Text version
AG-02NV-S-10-0085
Hughes Creek Culvert Replacement
IDAWY ACQUISITION SERVICE CENTER INSTRUCTIONAL COVER SHEET
issuing office:
U.S. Department of Agriculture
Forest Service
IDAWY Acquisition Service Center
1405 Hollipark Dr.
Idaho Falls, ID 83401
FAX (208) 557-5829
solicitation no.:
AG-02NV-S-10-0085
offers are solicited for: Hughes Creek Culvert Replacement important – notice to offeror:
at a minimum, offeror shall submit the following documents back with their response to this solicitation:
1. SF-1442 Solicitation, Offer, and Award (Complete, date, and sign)
2. Section B – Schedule of Items (Pages 4-6). (Complete Unit Price and Amount)
3. Section K – Representations and Certifications (Pages 49-53). (Complete the Representations and Certifications electronically via the Online Representations and Certifications Application (ORCA) website at http://orca.bpn.gov)
4. Section L - Technical and Business Proposal (Pages58-60)
5. Bid Guarantee
6. Acknowledge Amendment (If Any) it is required that you write the solicitation number on the outside of your envelope.
Return to:
IDAWY Acquisition Service Center
1405 Hollipark Drive it is required that all contractor’s be registered in the central contractor registration database prior to award under this solicitation. see clause i-2 – far 52.204-7 central contractor registration for details on how to apply.
all solicitations shall be issued through fedbizops. no paper solicitations shall be issued.
it is the offerors responsibility to watch for any and all amendments to the solicitation, which shall be issued electronically through fedbizops.
Table of Contents
PART I – THE SCHEDULE
· SECTION A – SF-1442, Solicitation Offer and Award
· SECTION B – Supplies or Services and Prices/Costs
· SECTION C – Descriptions/Specifications/Statement of Work
· SECTION E – Inspection and Acceptance
· SECTION F – Description and Performance
· SECTION G – Contract Administration Data
· SECTION H – Special Contract Requirements
PART II – CONTRACT CLAUSES
· SECTION I – Contract Clauses
PART III – LIST OF DOCUMENTS,EXIBITS AND OTHER ATTACHMENTS
· SECTION J – Exhibits, Attachments, and Appendices
PART IV – REPRESENTATIONS AND INSTRUCTIONS
· SECTION K – Representations, Certifications and Other Statements of Offerors or Respondents
· SECTION L – Solicitation Provisions
· SECTION M – Evaluation Factors for Award
OMB APPROVAL NO. 2700-0042
SOLICITATION, OFFER,
AND AWARD
(Construction, Alteration, or Repair)
1. SOLICITATION NO.
AG-02NV-S-10-0085
2. TYPE OF SOLICITATION
FORMCHECKBOX
SEALED BID (IFB)
FORMCHECKBOX
NEGOTIATED (RFP)
3. DATE ISSUED
07/29/2010
PAGE OF PAGES
IMPORTANT - The “offer” section on the reverse must be fully completed by offeror.
4. CONTRACT NO.
5. REQUISITION/PURCHASE REQUEST NO.
6. PROJECT NO.
7. ISSUED BY
CODE
| 8. ADDRESS OFFER TO |
USDA, Forest Service
IDAWY Acquisition Service Center
1405 Hollipark Drive
Idaho Falls, ID 83401 USDA, Forest Service
IDAWY Acquisition Service Center
1405 Hollipark Drive
9. FOR INFORMATION
CALL:
A. NAME
Judy Martin B. TELEPHONE NO. (Include area code) (NO COLLECT CALLS)
(208) 557-5841
SOLICITATION
NOTE: In sealed bid solicitations “offer” and “offeror” mean “bid” and “bidder.”
10. THE GOVERNMENT REQUIRES PERFORMANCE OF THE WORK DESCRIBED IN THESE DOCUMENTS (Title, identifying no., date):
Hughes Creek Culvert Replacement North Fork Ranger District
Salmon-Challis National Forest
Lemhi County
Price Range - The Government's estimate is between $100,000 and $250,000.
NOTE: (1) This solicitation is a Request for Proposals. Selection will be based on an evaluation described in Section M. Please review Section L Instructions for the Preparation of Technical and Business Proposals, and Section M prior to submitting your proposal.
(2) This is a Competitive HUBZone Small Business Set-Aside. All eligible and responsible HUBZone sources may submit a proposal. Any questions about HUBZone eligibility should be directed to the Offeror’s cognizant Small Business Administration Office.
11. The Contractor shall begin performance within 10 calendar days and complete it within 90 calendar days after receiving
FORMCHECKBOX
award, FORMCHECKBOX notice to proceed. This performance period is FORMCHECKBOX mandatory, FORMCHECKBOX negotiable. (See Section F clause 52.211-10)
12A. THE CONTRACTOR MUST FURNISH ANY REQUIRED PERFORMANCE AND PAYMENT BONDS?
(If “YES,” indicate within how many calendar days after award in Item 12B.)
FORMCHECKBOX
YES
FORMCHECKBOX
NO
12B. CALENDAR DAYS
10 Calendar Days
13. ADDITIONAL SOLICITATION REQUIREMENTS:
A.
Sealed offers in original and 3 copies to perform the work required are due at the place specified in Item 8 by 3:00 p.m. MST (hour) local time August 30, 2010 (date). If this is a sealed bid solicitation, offers must be publicly opened at that time. Sealed envelopes containing offers shall be marked to show the offeror’s name and address, the solicitation number, and the date and time offers are due.
B.
An offer guarantee
FORMCHECKBOX
is, FORMCHECKBOX is not required. (If “is required” see clause 52.228-1) C.
All offers are subject to the (1) work requirements, and (2) other provisions and clauses incorporated in the solicitation in full text or by reference.
D.
Offers providing less than 60 calendar days for Government acceptance after the date offers are due will not be considered and will be rejected.
NSN 7540-01-155-3212
1442-101
STANDARD FORM 1442 (REV. 4-85)
Computer Generated
Prescribed by GSA
FAR (48 CFR) 53.236-1(e) OFFER (Must be fully completed by offeror)
14. NAME AND ADDRESS OF OFFEROR (Include ZIP Code)
15. TELEPHONE NO. (Include area code)
| Duns No. ____________________________ |
| 16. REMITTANCE ADDRESS (Include only if different than Item 14) |
CODE
FACILITY CODE
17.
The offeror agrees to perform the work at the prices specified below in strict accordance with the terms of this solicitation, if this offer is accepted by the Government within calendar days after the date offers are due. (Insert any number equal to or greater than the minimum requirement stated in Item 13D. Failure to insert any number means the offeror accepts the minimum in Item 13D.
AMOUNTS
18. The offeror agrees to furnish any required performance and payment bonds.
19. ACKNOWLEDGMENT OF AMENDMENTS
The offeror acknowledges receipt of amendments to the solicitation -- give number and date of each
| AMENDMENT NO. |
| DATE |
20A. NAME AND TITLE OF PERSON AUTHORIZED TO SIGN OFFER (Type or print)
20B. SIGNATURE
20C. OFFER DATE
AWARD (To be completed by Government)
21. ITEMS ACCEPTED:
22. AMOUNT
23. ACCOUNTING AND APPROPRIATION DATA
24. SUBMIT INVOICES TO ADDRESS SHOWN IN
(4 copies unless otherwise specified)
ITEM
25. OTHER THAN FULL AND OPEN COMPETITION PURSUANT TO
FORMCHECKBOX
10 U.S.C. 2304(c)( )
FORMCHECKBOX
41 U.S.C. 253(c)( )
26. ADMINISTERED BY
CODE
| 27. PAYMENT WILL BE MADE BY |
IDAWY Acquisition Service Center
1405 Hollipark Drive
Idaho Falls, ID 83401
USDA, National Finance Center
P.O. Box 60000
New Orleans, LA 70160-0001
CONTRACTING OFFICER WILL COMPLETE ITEM 28 OR 29 AS APPLICABLE
FORMCHECKBOX
28. NEGOTIATED AGREEMENT (Contractor is required to sign this document and return ____ copies to issuing office.) Contractor agrees to furnish and deliver all items or perform all work, requisitions identified on this form and any continuation sheets for the consideration slated in this contract. The rights and obligations of the parties to this contract shall be governed by (a) this contract award, (b) the solicitation, and (c) the clauses, representations, certifications, and specifications or incorporated by reference in or attached to this contract.
FORMCHECKBOX
29. AWARD (Contractor is not required to sign this document.) Your offer on this solicitation is hereby accepted as to the items listed. This award consummates the contract, which consists of (a) the Government solicitation and your offer, and (b) this contract award. No further contractual document is necessary.
30A. NAME AND TITLE OF CONTRACTOR OR PERSON AUTHORIZED TO SIGN (Type or print) 31A. NAME OF CONTRACTING OFFICER (Type or print)
30B. SIGNATURE
30C. DATE
31B. UNITED STATES OF AMERICA
BY
31C. AWARD DATE
Computer Generated
STANDARD FORM 1442 BACK (REV. 4-85)
PART--THE SCHEDULE
SECTION B--SUPPLIES OR SERVICES AND PRICES
Hughes Creek Culvert Replacements North Fork Ranger District
Salmon-Challis National Forest
Lemhi, County, Idaho This solicitation and any resulting contract is a firm-fixed price type of contract, which under the definition in FAR 16.202-1, “this type of contract provides for a price that is not subject to any adjustment on the basis of the contractor’s cost experience in performing the contract. This contract type places upon the contractor maximum risk and full responsibility for all costs and resulting profit or loss.”
B- 1 - Schedule of Items
Item 1: Base Item – Ditch Creek Crossing on Ransack Loop Road
| ITEM NO. |
| DESCRIPTION |
| MM* |
| PAY UNIT |
| EST. |
QTY
| UNIT PRICE |
| TOTAL PRICE |
| 15101 |
| Mobilization |
| LSQ |
| LS |
| 1 |
| $__________ |
| $___________ |
| 15201 |
| Construction survey and staking |
| LSQ |
| LS |
| 1 |
| $__________ |
| $___________ |
| 15713 |
| Soil erosion and pollution control |
| LSQ |
| LS |
| 1 |
| $__________ |
| $___________ |
| 20102 |
| Clearing and grubbing |
| LSQ |
| LS |
| 1 |
| $__________ |
| $___________ |
| 20304 |
| Removal of existing 48" dia. culvert |
| LSQ |
| LS |
| 1 |
| $__________ |
| $___________ |
| 20411 |
| Embankment construction |
| DQ |
| CY |
| 50 |
| $__________ |
| $___________ |
| 25101 |
| Placed riprap, class 3 (commercial source) |
| DQ |
| CY |
| 24 |
| $__________ |
| $___________ |
| 25117 |
| Rock weir |
| AQ |
| EA |
| 6 |
| $__________ |
| $___________ |
| 30802 |
| Roadway aggregate (commercial source) |
| DQ |
| TON |
| 50 |
| $__________ |
| $___________ |
| 60205 |
| 14' span x 6' rise precast reinforced concrete box culvert with wingwalls and curbs |
| DQ |
| FT |
| 18 |
| $__________ |
| $___________ |
| 62201(A) |
| Equipment rental, hydraulic excavator with thumb attachment |
| AQ |
| HR |
| 8 |
| $__________ |
| $___________ |
| 62201(B) |
| Equipment rental, large dump truck |
| AQ |
| HR |
| 8 |
| $__________ |
| $___________ |
| 62503 |
| Seeding, dry method |
| LSQ |
| LS |
| 1 |
| $__________ |
| $___________ |
| ITEM NO. |
| DESCRIPTION |
| MM* |
| PAY UNIT |
| EST. |
QTY
| UNIT PRICE |
| TOTAL PRICE |
| 62509 |
| Mulching, dry method |
| LSQ |
| LS |
| 1 |
| $__________ |
| $___________ |
| 63313 |
| Object marker, type 3 (wood post) |
| AQ |
| EA |
| 4 |
| $__________ |
| $___________ |
| TOTAL ITEM 1 |
| $___________ |
Item 2: Optional Item A – Hughes Creek Crossing on West Fork Hughes Creek Road
| ITEM NO. |
| DESCRIPTION |
| MM* |
| PAY UNIT |
| EST. |
QTY
| UNIT PRICE |
| TOTAL PRICE |
| 15101 |
| Mobilization |
| LSQ |
| LS |
| 1 |
| $__________ |
| $___________ |
| 15201 |
| Construction survey and staking |
| LSQ |
| LS |
| 1 |
| $__________ |
| $___________ |
| 15713 |
| Soil erosion and pollution control |
| LSQ |
| LS |
| 1 |
| $__________ |
| $___________ |
| 20102 |
| Clearing and grubbing |
| LSQ |
| LS |
| 1 |
| $__________ |
| $___________ |
| 20304 |
| Remove and dispose of existing 9'-4" span x 6'-3" rise structural plate pipe-arch |
| LSQ |
| LS |
| 1 |
| $__________ |
| $___________ |
| 20411 |
| Embankment construction |
| DQ |
| CY |
| 180 |
| $__________ |
| $___________ |
| 25101 |
| Placed riprap, class 5 (commercial source) |
| DQ |
| CY |
| 85 |
| $__________ |
| $___________ |
| 25117 |
| Rock weir |
| AQ |
| EA |
| 3 |
| $__________ |
| $___________ |
| 27251 |
| Geocell foundation stabilization, 6" depth |
| AQ |
| SY |
| 62 |
| $__________ |
| $___________ |
| 30802 |
| Roadway aggregate (commercial source) |
| DQ |
| TON |
| 140 |
| $__________ |
| $___________ |
| 55213 |
| Precast concrete member, footing |
| DQ |
| FT |
| 98 |
| $__________ |
| $___________ |
| 60304 |
| 16' span, 7'-1" rise structural plate arch |
| DQ |
| FT |
| 48 |
| $__________ |
| $___________ |
| 62201(A) |
| Equipment rental, hydraulic excavator with thumb |
| AQ |
| HR |
| 8 |
| $__________ |
| $___________ |
| ITEM NO. |
| DESCRIPTION |
| MM* |
| PAY UNIT |
| EST. |
QTY
| UNIT PRICE |
| TOTAL PRICE |
| 62201(B) |
| Equipment rental, large dump truck |
| AQ |
| HR |
| 8 |
| $__________ |
| $___________ |
| 62503 |
| Seeding, dry method |
| LSQ |
| LS |
| 1 |
| $__________ |
| $___________ |
| 62509 |
| Mulching, dry method |
| LSQ |
| LS |
| 1 |
| $__________ |
| $___________ |
| TOTAL ITEM 2 |
| $___________ |
* Designated Method of Measurement: CQ=Contract Quantity; AQ= Actual Quantity;
LSQ=Lump Sum Quantity Note : Contract Quantity as defined in FP-03 Specification 109.02. The supplemental specification 109.02 states “contract quantities will be adjusted only when there are errors in the original design of 15% or more.”
B-2 – Optional Item
The Government will evaluate offers for award purposes by adding the total price for the optional item (Item 2) to the total price for the base item (Item 1). Evaluation of option will not obligate the Government to award the option item. Award of option item will depend on availability of funds.
Note: Payment for bond premiums in accordance with FAR Clause 52.232-5, Payment Under Fixed-Price Construction Contracts, shall not be in addition to the contract price.
SECTION C--DESCRIPTION/SPECIFICATIONS
C- 1 - Scope of Contract
Base item work includes replacing an existing culvert at the Ditch Creek crossing on Ransack Loop road with a concrete box culvert. This project includes structural excavation, roadway excavation, backfilling, compacting, providing, hauling and placing riprap and crushed aggregate, removing and disposing of existing culvert, and furnishing and installing a 14’ span x 6’ rise precast concrete box culvert.
The optional item includes replacing an existing culvert at the Hughes Creek crossing on the West Fork Hughes creek road with a structural plate arch. This project includes structural excavation, roadway excavation, backfilling, compacting, providing, hauling and placing riprap and crushed aggregate, removing and disposing of existing culvert, and furnishing and installing a structural plate pipe arch.
C- 2 - Project Location
From Salmon, ID, travel north on Hwy 93 approx. 26.5 miles to Hughes Creek Road, No. 60091. Turn left and travel westerly on Hughes Creek Road approx. 2.2 miles to Ditch Creek Road, No. 60089. Turn right and travel ¼ mile to Ransack Loop Road, No. 60093. Turn right and travel easterly 0.4 miles to the Ditch Creek Culvert site. The Hughes Creek Culvert site is located 3.9 miles from the Hwy. 93 junction on Hughes creek Road. Turn left on West Fork Hughes Creek Road, No. 60088 to cross Hughes Creek, which is the culvert replacement site.
C- 3 - Site Visit - (See Section L, FAR clause 52.236-27).
C- 4 - Start Work It is estimated that work will begin July 15, 2011.
C- 5 - Period of Performance (See Section F, FAR clause 52.211-10)
C- 6 - Government-Furnished Property The Government will provide the following items of Government property to the Contractor for use in the performance of this contract. This property shall be used and maintained by the Contractor in accordance with the provisions of the “Government Property” FAR clause contained elsewhere in the contract. The following items will be government furnished:
Unclassified Borrow – The Government provided material source for unclassified borrow on this project is the roadway cut slope located adjacent to the Ditch Creek project site at approximate station 14+00. Obtain material by excavating into the existing cut slope and constructing a new slope as directed by the CO. There is no charge for materials taken from this source so long as they are used on this project. The contractor will work within the existing construction limits as staked and approved in the field by the CO.
C- 7 – Small Business Competitiveness Demonstration Program Pursuant to FAR Part 19.1007 the Government is giving notice that contract award is being issued under the Small Business Competitiveness Demonstration Program.
C- 8 – Inspection of Worksite The Contractor acknowledges they have taken the necessary steps to ascertain the nature and location of work, and have investigated and satisfied themselves as to the general and local conditions that can affect the work or its cost. Any failure of the Contractor to take the actions described and acknowledged in this paragraph will not relieve the Contractor from the responsibility of estimating properly the difficulty and cost of successfully performing the work, or for proceeding to successfully perform the work without additional expenses to the government.
C- 9 – Recycling and Disposal of Refuse
With the exception of materials specifically indicated or specified to be salvaged for reuse in construction, or turned over to the Government, all refuse, excess or waste materials resulting from construction operations shall become the property of the Contractor and shall be recycled and/or disposed of. All disposals shall be in accordance with federal, state, and local laws and regulations. No disposal, viewing or sale of materials and/or equipment shall be allowed on Government property.
C-10 – Safety
During the execution of this contract, the Contractor shall conform to the rules and regulations as set forth by OSHA Safety and Health Standards, 29 CFR Part 1926 - Safety and Health Regulations for Construction. Smoking will not be permitted in any building or structure.
C-11 – Temporary Facilities
(a) STAGING AREA: The Contracting Officer Representative shall arrange the location for exterior stockpiling of materials. The Government will provide adequate staging area as close to the job site as practicable. The Contractor shall be responsible for protecting materials stockpiled against adverse weather, damage, theft, and other risks of loss. The Government assumes no responsibility for material or equipment left in the storage area.
(b) SANITARY FACILITIES: Toilet facilities will not be provided by the Government at job sites. The Contractor shall provide temporary toilet facilities (porta-potty) at the site during all construction work. Toilet facilities shall be provided at a rate of one stool for every 10 workers assigned or working on site with a minimum of one required.
(c) WATER AND ELECTRICITY: Water is available at the site for construction purposes. Utilities are not available at the site for construction purposes. The Contractor will be responsible for coordinating the installation of temporary power for the site and the cost for the service.
C-12 – Existing Utilities
The Contractor shall field verify all utility locations before digging or trenching. This shall include, but not be limited to, the use of sonic, electronic or magnetic detection devices, by noting pull box and utility box locations at the surface, use of locator services, and by potholing. Contractor shall be responsible for repairing any utilities damaged during construction at no additional cost to the Government.
C-13 - Submittals
(a) Definition: Submittals - Product literature, catalog cuts, product samples, shop drawings, as-built drawings, Quality Control Plans, and other documents submitted to the Contracting Officer for information or for review and approval when required.
(b) Submittals shall be presented in two copies unless indicated otherwise. The Contracting Officer will return one copy of the submittal to the Contractor, whether approved or rejected.
(c) Salient characteristics of the materials proposed for use shall be clearly identified in the submittal. The Project Site Superintendent shall certify that he has reviewed the submittal and has determined that the submittal is in full compliance with the requirements of the Contract. Illegible, incomplete, or uncertified submittals may be rejected.
(d) Submittals shall be approved by the Contracting Officer prior to any work being performed on the contract or materials being delivered to the job site.
(e) Review of submittals, and corrections or comments made during the review, does not relieve the Contractor from compliance with the requirements of this Contract.
(f) Allow 14 calendar days for government review of submittals. Review time shall commence upon receipt of a satisfactory submittal certified by the Project/Site Superintendent containing all information required to completely and thoroughly evaluate the submittal. Time shall start anew for each submittal and any required resubmissions.
C-14 - Contractor Requirements
A. All equipment used on the site shall be cleaned and inspected off National Forest land prior to its arrival on the site. The equipment must be 1) free of all mud, seeds, plants, and plant fragments; and 2) free of oil, fuel, or toxic leaks that would wash off into the water. Notify the CO 48 hours in advance of mobilizing equipment to the site to arrange an inspection. Construction equipment does not include cars, pickup trucks, and other vehicles that regularly travel between the construction site and areas outside of National Forest System lands.
B. Submit for approval, a written Hazardous Spill Plan for all projects which involve fuel storage and refueling actions. The plan will contain a description of the specific hazardous materials, procedures, and spill containment that will be used, including inventory, storage, and handling. All vehicles carrying fuel will have specific equipment and materials needed to contain or clean up any incidental spills at the project site. Equipment and materials will be specific to each project site, and can include spill kits appropriately sized for specific quantities of fuel, shovels, absorbent pads, straw bales, containment structures and liners, and/or booms. Storing and refueling areas will be located in staging areas away from streams in areas where a spill would not have the potential to reach live water. Containment structures may be necessary if prevention of spilled material from reaching live water cannot be assured.
C. Should quantities of stored fuel for a project exceed 660 gallons in a single tank; or exceed 1320 gallons for all storage combined; contractors and agency operators will be required to have a standard EPA written Spill Prevention Control and Containment (SPCC) Plan onsite, which describes measures to prevent or reduce impacts from potential spills from fuel, hydraulic fluid, etc. (40 CFR 112, Oil Pollution Act relating to SPCC Plans).
D. Submit a Traffic Control Plan for approval meeting requirements of FSSS 156.
E. Construction work shall be put on hold during any intense seasonal storms, to reduce surface runoff and sediment input to streams.
C-15 - Technical Requirements
Specific construction drawings and Forest Service Supplemental Specifications are included in Section J. All items shown or noted on plans, which are not specifically proposal items, are considered indirect payment items, per FP-03, Section 109.05(b). The cost of furnishing and installing all indirect payment items will not be paid for separately, but shall be included in the unit price proposed for other items unless noted otherwise.
C-16– Standard Specifications For Construction Of Roads And Bridges on Federal Highway Projects The Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects, FP-03, U.S. Customary Units (FHWA-FLH-03-002) are included by reference. The requirements contained in these specifications are hereby made a part of this solicitation and any resultant contract. Supplemental Project Specifications (SPS) amend or supplement the standard specifications. The Supplemental Project Specifications are included as a separate attached document and are a part of this solicitation and any resulting contract. The following list of Standard and Supplemental Project Specifications are applicable to this project.
FP-03 101
Terms, Format, and Definitions
FSSS 101
Terms, Format, and Definitions
FSSS 102
Bids, Award, and Execution of Contract
FP-03 103
Scope of Work
FSSS 103
Scope of Work
FP-03 104
Control of Work
FSSS 104
Control of Work
FP-03 105
Control of Material
FSSS 105
Control of Material
FP-03 106
Acceptance of Work
FSSS 106
Acceptance of Work
FP-03 107
Legal Relations and Responsibility to the Public
FSSS 107
Legal Relations and Responsibility to the Public
FSSS 108
Prosecution and Progress
FP-03 109
Measurement and Payment
FSSS 109
Measurements and Payment
FP-03 151
Mobilization
FSSS 151
Mobilization
FP-03 152
Construction Survey and Staking
FSSS 152
Construction Survey and Staking
FP-03 154
Contractor Sampling and Testing
FSSS 154
Contractor Sampling and Testing
FSSS 155
Schedules for Construction Contracts
FP-03 156
Public Traffic
FSSS 156
Public Traffic
FP-03 157
Soil Erosion Control
FSSS 157
Soil Erosion Control
FP-03 201
Clearing and Grubbing
FSSS 201
Clearing and Grubbing
FP-03 203
Removal of Structures and Obstructions
FSSS 203
Removal of Structures and Obstructions
FP-03 204
Excavation and Embankment
FSSS 204
Excavation and Embankment
FP-03 251
Riprap
FSSS 251
Riprap
FSSS 272
Geocell Foundation Stabilization
FP-03 308
Minor Crushed Aggregate
FSSS 308
Minor Crushed Aggregate
FP-03 552
Structural Concrete
FSSS 552
Structural Concrete
FP-03 603
Structural Plate Structures
FSSS 603
Structural Plate Structures
FP-03 622
Rental Equipment
FSSS 622
Rental Equipment
FP-03 625
Turf Establishment
FSSS 625
Turf Establishment
FP-03 703
Aggregate
FSSS 703
Aggregate
FP-03 704
Soil
FSSS 704
Soil
FP-03 725
Miscellaneous Material
FSSS 725
Miscellaneous Material
FP-03 736
Geocell
FSSS 736
Geocell
NOTE: Offerors are cautioned to carefully review these Standard and Supplemental Project Specifications prior to submission of proposals. All specifications in the “Standard Specifications for Construction of Roads and Bridges on Federal Highway Projects” FP-03 U.S. Customary Units are binding on the parties signing the contract, including any that may be omitted above.
SECTION D – PACKAGING AND MARKING
D- 1 - Packing and Marking
All shipments of materials, equipment and/or supplies shall be addressed to the Contractor and not to the Government.
D- 2 - Project Labeling for Official Correspondence
The Government singularly identifies each project with a contract number at time of award. The contract number is a unique identifier to purposely and permanently represent an awarded project. The Government issued contract number is to be referenced on all official communication starting upon notice of award.
SECTION E--INSPECTION AND ACCEPTANCE
E- 1 - FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998)
This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/ and the Agriculture Acquisition Regulations may be accessed at www.usda.gov/da/procure/agar/subchaph.html#11.
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.246-12 Inspection of Construction (AUG 1996) E- 2 – Pre-Final and Final Inspection
a. Pre-final Inspection: The Government may, at its own discretion, conduct a pre-final inspection prior to the contractor requesting a final inspection. Any discrepancies noted shall be corrected prior to final inspection.
b. Final Inspection: When the work is ready for final inspection, the Contractor shall submit a written request for the final inspection to the duly assigned Contracting Officer’s Representative at least seven (7) days prior to the desired final inspection date. The final inspection will be performed with the Contractor by the appropriate Government personnel. If any discrepancies are noted, they shall be handled in accordance with 52.246-12.
SECTION F--DELIVERIES OR PERFORMANCE
F- 1 - FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/ and the Agriculture Acquisition Regulations may be accessed at www.usda.gov/da/procure/agar/subchaph.html#11.
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.242-14 Suspension of Work (APR 1984) F- 2 - FAR 52.211-10 Commencement, Prosecution, and Completion of Work (APR 1984) The Contractor shall be required to (a) commence work under this contract within 10 calendar days after the date the Contractor receives the notice to proceed, (b) prosecute the work diligently, and (c) complete the entire work ready for use not later than 90 calendar days from the start date annotated on the Notice to Proceed. The time stated for completion shall include final cleanup of the premises.
SECTION G--CONTRACT ADMINISTRATION DATA
G- 1 - Contract Administration
(a) Contracting Officer means a person with the authority to enter into, administer and/or terminate contracts and make related determinations and findings. The Contracting Officer signs all contractual documents, approves and signs all modifications to contracts, processes and approves payment requests, reviews and makes final decisions on contractual discrepancies, and administers the contract. The Contracting Officer is the only authorized individual to make changes to a contract.
(b) CONTRACTING OFFICER'S REPRESENTATIVE. The Contracting Officer will designate a representative, hereinafter referred to as the Contracting Officer's Representative (COR) or, alternatively, as the Engineer, who will provide on-the-ground administration for the Government. The COR will be designated in writing and a copy of the designation will be furnished to the Contractor before or at the pre-work conference. The Contractor is cautioned to read the COR designation because certain authority under the contract is reserved solely for the Contracting Officer. The term "Contracting Officer" as used throughout the contract shall be interpreted to include the Contracting Officer's designated representative(s) acting within the limits of their delegation of authority.
(c) CONTRACTOR'S REPRESENTATIVE. Any representative of the Contractor shall be designated in writing. The designation shall clearly indicate the name and limitations of authority, if any, of the representative.
G -2 - Address of Correspondence All correspondence, unless otherwise specified, shall be directed to the following address:
(a) The address and telephone number of the Contracting Officer is:
IDAWY Acquisition Service Center Contact:
Judy Martin, Contracting Officer
1405 Hollipark Drive Idaho Falls, ID 83401
(208) 557-5841 Note: Include Contract Number on all correspondence.
SECTION H--SPECIAL CONTRACT REQUIREMENTS
H- 1 - FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/ and the Agriculture Acquisition Regulations may be accessed at www.usda.gov/da/procure/agar/subchaph.html#11.
AGRICULTURE ACQUISITION REGULATION (48 CFR CHAPTER 4) CLAUSES
452.236-72 Use of Premises (NOV 1996)
H- 2 - Key Personnel The key personnel specified in the Offeror’s Technical Proposal are considered to be essential to the work being performed hereunder. Prior to diverting any of the specified individuals to other programs, the Contractor shall notify the Contracting Officer reasonably in advance and shall submit justification (including proposed substitutions) in sufficient detail to permit evaluation of the impact on the contract. No diversion shall be made by the Contractor without the written consent of the Contracting Officer: Provided that the Contracting Officer may ratify in writing such diversion and such ratification shall constitute the consent of the Contracting Officer required by this clause. The contract may be amended from time to time during the course of the contract to either add or delete personnel, as appropriate.
H- 3 - Fire Control
(a) Contractor's Responsibility for Contractor-Caused Fires. The Contractor, whether or not directed by the Forest Service, shall immediately extinguish, without expense to the Government, all fires on or in the vicinity of the project which are caused by Contractor's employees, whether set directly or indirectly as a result of Contractor operations. The Contractor may be held liable for all damages and costs of additional labor, subsistence, equipment, supplies, and transportation resulting from fires set or caused by the Contractor's employees or resulting from contract operations.
(b) Other Fires. For the purpose of fighting forest fires on or in the vicinity of the project which are not caused by the Contractor or the Contractor’s employees, the Contractor when requested by the Contracting Officer shall place the employees and equipment temporarily at the disposal of the Forest Service. Payment for such services will be made by the Government at not less than the current rate for fire-fighting services established by the Forest Service in the area concerned.
Any employees and equipment furnished will be relieved from fire fighting as soon as the Forest Service finds that it is practicable to employ other labor and equipment adequate for the protection of the area.
An equitable adjustment in contract time may be made for this period.
(c) Fire Protection Requirements - Fire Plan. At all times during closed fire season period, as specified by State law, the Contractor shall comply with each of the following provisions to the extent applicable to the Contractor’s operation under the contract.
(1) Fire Tools. The Contractor will provide for each employee in the contract area at least one approved handtool of a type appropriate in the contract area, such as shovel, pulaski, or ax. Tools required and furnished under (2) and (4) below, shall count toward fulfillment of the above requirement. Where additional tools, beyond those required under (2) and (4) below, are to be provided, the Contractor shall seal such tools in one or more boxes painted red and marked "Tools for Fire Only." All tools required herein shall be kept sharp and in good serviceable condition and maintained at locations to be designated by the Forest Service.
(2) Fire Extinguishers and Tools on Mobile or Stationary Equipment. Each unit of powered equipment used in connection with this contract, including automobiles, trucks, tractors, etc., shall be equipped with serviceable tools and fire extinguishers as follows:
One - fire extinguisher, dry chemical type of not less than 2-1/2 pound capacity with 4 BC or higher rating.
One - shovel, round point #0 lady or equal.
One - ax, 2 pounds or over, 26-inch minimum length, or one pulaski.
One - water container (at least 1-gallon capacity), not required with stationary equipment.
(3) Spark Arresters. Each internal combustion engine shall be provided with a spark arrester or spark arresting device approved by the Forest Service. Exceptions where the Forest Service may approve mufflers, or other equipment in lieu of spark arresters qualified and rated under Forest Service Standard 5100-1a are: (a) small multiposition engines, such as chain saws, shall meet Society of Automotive Engineers J335b standards; (b) passenger-carrying vehicles and light trucks may have baffle-type mufflers with tail pipe; (c) heavy-duty trucks may have a vertical stack exhaust system and muffler, provided the exhaust stack extends above the cab of the vehicle. An exhaust-driven turbocharger is considered to be a satisfactory spark arrester. Internal combustion engine exhaust systems, arresters, and other devices must be properly installed and maintained.
(4) Powersaws. For each powersaw used in connection with this contract, the following will be provided:
One - shovel, round point #0 lady or equal. Shovel must be immediately available for use.
One - Fire extinguisher, containing not less than 8 ounces of extinguisher fluid, or a dry chemical powder-type of not less than 1-pound capacity. The extinguisher must be immediately accessible to the saw operator at all times.
Any fueling or refueling of a powersaw shall only be done in an area which has first been cleared or is free of all material capable of carrying fire; powersaw shall be moved at least 10 feet from place of fueling before starting.
(5) Blasting. Fuse or prima cord shall not be used unless authorized in writing by the COR with special precautions stated.
(6) Smoking. Smoking shall not be permitted within the contract area except on surfaced or dirt roads, at landings, within closed vehicles, in camps, or at other posted places, and shall never be allowed while working or traveling on foot.
(7) Storage of Petroleum and Other Highly Flammable Products. Gasoline, oil, grease, or other highly flammable material will be stored either in a separate building used exclusively for such storage, or at a site where all combustible debris and vegetation is cleared away within a radius of 25 feet. Fire extinguishers and/or sand barrels may be required at such locations specified by the Forest Service when unusually hazardous conditions exist.
(8) Debris Burning and Warming Fires. Burning permits will be required for all debris burning fires. Lunch and warming fires may be allowed in fireproofed areas during periods of low fire danger if and as specified in the fire plan. Such fires must not be left burning unattended.
(9) Precautions for Stoves. Stovepipes on all temporary buildings, trailers, and tents using wood burning stoves, will be equipped with roof jacks and serviceable spark arresters of mesh with openings no larger than 5/8 inch.
All stovepipes, inside and out, will not be closer than 2 feet from any wood or other flammable material or 1 foot if the combustible material is protected by a metal or asbestos shield.
(10) Welding. Welding or use of cutting torches will be permitted only in areas that have been cleared or are free of all material capable of carrying fire. Flammable debris and vegetation must be removed from within a minimum of 10 feet radius of all welding and cutting torch operations. A shovel and a 5-gallon standard backpack water container (filled) with handpump attached, shall be immediately available for use in the event of a fire start.
(11) Fire Plan. Prior to initiating work on the contract area, during the closed fire season period, a fire prevention and suppression plan will usually be prepared. The Contractor and the Forest Service will jointly prepare this plan. Such plan shall include a detailed list of men and equipment at the Contractor's disposal for implementing the plan. The fire plan shall also specify additional measures and/or special requirements, such as Hoot Owl restrictions, necessary during periods of critical fire weather conditions.
When Hoot Owl restrictions are invoked, the Forest Service may curtail or shut down all or portions of a Contractor's operations. The following requirements may be imposed:
(i) All high fire risk operations could be terminated at 1300 local time.
(ii) All burning could be stopped, including debris burning fires.
(iii) Patrolman may be required for a period of 2 hours after high fire risk operations and 1 hour after end of work shift. The Contractor shall provide the patrolman unless the contract is for equipment rental, in which case the Government will provide the patrolman.
(12) Pump and Trailer. Not Required.
(13) Burning. Before starting any open burning, the Contractor shall comply with the following:
(i) Submit a burning plan, subject to approval by the Contracting Officer, designed to minimize the impact on air quality and to lessen any fire damage.
(ii) Obtain a burning permit from the District Ranger.
(iii) Use weather forecasts as far as possible in scheduling burning for more favorable dispersal of smoke.
(iv) Fuel shall be reasonably free of dirt and piled to facilitate rapid and complete combustion. Piles shall be tended during burning operations to maintain combustion and to eliminate unnecessary smudges. Piles shall be patrolled during off-work hours to avoid wildfires.
(v) Unless fire season controls dictate otherwise, burning shall be scheduled, as far as practicable, for the most favorable conditions during the burning period.
(vi) Under certain atmospheric conditions, smoke accumulations may become excessive and in these cases, the Regional Forester may, at his/her discretion, prohibit all open burning for definite periods within specific areas of the National Forest.
H- 4 - Incidental Payment Items
The intent of the contract is to provide for the complete construction of the project described in the contract. Unless otherwise provided, the Contractor shall furnish all labor, materials, equipment, tools, transportation, and supplies and perform all work required to complete the project in accordance with drawings, specifications, and provisions of the contract. Payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work and materials will be considered as incidental to and included in the payment for items shown.
H- 5 - Conformity With Drawings and Specifications
Unless working tolerances are specified, all work performed and materials furnished shall be in reasonably close conformity with lines, grades, cross sections, dimensions, and material requirements shown on the drawings, indicated in the specifications, or designated on the ground. "Reasonably close conformity" is compliance with reasonable and customary manufacturing and construction tolerances.
H- 6 - Local Material Sources
(a) Designated Sources--Sources of local materials will be designated on the drawings. The Government assumes responsibility for the quality and quantity of material in the source. The Contractor shall determine the equipment and work required to produce the specified product.
The Contractor shall utilize all suitable material in the source. The designation of source will include the rights of the Contractor to use certain area(s) for plant site, stockpiles, and haul roads. Any Contractor royalty payment requirements will be stated below.
When materials are subject to weight measurement, the weight/volume relationship used for determination of designed quantities will be shown on the Drawings.
Should the designated source, due to causes beyond the control of the Contractor, contain insufficient suitable material, the Government will provide another source with an equitable adjustment in accordance with the Differing Site Conditions and Changes clauses.
(b) Contractor-Furnished Sources--When the material sources are not designated as provided above or the Contractor elects not to use designated sources, the Contractor shall be responsible for providing the specified product with no adjustment in contract price, unless weight/volume relationship differences between designated source material and Contractor-furnished source material result in financial disadvantage to the Government. Quality testing shall be the responsibility of the Contractor. Test results shall be furnished to the Contracting Officer.
H- 7 - Samples, Tests, Cited Specifications Reference made in the contract to specifications, standards, or test methods adopted by AASHTO, ASTM, GSA, or other recognized National technical associations, shall mean specifications, standards, or test methods (including interim or tentative issues) which are in effect on the date of the solicitation.
H- 8 - Barricades, Warning Signs, and Other Devices The Contractor shall provide, erect, and maintain all necessary barricades, suitable and sufficient lights, danger signals, signs, and other traffic control devices, and shall take all necessary precautions for the protection of the work and safety of the public. Roads closed to traffic shall be protected by effective barricades, and obstructions shall be illuminated during the hours of darkness. Suitable warning signs shall be provided to properly control and direct traffic.
The Contractor shall erect warning signs in advance to any place on the project where operations may interfere with the use of the road or trail by traffic and at all intermediate points where the new work crosses or coincides with an existing road or trail. All road barricades, warning signs, lights, temporary signals, flagmen and pilot car operators and equipment, and other protective devices, except for special devices, shall conform with Part VI of the Manual on Uniform Traffic Control Devices for Streets and Highways, published by the Federal Highway Administration and applicable safety codes.
Necessary warning signs and guards shall be posted during blasting operations to safeguard the public.
H- 9 - Subcontract Data The Contractor shall submit an executed Statement and Acknowledgment Standard Form 1413, to the Contracting Officer for every subcontractor (including every subcontractor of the second or lower tier) that will be performing work at the construction site. This shall be submitted before the subcontractor begins work. This form provides an acknowledgment by the subcontractor that mandatory "flowdown" contract clauses have been included in their contract in accordance with FAR Clause 52.222-11. Completing this form creates no contractual relationship between subcontractors and the Government.
H-10 - Site Superintendent It shall be the responsibility of the Contractor to provide a responsible site superintendent to represent the Contractor in the field in all matters under this contract including, but not limited to construction, day-to-day coordination of activities, control over employees and subcontractors, and coordination with local Government personnel. The site superintendent shall be designated in writing. They shall be available on site in person to respond to any and all problems during normal working hours. The site superintendent shall be responsible for on-site Quality Control.
Site superintendent shall maintain on site a file containing the following project documents.
· Executed Copy of the Contract
· Contract Drawings
· Contract Specifications
· Quality Control Plan – (up to date)
· As-Built Drawing – (up to date) if required
· Work Orders
· Modifications
This file shall be maintained and available to the Contracting Officer upon request. If the Site Superintendent is replaced, the existing Superintendent shall review all documents and ongoing issues with the new Superintendent.
H-11 - Designation of Contracting Officer Representative
Prior to the commencement of work, the COR will be designated. The COR is responsible for administering the performance of the work under this contract. In no event, however, will any understanding, agreement, modification, change order, or other matter deviating from the terms of this contract be effective or binding upon the Government unless formalized by the Contracting Officer prior to the completion of this contract.
H-12 – Washing Equipment All equipment used on the site shall be cleaned and inspected off National Forest land prior to its arrival on the site. The equipment must be 1) free of all mud, seeds, plants, and plant fragments; and 2) free of oil, fuel, or toxic leaks that would wash off into the water. Notify the Contracting Officer 48 hours in advance of mobilizing equipment to the site to arrange an inspection.
H-13 – Fuel Storage and Pumps Storage of fuel and other toxicants within Riparian Conservation Areas (RCA – within 300 feet of live streams) is prohibited. Refueling of equipment may be done within the RCA only at locations approved by the Contracting Officer (CO). Centrifugal pumps used for removing water from structure excavation shall sit in a secondary spill container with sufficient capacity to contain the quantity of fuel in the pump fuel tank. A Spill Prevention & Containment Plan is required and shall be submitted to the CO for approval prior to beginning construction. A spill containment kit shall be available on site that is to accommodate potential spills from the equipment used during construction.
All pumps used for drafting shall be outfitted with a suction screen that has a maximum opening size of 3/32”. Locate water drafting sites at a location approved by the Contracting Officer.
H-14 - Prework Conference Prior to commencement of work, the Contracting Officer will arrange a meeting with the Contractor to discuss the contract terms and work performance requirements. Also at this meeting such things as work progress schedule and fire prevention and suppression plans shall be developed and established in writing.
PART II--CONTRACT CLAUSES
SECTION I--CONTRACT CLAUSES
I- 1 - FAR 52.252-2 Clauses Incorporated by Reference (FEB 1998) This contract incorporates one or more clauses by reference, with the same force and effect as if they were given in full text. Upon request, the Contracting Officer will make their full text available. Also, the full text of a clause may be accessed electronically at this/these address(es): www.arnet.gov/far/ and the Agriculture Acquisition Regulations may be accessed at www.usda.gov/procurement/policy/agar.html
FEDERAL ACQUISITION REGULATION (48 CFR CHAPTER 1) CLAUSES
52.202-1 Definitions (JUL 2004) ALT I (MAY 2001)
52.203-3 Gratuities (APR 1984)
52.203-5 Covenant Against Contingent Fees (APR 1984)
52.203-6 Restrictions on Subcontractor Sales to the Government (SEP 2006) 52.203-7 Anti-Kickback Procedures (JUL 1995)
52.203-8 Cancellation, Rescission, and Recovery of Funds for Illegal or Improper Activity
(JAN 1997)
52.203-10 Price or Fee Adjustment for Illegal or Improper Activity (JAN 1997)
52.203-12 Limitation on Payments to Influence Certain Federal Transactions (SEP 2007)
52.204-4 Printed or Copied Double-Sided on Recycled Paper (AUG 2000)
52.209-6 Protecting the Government's Interest when Subcontracting with Contractors Debarred, Suspended, or Proposed for Debarment (SEP 2006)
52.215-2 Audit and Records - Negotiation (JUN 1999) 52.219-3 Notice of Total HUBZone Set-Aside (JAN 1999) 52.219-8 Utilization of Small Business Concerns (MAY 2004) 52.219-14 Limitations on Subcontracting (DEC 1996)
52.219-28 Post-Award Small Business Program Rerepresentation (APR 2009) 52.222-3 Convict Labor (JUN 2003)
52.222-6 Davis-Bacon Act (JUL 2005)
52.222-7 Withholding of Funds (FEB 1988)
52.222-8 Payrolls and Basic Records (JUN 2010)
52.222-9 Apprentices and Trainees (JUL 2005)
52.222-10 Compliance with Copeland Act Requirements (FEB 1988)
52.222-11 Subcontracts (Labor Standards) (JUL 2005) 52.222-12 Contract Termination - Debarment (FEB 1988)
52.222-13 Compliance with Davis-Bacon and Related Act Regulations (FEB 1988)
52.222-14 Disputes Concerning Labor Standards (FEB 1988)
52.222-15 Certification of Eligibility (FEB 1988)
52.222-21 Prohibition of Segregated Facilities (FEB 1999)
52.222-26 Equal Opportunity (MAR 2007)
52.222-27 Affirmative Action Compliance Requirements for Construction (FEB 1999)
52.222-35 Equal Opportunity for Special Disabled Veterans, Veterans of the Vietnam Era, and Other Eligible Veterans (SEP 2006)
52.222-36 Affirmative Action for Workers with Disabilities (JUN 1998)
52…