List_of_Revisions_from_Original_M-C_Boat_Docks_Solic.pdf
PDF 319 KB Posted
- Solicitation number
- AG-03H6-S-15-0006
About this file
This document details the revisions from the original M-C boat docks solicitation AG-03H6-S-15-0002 that was cancelled on 6-9-15.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Meriwether-Coulter Boat Dock Reconstruction
Changes from former solicitation AG-03H6-S-15-0002 dated 3/17/15
SPECIFICATIONS:
Schedule B o Schedule broken into three sections
1. Base Bid (Meriwether)
2. Additive 1 Bid Items (Coulter)
3. Additive 2 Bid Items (Demolition & Disposal) o 25406-A Treated Timber Crib Retaining Wall Repairs
1. Convert from “lump sum” bid item to “each” o 64605-A Floatable Dock System – Maintenance Tools & Extra Parts
1. This line item was added to the base bid schedule
Section C o Scope of contract
1. Revised to break out base bid and option items into separate descriptions.
2. In the Note, highlighted and italicized “or an approved equal” to exhibit that alternate modular dock systems may be considered if in compliance with specifications.
Pre-Bid Tour o No formal pre-bid tour is scheduled
Section F o Completion date changed to 15 June 2016
FOREST SERVICE SUPPLEMENTAL SPECIFICATIONS (FSSS)
103 – Scope of Work o Revised to break out base bid and option items into separate descriptions.
o In the Note, highlighted and italicized “or an approved equal” to exhibit that alternate modular dock systems may be considered if in compliance with specifications.
105 – Control of Material o Gabion Infill Rock Source – Government Furnished
Added note for general location of rock source in parenthesis
(approximately 100 yards NE of the mooring barge location)
201 – Clearing and Grubbing o 201.01 Description
Eliminated language directing slash to be removed from site and replaced with language directing slash to be stored on site.
DRAWINGS
Sheet 3 of 9 o Replaced “Estimated Quantities” table with revised table
Sheet 7 of 9 o Replaced “Estimated Quantities” table with revised table o In “Tree/Brush Removal Area”, eliminated language directing slash to be removed from site and replaced with language directing slash to be stored on site.
o Previous option item dock slip has been changed to future boat slip option (removed from scope of work for this contract)
Sheet 8 of 9 o Previous option item dock slip has been changed to future boat slip option (removed from scope of work for this contract)