbsc.doc DOC document
AG-046W-S-09-0025A_road-maintenance-idiq.pdf PDF
811_SPS_F06_SURF MAINT.doc DOC document
801_quantity_measurement_terms.doc DOC document
807_SPS_F06_EQUIP RENT.doc DOC document
833_SPS_F06_DRAIN STRUCT INST-REPL_pbsc.doc DOC document
834_SPS_F06_RDWY DRAIN SYS_MAINT_pbsc.doc DOC document
861_SPS_F06_MAINT CTLGRDS-GATES-GRDRLS.doc DOC document
841_SPS_F06_VEGETATION TREAT.doc DOC document
800_definition_abbreviation.doc DOC document
842_SPS_F06_RDWY VEG MAINT.doc DOC document
Show all 19

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

R06F06/SPS 808F06 - WORK AREA MANAGEMENT (2/08)

808.01 Description

This Section establishes Contractor responsibilities for traffic control and equipment requirements in work areas.

808.02 Requirements

A. Traffic Conditions - Unless otherwise provided in the SPECIAL PROJECT SPECIFICATIONS, roads are open to traffic with not more than fifteen (15) minutes maximum delay time.

B. A plan for satisfactory handling of traffic, approved by the Government, is required prior to initiating or performing work which interferes with use of traveled roadways.

C. Traffic Control Devices

1. Provide signs and other devices complying with National Standards as contained in Part VI of the Manual of Uniform Traffic Control Devices (MUTCD). Provide traffic control for occupied work areas that is in accordance with these specifications. All signs and devices remain the property of the Contractor.

2. Keep traffic devices current with maintenance operation and remove upon completion.

3. Use warning signs to control traffic approaching the work area from either direction and also from side accesses having standard Government rectangular or trapezoidal-shaped route markers with horizontal numbering.

4. Required signs may be mounted on portable or temporary mountings. Use standard MUTCD shapes, colors, sizes, and legends.

5. Mark hazards incidental to the work within or on the traveled way, shoulders, or turnouts with hazard identification markers, illuminated beacons, and other MUTCD devices to safely guide road users through the area. Mark work segments not completed on a daily basis appropriately for night travel. Obtain authorization before commencing work at night.

6. Advisory speed plates may be used to control traffic through the work area.

D. Flaggers - Provide properly equipped, trained and certified, flag person(s) where the traffic is required to stop before proceeding. Stop traffic in locations which provide width enough for passage of traffic and reasonable protection for vehicles. When flag control is used, advance warning signs are required.

E. Contractor's Equipment

1. Equip all vehicles and machinery operating on or from the traveled way or road shoulder with flashing lights, strobes, or rotary beacons operated continuously while work is in progress. Use truck headlights at all times while operating. Backup horns are required on all self-propelled equipment in excess of 5½ tons gross weight.

2. Park vehicles and machinery not currently used in the maintenance operation off the traveled way at approved locations to minimize interference with normal use.

808.03 Measurement and Payment

No separate measurement or payment will be made for meeting requirements of this Section. All work and materials are incidental to paid work in this contract.

SPS808F06 - WORK AREA MANAGEMENT (2/28/08) 1

File details come from the government source that posted it. Updated .