Attachment_2-MKCAdminSiteBuildingRelocateSpecs.5.13.2015.pdf

PDF 3 MB Posted

Attached to
Relocation of a Bunkhouse and a Visitor Center to the New Administrative Site
Solicitation number
AG-0261-S-15-0057
Issued by

About this file

Attachment 2

View the file

Other files

File Type Posted
amendment_2.pdf PDF
amendment_1.pdf PDF
Attachment_1-Wage_Determination.pdf PDF
ag0261s150057.pdf PDF
Attachment_3-Kyle.Admin.Drawings.5.13.2015.Signed..pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

USDA FOREST SERVICE, R-4

MKC ADMIN SITE BUILDING RELOCATION

SECTION 010250 - CONSTRUCTION STAKING

PART 1 - GENERAL

1.1 SUMMARY

A. This work shall consist of the construction staking of roads, parking lots, parking spurs, culverts, buildings pads, and utilities in accordance with the Drawings and Specifications. The work includes the furnishing of all labor, equipment, instruments, materials, transportation and other incidentals necessary to complete the construction staking in accordance with these specifications and acceptable engineering practice.

1.2 QUALITY CONTROL

A. Construction staking shall be accomplished under the direction of a Civil Engineer, Engineering Technician, or Land Surveyor closely associated and familiar with construction staking; periodic visits to the project site are required.

1.3 MEASUREMENT AND PAYMENT

A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the Schedule of Items.

PART 2 - PRODUCTS

2.1 GOVERNMENT-FURNISHED SURVEY CONTROL SHEETS

A. The Government will provide the contractor with a set of survey control sheets showing horizontal and vertical control for site(s) to be staked. The Government will provide the Contractor with layout information that will include the Northing, Easting, and Elevations for centerline of roads, culverts, spurs and parking areas, edge of parking areas, and corners of buildings and other structures.

2.2 STAKES

A. Identification stakes and hubs shall be of sufficient length and width to provide and solid set in the ground and to provide space for marking above ground when applicable.

Other dimensions and materials may be used, such as steel reinforcing bars, wire flagging and markers, and metal pins, if approved in writing by the Contracting Officer (CO). The top 2 inches of all slope, guard, reference, clearing, and structure stakes shall be painted or marked with plastic flagging. Colors used on stakes or for flagging shall be as follows:

1. Roads, parking lots, and parking spurs -Orange

CONSTRUCTION STAKING 010250-1

Attachment 2 Solicitation No.:AG-0261-S-15-0057

2. Waterlines, utilities, and culverts -Blue

3. Buildings, excavation and grading -Yellow

2.3 SURVEY NOTE PAPER AND BOOKS

A. Paper for survey notes shall be moisture-resistant paper. Notes shall be contained in books with covers that will protect the contents and retain the pages in numerical sequence during field use. Field notebooks or note paper shall be furnished by the contractor.

PART 3 - EXECUTION

3.1 GENERAL

A. The Contractor shall be required to provide all necessary staking and control for all phases of construction. The contractor shall use the data and information shown on the project drawings to establish the location of all facilities to be constructed under this contract. The Contractor may choose any method of establishing horizontal and vertical controls provided the following minimum precision and accuracy requirements are met.

B. Accuracy requirements:

1. Minimum position close; 1/1000

2. Vertical closure: 0.05 ft (vertical)/station (100 feet horizontal)

3. Cross section and slope stake precision:

C. Allowable deviation of cross section line projection from a true perpendicular to tangents, a true bisector of angle points, or a true radius of curves: +/-3 degrees.

D. Cross section topography measurements shall be taken so that variations in ground form a straight line connecting the cross section points will not exceed: 1.0 ft.

E. Horizontal and vertical accuracy for slope stake, slope stake references, and clearing limits. In feet or percentage of horizontal distance measured form centerline or reference stake, whichever is greater. Slope reference stakes and slope stakes: 0.15 ft or 0.6%. Clearing limits: 1.0 ft.

3.2 ESTABLISING AND REFERENCING IMPROVEMENT LOCATIONS

A. Access Roads, Parking Spurs, and Parking lots:

1. Slope stakes (cut and fill catch points), clearing limits, and slope stake references shall be established on both sides of the centerline at each station established.

Slope stakes and slope stake references shall be located on a line at right angles to tangents and on radial lines or curves. Slope stake catch points shall be located by using the grading plans and/or profiles as shown on the drawings.

2. Slope stakes shall be set at 50-foot intervals, at significant breaks in the ground profile, culvert locations, and widening transition points. Slope stakes shall be set at 25 foot intervals around curves having a radius less than 100 feet.

CONSTRUCTION STAKING 010250-2

Attachment 2

B. Culverts

1. Slope stakes and slope reference stakes shall be set at all culvert locations. A culvert reference stake and hub shall be set on the centerline of the culvert 10 feet from each end or beyond the clearing limit, which ever is greater. The following shall be recorded on these stakes:

a. The actual field measured length

b. The vertical and horizontal distance from hubs to the invert at the ends of the culvert.

C. Waterline, Sewerline, & other Utilities

1. Waterline, Sewerline, & other Utilities shall be staked at the locations shown on the drawings with the specified minimum burial depth. Waterline and sewerline elevations shall be accurately staked to provide for drainage as indicated on the drawings. Grade stakes shall be established as necessary to provide the control for the construction work.

D. Buildings Pads

1. Slope stakes and slope stake references shall be established at each corner and as necessary to provide adequate construction control.

3.3 DISCREPANCIES

A. The contractor shall compare the staked centerline horizontal and vertical alignment with the design data. Differences between previously recorded and observed elevations of bench marks shall be referred to the Contracting Officer. Differences in centerline profile elevations exceeding 1 foot at any two or more consecutive points shall be reported to the contracting Officer for evaluation and possible revision. Staking of these areas shall be deferred until the Contacting Officer resolves these differences.

3.4 VERTICAL CONTROL

A. Vertical control for construction shall be as referenced on the Drawings.

3.5 MARKING STAKES

A. All stakes shall be legibly marked, in the format agreed upon with the Contracting Officer, with a stake pencil that leaves an imprinted or with waterproof ink. Marking shall conform to the nomenclature below;

PI Point of Intersection of tangents PC Point of curvature POC Point on curve Pt Point of tangency POT Point on tangent RP Reference point P P-line (preliminary location line) L L-line (final location line)

CONSTRUCTION STAKING 010250-3

Attachment 2

BM Bench mark TBM Temporary bench mark BT Begin taper (any) ET End taper (any) C Cut F Fill L Centerline D Ditch W Width

3.6 SURVEY NOTES

A. All survey data shall be neatly recorded in survey books. All survey notes shall become the property of the Forest Service. Errors shall be deleted by lining out. Date, crew names and positions, instrumentation, and weather shall be recorded in the notes at the beginning of each day’s work. The party chief shall sign or initial each page of the notes immediately after the last entry for each day’s work.

B. Electronically recorded survey notes shall be consecutively numbered and headed to identify the contents. The notes shall be supported and accompanied by a bound book that records the project name and for each day identifies date, crew names and positions, instrumentation, weather, type of survey, stationing of sections between which survey was performed, and survey data or sketched that cannot be electronically recorded. The party chief shall sign or initial the electronically recorded notes and Day Book immediately after the last entry for each day’s work.

END OF SECTION 010250

May 2015

CONSTRUCTION STAKING 010250-4

Attachment 2

SECTION 011250 - MEASUREMENT AND PAYMENT

PART 1 - GENERAL

1.1 SUMMARY

A. Measurement and payment for contract work will be made only for and under those pay items included in the Schedule of Items. All other work, labor, materials, equipment, and incidentals necessary to successfully complete the project will be considered as included in the payment for items shown. This section defines the method of measurements and basis of payment for work items listed in the Schedule of Items.

B. When more than one class, size, type, thickness, etc. is specified in the Schedule of Items for any pay item, suffixes will be added to the item number to differentiate between the pay items.

1.2 DETERMINATION OF QUANTITIES

A. The following measurements and calculations shall be used to determine contract quantities for payment.

1. For individual construction items, longitudinal and lateral measurements for area computations shall be made horizontally or corrected to horizontal measurement unless otherwise specified. Measurements for geotextiles, netting and erosion control blankets shall be along slope lines.

2. For excavation or embankment volumes, the average end area method shall be used to compute volumes. However, if in the judgment of the Contracting Officer (CO), the average end area method is impractical, measurement shall be made by volume in hauling vehicles or by other three-dimensional methods.

3. For Structures, they shall be measured according to neat lines shown on the drawings or as altered by the CO, in writing, to fit field conditions.

4. For items that are measured by the linear foot, such as pipe culverts, fencing, guardrail, piping, utilities, and underdrains, measurements shall be made parallel to the base or foundation upon which the structures are placed.

5. For aggregates weighed for payment, the tonnage shall not be adjusted for moisture content, unless otherwise provided for.

6. For standard manufactured items (such as fence, wire, plates, rolled shapes, pipe conduits) identified by gauge, weight, section dimensions, and so forth, such identifications shall be considered the nominal weights or dimensions. Unless controlled by tolerances in cited specifications, manufacturer's tolerances shall be accepted.

B. Earthwork Tolerances - Adjustments of horizontal or vertical alignment, within the tolerances specified in this contract, or shifts of balance points up to 100 feet shall be made by the contractor as necessary to produce the designed sections and to balance earthwork. Such adjustments shall not be considered as "Changes."

MEASUREMENT AND PAYMENT 011250-1

Attachment 2

1.3 UNITS OF MEASUREMENT

A. Payment shall be by units defined and determined according to U.S. Standard measure and by the following:

1. Acre: Make longitudinal and transverse measurements for area computations horizontally.

2. 50lb Bag: Measurement will be for the actual number of 50lb bags of standard bentonite grout.

3. 94lb Bag: Measurement will be for the actual number of 94lb bags of standard cement or grout.

4. Cubic Yard (CY): A measurement computed by one of the following methods:

a. Excavation, Embankment, or Borrow. The measurement computed by the average end area method from measurements made longitudinally along a centerline or reference line.

b. Material in Place or Stockpile. The measurement computed using the dimensions of the in-place material.

c. Material in the Delivery Vehicle. The measurement computed using measurements of material in the hauling vehicles at the point of delivery.

Vehicles shall be loaded to at least their water level capacity. Leveling of the loads may be required when vehicles arrive at the delivery point.

5. Each (EA): One complete unit, which may consist of one or more parts.

6. Gallons (GAL): The quantity shall be measured by any of the following methods:

a. Measured volume in container.

b. Metered volume by approved metering system.

c. Commercially package volume.

7. Hour (HR): Measurement will be for the actual number of hours (or fraction thereof) ordered by the Contracting Officer and performed by the contractor.

8. Linear Foot (LF): Measurement of work along its length from point-to-point;

parallel to the base or foundation. Do not measure overlaps.

9. Lump Sum (LS): One complete unit.

10. Mile: Measured horizontally along the centerline of each roadway, approach, or ramp.

11. Pound (LB): For sacked or packaged material, measurement will be the net weight as packed by the manufacturer.

12. Square Foot (SF): Measured on a plane parallel to the surface being measured.

13. Square Yard (SY): Measured on a plane parallel to the surface being measured.

14. Ton: Measured as a short ton consisting of 2,000 pounds.

1.4 METHOD OF MEASUREMENT

A. One of the following methods of measurement for determining final payment is designated on the Schedule of Items for each pay item:

1. ACTUAL QUANTITIES (AQ) - These quantities are determined from actual measurements of completed work.

MEASUREMENT AND PAYMENT 011250-2

Attachment 2

2. CONTRACT QUANTITIES (CQ) - These quantities denote the final number or units to be paid for under the terms of the contract. They are based upon the original design data available prior to advertising the project. Original design data include the preliminary survey information, design assumptions, calculations, drawings, and the presentation in the contract. Changes in the number of units shown in the Schedule of Items may be authorized under any of the following conditions:

a. As a result of changes in the work authorized by the CO.

b. As a result of the CO determining that errors exist in the original design that cause a pay item quantity to change by 15 percent or more.

c. As a result of the Contractor submitting to the CO a written request showing evidence of errors in the original design that cause a pay item quantity to change by 15 percent or more. The evidence must be verifiable and consist of calculations, drawings, or other data that show how the designed quantity is believed to be in error.

3. LUMP SUM QUANTITIES (LSQ) - These quantities denote one complete unit of work as required by or described in the contract, including necessary materials, equipment, and labor to complete the job. They shall not be measured.

4. STAKED QUANTITIES (SQ) - These quantities are determined from staked measurements prior to construction.

5. VEHICLE QUANTITIES (VQ) - These quantities are measured or weighed in hauling vehicles.

PART 2 - PRODUCTS (NOT APPLICABLE)

PART 3 - EXECUTION (NOT APPLICABLE)

END OF SECTION 011250

MEASUREMENT AND PAYMENT 011250-3

SECTION 011900 - MOBILIZATION

PART 1 - GENERAL

1.1 SUMMARY

A. This item is intended to compensate the Contractor for operations including, but not limited to, those necessary for the movement of personnel, equipment, supplies, and incidentals to the project site; for payment of premiums for bonds and insurance for the project; and for any other work and operations which must be performed or costs that must be incurred incident to the initiation of meaningful work at the site and for which payment is not otherwise provided for under the contract.

1.2 MEASUREMENT AND PAYMENT

A. The measurement shall be lump sum for mobilization. Payment shall be as follows:

1. Bond premiums will be reimbursed after receipt of the evidence of payment.

2. 50% of the lump sum, not to exceed 5% of the original contract amount, will be paid following completion of 5% of the original contract amount not including mobilization and bond premiums.

3. Payment of the remaining portion of the lump sum, up to 10% of the original contract amount, will be paid following completion of 10% of the original contract amount not including mobilization and bond premiums.

4. Any portion of the lump sum in excess of 10% of the original contract amount will be paid after final acceptance.

5. Progress payments for mobilization and preparatory work shall be subject to retainage.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION (NOT USED)

END OF SECTION 011900

MOBILIZATION 011900-1

SECTION 013300 - SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other miscellaneous submittals. See Table 013300-1 for a summary of required submittals.

B. See other specification section within this package for additional requirements on submittal.

1.2 SUBMITTAL PROCEDURES

A. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

1. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

a. The Contracting Officer (CO) reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

B. Processing Time: Allow enough time for submittal review, including time for re-submittals, as follows. Time for review shall commence on CO's receipt of submittal.

1. Initial Review: Allow 14 days for initial review of each submittal. Allow additional time if processing must be delayed to permit coordination with subsequent submittals. CO will advise Contractor when a submittal being processed must be delayed for coordination.

2. If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Allow 14 days for processing each re-submittal.

4. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing.

C. Identification: Place a permanent label or title block on each submittal for identification.

1. Indicate name of firm or entity that prepared each submittal on label or title block.

2. Provide a space on label or beside title block to record Contractor's review and approval markings and action taken by CO.

3. Include the following information on label for processing and recording action taken:

SUBMITTAL PROCEDURES 013300-1

Attachment 2

a. Project name.

b. Date.

c. Name and address of Contractor.

d. Name of manufacturer.

e. Unique identifier, including revision number.

f. Number and title of appropriate Specification Section.

g. Drawing number and detail references, as appropriate.

h. If more than one item is shown on submittal sheet, identify item.

D. Deviations: Highlight, encircle, or otherwise identify deviations from the Contract Documents on submittals.

E. Additional Copies: Unless additional copies are required for final submittal, and unless CO observes noncompliance with provisions of the Contract Documents, initial submittal may serve as final submittal.

F. Use for Construction: Use only final submittals with mark indicating action taken by CO in connection with construction.

1.3 MEASUREMENT AND PAYMENT

A. No separate measurement and/or payment will be made for this section. Payment shall be included with work shown in the Schedule of Items.

PART 2 - PRODUCTS

2.1 ACTION SUBMITTALS – (Submittals requiring CO approval)

A. General: Prepare and submit Action Submittals required by individual Specification Sections.

1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will return two copies. Mark up and retain one returned copy as a Project Record Document.

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

1. If information must be specially prepared for submittal because standard printed data are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options are applicable.

3. Include the following information, as applicable:

a. Manufacturer's written recommendations.

b. Manufacturer's product specifications.

c. Manufacturer's installation instructions.

d. Manufacturer's catalog cuts.

e. Wiring diagrams showing factory-installed wiring.

f. Compliance with recognized trade association standards.

SUBMITTAL PROCEDURES 013300-2

Attachment 2

g. Compliance with recognized testing agency standards.

C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do not base Shop Drawings on reproductions of the Contract Documents or standard printed data.

1. Preparation: Include the following information, as applicable:

a. Dimensions.

b. Identification of products.

c. Fabrication and installation drawings.

d. Roughing-in and setting diagrams.

e. Wiring diagrams showing field-installed wiring, including power, signal, and control wiring.

f. Notation of dimensions established by field measurement.

2. Wiring Diagrams: Differentiate between manufacturer-installed and field-installed wiring.

D. Contractor's Construction Schedule: The contractor shall submit a Construction Schedule, for approval by CO, in accordance with the contract provisions within 10 days of receipt of the Notice to Proceed, or before the commencement of work.

E. Samples: Prepare physical units of materials or products, including the following:

1. Samples for Initial Selection: Submit manufacturer's color charts consisting of units or sections of units showing the full range of colors, textures, and patterns available.

2.2 INFORMATIONAL SUBMITTALS – (Submittals NOT requiring CO approval)

A. General: Prepare and submit Informational Submittals required by other Specification Sections.

1. Number of Copies: Submit three copies of each submittal, unless otherwise indicated. CO will not return copies.

2. Certificates and Certifications: Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.

3. Test and Inspection Reports: Comply with requirements in Section 014100 "Quality Control."

B. Material Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements.

C. Field Test Reports: Prepare reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements.

SUBMITTAL PROCEDURES 013300-3

Attachment 2

D. Maintenance Data: Prepare written and graphic instructions and procedures for operation and normal maintenance of products and equipment.

E. Manufacturer's Instructions: Prepare written or published information that documents manufacturer's recommendations, guidelines, and procedures for installing or operating a product or equipment. Include name of product and name, address, and telephone number of manufacturer.

PART 3 - EXECUTION

3.1 GENERAL

A. Review each submittal and check for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to CO.

B. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

C. CO will not review submittals that do not bear Contractor's approval stamp and will return them without action.

D. Submittals not required by the Contract Documents will not be reviewed and may be discarded.

E. Substitutions – Whenever materials, products, and equipment are listed by name or brand in the specifications and/or on the drawings, it is used as a measure of quality, utility, or standard. If the Contractor prefers to use any other brand or manufacturer of same quality, appearance and utility to that specified, he shall request substitution as provided below, not less than 30 days before the planned installation of the item. The Contracting Officer will approve or disapprove the request for substitution.

F. Requests for substitutions will only be considered if contractor submits the following:

1. Complete technical data including drawings, complete performance specifications, test data, samples and performance tests of the article proposed for substitution. Submit additional information if required by Contracting Officer.

All items in the above information shall be circled, tagged, or marked in some way to indicate all deviations or differences which the proposed item differs from the originally specified item.

2. Similar data as above for item originally specified. All items shall be marked to identify where/how the proposed substitution will differ.

3. A statement by the Contractor that the proposed substitution is in full compliance with the contract documents, applicable codes, and laws.

4. The Contractor shall be responsible for any effect upon related work in the project for any substitution and shall pay any additional costs generated by any substitutions.

SUBMITTAL PROCEDURES 013300-4

Attachment 2

3.2 SUBMITTAL SCHEDULE – Submittals shall be made as required by and called for in the drawings and specifications. The following table is a summary of the required submittals for the project - the table is to assist the Contractor and may not be all inclusive – additional submittals may be required by specific specifications:

TABLE 013000-1

Spec.

Section Section Title Subsect ion Required Submittal

Section C Section C 1.4 A Traffic Control and Signing Plan 014100 Quality Control 1.2 B Contractor quality control plan 014100 Quality Control 1.2 C Contractor’s Quality Control Daily

Reports 014100 Quality Control 1.2 D Defective work/Corrective action logs 014100 Quality Control 1.2 E Test Reports 014100 Quality Control 1.2 F Off-Site Inspection Reports 014100 Quality Control 1.2 G As-Built Drawings 014100 Quality Control 1.2 H Permits, Licenses, and Certificates 022310 Building Relocation 1.2 A Qualification Data 22310 Building Relocation 1.2 B Project Schedule for Building

Relocations 022310 Building Relocation 1.2 C Foundation Design And Support

Calculations 022310 Building Relocation 1.2 D Modular Building Connection

Details and Calculations 033000 Cast-In-Place Concrete 1.4 A Product Data 033000 Cast-In-Place Concrete 1.4 B Design Mixtures 033000 Cast-In-Place Concrete 1.4 C Steel Reinforcements Shop

Drawings 033000 Cast-In-Place Concrete 1.4 D Material Test Reports 033000 Cast-In-Place Concrete 1.4 E Material Certificates 033000 Cast-In-Place Concrete 1.4 F Field quality-control test reports 221100 Water Distribution Systems 1.3 A Product Data 221100

Water Distribution Systems

1.3 B Plan for disposal of water used for

testing and disinfection of waterlines

221100

Water Distribution Systems

1.3 C Bunkhouse Water System

Operations and Maintenance procedures to be added to site Water System Operations & Maintenance Manual

221300 Sanitary Sewer System 1.3 A Product Data 231126 Facility Liquefied-Petroleum Gas

Piping

1.3 A Product Data

231126 Facility Liquefied-Petroleum Gas 1.3 B Shop Drawings

SUBMITTAL PROCEDURES 013300-5

Attachment 2

Spec.

Section Section Title Subsect ion Required Submittal

Piping 231126 Facility Liquefied-Petroleum Gas

Piping

1.3 C Seismic Qualification

231126 Facility Liquefied-Petroleum Gas Piping

1.3 D Welding Certificates

231126 Facility Liquefied-Petroleum Gas Piping

1.3 D Field quality-control reports

231126 Facility Liquefied-Petroleum Gas Piping

1.3 E Operation and maintenance data

260500 Common Work Results for Electrical

1.2 A Product Data

260533 Raceway and Boxes for Electrical System

1.3 A Product Data

270500 Common Work Results for Communications

1.3A Qualification Data

270500 Common Work Results for Communications

1.3B Product Data

270500 Common Work Results for Communications

1.3C As-Built Drawings & O&M Manuals

270528 Pathways for Communications Systems

1.3A Product Data

271200 Communications Copper Network Cabling 1.3A Product Data

321204 Crushed Aggregate Base or Surface Course

1.2 A Aggregate source, gradation, and

material properties

321204 Crushed Aggregate Base or Surface Course

1.2 B Compaction density test results and

proctor

END OF SECTION 013300

SUBMITTAL PROCEDURES 013300-6

SECTION 014100 - QUALITY CONTROL

PART 1 - GENERAL

1.1 DESCRIPTION

A. The work of this section consists of preparing and executing a quality control program.

B. This section includes administrative and procedural requirements for quality-control services.

C. Quality-control services include inspections, tests, and related actions, including reports performed by Contractor, by independent agencies, and by governing authorities. They do not include contract enforcement activities performed by the Contracting Officer.

D. Testing services are required to verify compliance with requirements specified or indicated. These services do not relieve Contractor of responsibility for compliance with Contract Document requirements.

E. Requirements of this section relate to customized fabrication and installation procedures, not production of standard products.

1. Specific quality-control requirements for individual construction activities are specified in the sections that specify those activities. Requirements in those sections may also cover production of standard products.

2. Specified inspections, tests, and related actions do not limit Contractor’s quality-control procedures that facilitate compliance with Contract Document requirements.

3. Requirements for Contractor to provide quality-control services required by the Contracting Officer, or authorities having jurisdiction are not limited by provisions of this section.

1.2 SUBMITTALS

A. As specified in specification 013300.

B. Quality Control Plan:

1. At the time of the preconstruction conference, submit for approval a written Contractor Quality Control (CQC) Plan.

2. If the CQC Plan requires any revisions or corrections, the Contractor shall resubmit the plan within 10 days.

3. The Government reserves the right to require changes in the CQC Plan during the contract period as necessary to obtain the quality specified.

4. No change in the approved CQC Plan may be made without written concurrence by the Contracting Officer.

QUALITY CONTROL 014100-1

Attachment 2

5. The CQC Plan shall be a comprehensive document that addresses every aspect of the Contractor’s activity in support of quality finished products. Each aspect of quality control addressed by the contract documents shall be addressed.

Mandatory items of the CQC Plan include, but are not limited to the following:

a. A statement of the Contractor’s quality control policy.

b. A list of personnel responsible for quality control and assigned duties.

Include each person’s qualifications.

c. A copy of a letter of direction to the Contractor’s Quality Control

Supervisor outlining assigned duties.

d. Names, qualifications, and descriptions of laboratories to perform sampling and testing, and samples of proposed report forms.

e. Methods of performing, documenting, and enforcing quality control of all work.

f. Methods of monitoring and controlling environmental pollution and contamination as required by regulations and laws.

g. Outline showing each Definable Feature of Work (DFW) (identified by specification section) describing the quality control activities that take place at each phase for each DFW.

h. Detailed description of the mechanisms to be used to track deficient work, notify responsible parties, ensure correction, and provide verification.

Contractor shall maintain a log of defective work/corrective actions and shall provide a copy of new log entries to the Contracting Officer as deficiencies are identified. Provide a sample of the log.

i. Contractor’s program of quality control for items fabricated off-site.

j. Detailed description of how record documents will be identified, collected, organized, and retained during the course of the project.

C. Contractor’s Quality Control Daily Reports: Submit showing all inspections and tests on the first work day following the date covered by the report.

D. Defective work/corrective action logs.

E. Test Reports:

1. Submit Daily Test Information Sheets with Quality Control Daily Reports.

2. Submit failing test results and proposed remedial actions within four hours of noted deficiency.

3. Submit three copies of complete test results not later than three calendar days after the test was performed.

4. Testing and Inspection Reports shall include the following:

a. Date of issue.

b. Project title and number.

c. Name, address, and telephone number of testing agency.

d. Dates and locations of samples, tests, or inspections.

e. Names of individuals performing tests and inspections.

f. Reference Specification Section(s).

g. Complete test or inspection data.

QUALITY CONTROL 014100-2

Attachment 2

h. Test and inspection results and an interpretation of test results.

i. Ambient conditions at time sample was taken, tested, or inspected.

j. Comments or professional opinion on whether tested or inspected work complies with the Contract Document requirements.

k. Name and signature of laboratory inspector.

l. Recommendations on retesting and reinspecting.

F. Off-Site Inspection Reports: Submit prior to shipment.

G. As-Built Drawings

H. Permits, Licenses, and Certificates

I. If the CQC plan and Quality Control Daily Reports are not submitted as specified, the Contracting Officer may retain all payments until such time a plan is approved and implemented.

1.3 QUALITY ASSURANCE

A. General:

1. The quality of all work shall be the responsibility of the Contractor. Testing shall be the responsibility of an independent testing laboratory, the cost of which shall be borne by the Contractor.

2. Inspect and test all work often enough to ensure that the quality of materials, workmanship, construction, finish, and functional performance is in compliance with applicable specifications and drawings.

3. Quality Control Daily Reports shall be completed by the Quality Control Supervisor.

4. Test reports shall be completed by person performing the test.

5. The Contracting Officer may designate locations of tests.

B. Quality Control Staff:

1. The Contractor's Quality Control Supervisor may also perform the duties of Project Superintendent.

2. The Contractor's designated Quality Control Supervisor shall be on the project site whenever contract work is in progress.

3. The Contractor's job supervisory staff may be used to assist the Quality Control Supervisor, supplemented as necessary by additional certified testing technicians.

C. Testing Laboratory and Equipment:

1. Employ certified independent laboratories to perform sampling and testing. The testing laboratory organization shall be certified for the type of testing work to be done.

2. All measuring devices, laboratory equipment, and instruments shall be calibrated at established intervals against certified standards in accordance with NBS requirements. Upon request, measuring and testing devices shall be made available for use by the Government for verification tests.

QUALITY CONTROL 014100-3

Attachment 2

1.4 MEASUREMENT AND PAYMENT

A. No separate payment will be made for the work included under this section; rather payment shall be considered to be included in the items of work listed in the Schedule of Items.

PART 2 - PRODUCTS (Not Applicable)

PART 3 - EXECUTION

3.1 OFF-SITE CONTROL

A. Items that are fabricated or assembled off-site shall be inspected for quality control at the place of fabrication.

3.2 ON-SITE CONTROL

A. Notification:

1. Notify the Contracting Officer at least 48 hours in advance of the preparatory phase meeting.

2. Notify the Contracting Officer at least 24 hours in advance of the initial and follow-up phases.

B. Preparatory Phase: Perform before beginning each feature of work.

1. Review control submittal requirements with personnel directly responsible for the quality control work. As a minimum, the Contractor's Quality Control Supervisor and the foreman responsible for the feature of work shall be in attendance.

2. Review all applicable specification sections and drawings related to the feature of work.

3. Ensure that copies of all referenced standards related to sampling, testing, and execution for the feature of work are available on site.

4. Ensure that provisions have been made for field control testing.

5. Examine the work area to ensure that all preliminary work has been completed.

6. Verify all field dimensions and advise the Contracting Officer of discrepancies with contract documents.

7. Ensure that necessary equipment and materials are at the project site and that they comply with approved shop drawings and submittals.

8. Review the Site Specific Health and Safety Plan. Note the hazards associated with the subject DFW, and discuss safety provisions. Identify any hazards that were overlooked in preparation of the SSHSP. Arrange for necessary safety equipment, controls, or monitoring.

9. Prepare a report on all preparatory phase activities and discussions. Attach report to Contractor's Quality Control Daily Report.

C. Initial Phase:

QUALITY CONTROL 014100-4

Attachment 2

1. As soon as work begins, inspect and test a representative portion of a particular feature of work for quality of workmanship.

2. Review control-testing procedures to ensure compliance with contract requirements.

3. Review use of proper safety materials and procedures.

4. Prepare a report on all initial phase activities and discussions. Attach report to

Contractor's Quality Control Daily Report. Exact location of initial phase shall be indicated for future reference and comparison with follow-up phases.

D. Follow-Up Phase: Inspect and test as work progresses to ensure compliance with contract requirements until completion of work.

E. Additional Preparatory and Initial Phases: Additional preparatory and initial phases may be required on the same feature of work for the following reasons:

1. Quality of on-going work is unacceptable.

2. Changes occur in the applicable quality control staff, on-site production supervision, or work crew.

3. Work on a particular feature of work is resumed after a substantial period of inactivity.

3.3 DOCUMENTATION

A. Maintain Quality Control Daily Reports and Daily Test Report Information Sheets of quality control activities and tests.

B. Quality Control Daily Reports may not be substituted for other written reports required under clauses of the contract, such as Disputes, Differing Site Conditions, or Changes.

C. Maintain itemized documentation of materials that have arrived on-site and provide for review when requested by the Contracting Officer. Review and verification will be required to process payment requests.

D. Record Documents.

E. Defective work/corrective action log shall be maintained daily and copies provided to the Contracting Officer at a minimum weekly, or as requested by the Contracting Officer.

3.4 PERMITS, LICENSES, AND CERTIFICATES

A. For Contracting Officer’s records, submit copies of permits, licenses, certifications, inspection reports, releases, jurisdictional settlements, notices, receipts for fee payments, judgments, correspondence, records, and similar documents, established for compliance with standards and regulations relevant to the on performance of the work.

3.5 AS-BUILT DRAWINGS

A. The Contractor shall maintain a set of the contract drawings depicting as-built conditions. These drawings shall be maintained in a current condition and shall be

QUALITY CONTROL 014100-5

Attachment 2 available for review. All variations from the original contract drawings shall be indicated in red on the drawings. Upon completion of the contract work, as-built drawings shall be submitted to the Contracting Officer.

3.6 ENFORCEMENT

A. The Contractor shall stop work on any item or feature pending satisfactory correction of any deficiency noted by the quality control staff or the Contracting Officer.

3.7 REPAIR AND PROTECTION

A. General: Upon completion of inspection, testing, sample taking and similar services, repair damaged construction and restore substrates and finishes.

B. Protect construction exposed by or for quality-control service activities, and protect repaired construction.

C. Repair and protection is Contractor’s responsibility, regardless of the assignment of responsibility for inspection, testing, or similar services.

3.8 SAMPLING, TESTING, AND CERTIFICATION REQUIREMENTS

A. Sampling, testing, and Certification requirements and frequency for specific items shall be as specified in the drawings and specification. The following table is a summary of the required sampling, testing, and certification for the project - the table is to assist the Contractor, but may not be all inclusive – additional submittals may be required by specific specification section:

B.

TABLE 014100-1

Item

Subsection Certification or Test Required

Frequency

033000 3.14 Concrete - Slump Test, Air Content, Temperature

1 composite per truck load delivered

033000 3.14 Concrete – Compression Test Specimens See Spec.

221100 3.2 P Bent Strap Test Once Daily 221100 3.7 A Hydrostatic Testing See Spec.

221100 3.7 B Pressure and Leakage Test See Spec.

221100 3.8 A Bacteriological Examination After disinfection, before use

221300 3.6 Hydrostatic Testing See Spec.

221300 3.7 A Flushing Pipelines After System Test 221300 3.7 B Leakage Tests Until Passing 221300 3.7 C System Test See Spec.

231126 3.10 Test, inspect, and purge See Spec.

271200 3.5 Field tests and Inspections to verify cable placement and installation See Spec.

QUALITY CONTROL 014100-6

Attachment 2

TABLE 014100-1

Item

Subsection Certification or Test Required

Frequency 312000 3.19 Compaction Test – at Pipe Zone One per 750 Feet of

Trench 312000 3.19 Compaction Test – at Pipe Zone One test – at each road and parking area crossing 312000 3.19 Compaction Test – above Pipe Zone One per 750 Feet of

Trench 312000 3.19 Compaction Test – above Pipe Zone One test every other lift – at each road & parking crossing

312000 3.19 Compaction Test – Exterior Concrete Slabs

One per 400 sf, minimum of 1 per slab

312000 3.19 Compaction Test – Backfill/Fills and Subgrade under Buildings foundation and slab

One test per lift at each building

312000 3.19 Moisture-Density Relationship One test for each soil type encountered

END OF SECTION 014100

QUALITY CONTROL 014100-7

SECTION 015100 - TEMPORARY TRAFFIC CONTROL

PART 1 - GENERAL

1.1 SUMMARY

A. This work consists of furnishing, maintaining, relocating, and removing temporary traffic control and safety devices and services for the control and protection of public traffic near the project site. Prior to beginning construction the Contractor shall submit a traffic control and safety plan to the Contracting Officer for review and approval. As a minimum the traffic control and safety plan shall address signing in and near the project site and at all road and highway junctions that will be used as access to the project site, material sources, water sources and disposal sites as well as any other areas where the Contractor will be performing work under this contract. The traffic control and safety plan shall also address temporary traffic control requirements required by the Nevada Department of Transportation during times that building modules, containers, and other items scheduled for relocation are being transported on State Route 157 between the two project sites.

1.2 MEASUREMENT AND PAYMENT

A. No separate measurement or payment will be made for work specified in this section.

All work will be included in other work items shown in the Schedule of Items.

PART 2 - PRODUCTS

2.1 TRAFFIC CONTROL

A. Traffic control and safety devices (barricades, cones, tubular markers, vertical panels, drums, portable barriers and so forth) designs and configurations shall conform to the MUTCD. When interpreting the requirements in the applicable MUTCD sections, replace the word should with the word shall.

PART 3 - EXECUTION

3.1 GENERAL

A. All signs shall be constructed to comply with the requirements of MUTCD for the construction operations. Install and maintain temporary traffic control and safety devices adjacent to and within the project as shown on the approved traffic control and safety plan and MUTCD. Install and maintain traffic control and safety devices as follows:

TEMPORARY TRAFFIC CONTROL 015100-1

Attachment 2

1. Furnish and install traffic control and safety devices before the start of construction operations.

2. Install only those traffic control and safety devices needed for each stage or phase.

3. Relocate temporary traffic control devices as necessary.

4. Immediately replace any device that is lost, stolen, destroyed, or inoperative.

5. Keep temporary traffic control and safety devices clean.

6. Remove all temporary traffic control devices upon contract completion or when approved.

B. Barricades

1. Perform the work described under MUTCD Part VI. Use type III or IV reflective sheeting. Use wood, metal, or plastic barricades. When type II barricades are used, use barricades that collapse when tipped over.

C. Construction Signs

1. Use type III or IV reflective sheeting. Use wood, metal, fiberglass, or other approved posts.

3.2 PROJECT COORDINATION

A. Coordinate planned moves of building modules, containers, and Propane Tank with Nevada Department of Transportation (NDOT) before beginning each move. Obtain all necessary permits for moving the various modules. Provide all required personnel and equipment (flaggers, pilot vehicles, etc.) required in the permits or by NDOT for each movement.

B. Coordinate planned moves of building modules and containers with Nevada Energy and verify that adequate clearance for modules exists where modules pass under overhead power lines.

END OF SECTION 015100

TEMPORARY TRAFFIC CONTROL 015100-2

SECTION 022310 - BUILDING RELOCATION

PART 1 - GENERAL

1.1 SUMMARY

A. This Section includes removal and relocation of buildings and structures.

B. Related Sections include the following:

1. Section 024100 “Waste Material Disposal.”

2. Section 221102 “Curb Valves and Boxes.”

3. Section 033000 “Cast In Place Concrete”

4. Section 072100 “Thermal Insulation”

5. Section 221100 “Water Distribution Systems”

6. Section 221300 “Sanitary Sewer System”

7. Section 311000 “Clearing and Grubbing”

8. Section 312000 “Earthwork.”

9. Section 321204 “Crushed Aggregate Base or Surface Course.”

1.2 SUBMITTALS

A. Qualification Data: For the following:

1. Building Relocation Firm.

B. Project Schedule for Building Relocations: Indicate detailed sequence of installation of utilities, construction of new pad and utility installation, preparation of buildings for moving, disconnection of utilities, installation and connection at new location, with starting and ending dates for each activity, interruption of utility services.

C. Foundation Design: Submit engineered drawings and calculations for proposed permanent reinforced concrete foundation system for the Bunkhouse at the new Administrative Site to the Contracting Officer for review and approval through the Region 4, Director of Engineering as part of the Base Bid for the relocation of the bunkhouse. Drawings and calculations are to be sealed by a Registered Engineer.

Foundation design shall include design of permanent foundation supports for the ramps/porches of the existing bunkhouse that will be relocated to the new administrative site and re-installed once the bunkhouse has been set up on its new foundation.

D. Submit engineered drawings and calculations for the proposed permanent reinforced concrete foundation system, ramp and stairs for the Visitor/Training Center at the new Administrative Site to the Contracting Officer for review and approval through the Region 4, Director of Engineering. Drawings and calculations are to be sealed by a Registered Engineer. Engineered foundation design for the Visitor/Training Center

BUILDING RELOCATION 022310-1

Attachment 2 shall incorporate the same frost depth protection and crawl space depth requirements as SHOWN ON THE DRAWINGS for the bunkhouse foundation design. An external access to the designed crawl space shall also be incorporated in the foundation design. .

E. Modular Building Connection Details: Submit for review and approval by the Contracting Officer details of all types of intended connections to re-connect the two modular buildings at the new Administrative Site. Said details shall include drawings and calculations where appropriate. Include detailed description of the reconnection and testing of the existing fire sprinkler system for the bunkhouse.

1.3 QUALITY ASSURANCE

A. Pre-relocation Conference: Conduct conference at Project site.

1.4 PROJECT CONDITIONS

A. Buildings to be relocated will be vacated by the government and their use discontinued before start of work to prepare the building for relocation.

1. Contractor shall provide not less than 7 day notice to the Contracting Officer of planned date for preparation of buildings for relocation. The government will vacate the buildings prior to the preparation and relocation.

B. The Government will occupy other buildings on the site and immediately adjacent to the buildings to be relocated. Contractor shall conduct building relocation operation without disruption of government operations at the site.

1. Provide not less than three days’ notice to CO of activities that will affect Government operations. Disruption of utilities shall not be for more than one hour within any one time.

2. Maintain access to existing walkways, exits, and other adjacent occupied or used facilities. Do not close or obstruct walkways, exits, or other occupied or used facilities without written permission from authorities having jurisdiction.

1.5 COORDINATION

A. Arrange demolition and relocation schedule so as not to interfere with the Government’s operations on-site.

B. Contact utility (Power and Telecommunications) companies and arrange to have services to buildings being relocated disconnected at the service drops and at the building main panels.

C. Contact the Liquified Petroleum Gas company that owns/services the 1000 gallon propane tank that provides fuel to the bunkhouse. Arrange for them to empty the tank and to relocate the tank to the new location. The company that owns/services the Bunkhouse propanel tank will be provided by the Contracting Officer upon award.

1.6 MEASUREMENT AND PAYMENT

BUILDING RELOCATION 022310-2

Attachment 2

A. The Pay Item for Relocation of the Bunkhouse will be a Lump Sum pay item.