This single source justification document outlines the requirement for the purchase and installation of a third alarmed Protected Distribution System drop box from Network Integrity Systems to connect the AFIT/EXA facility to AFIA servers. The contractor will install one PDS drop box with fiber optic cable at the AFIT/EXA facility where the network equipment is located to allow compliance with Air Force security requirements. Network Integrity Systems has already installed two compatible PDS systems on Kirtland AFB, and using this contractor will save $70,000 in initial server costs plus $10,000 annually in maintenance and support costs by leveraging their existing 24/7 service contract with AFIA. Previous solicitations for this requirement received no responses or only one response due to a lack of compatible equipment from other vendors. Using another contractor risks incompatibility with the existing system and additional time and costs. There is no indication more of this product will be required in the future.

View the file

Other files for this federal contract opportunity

Other files attached to PDS Drop Box Purchase and Installation, newest first.
File Type Posted
NOTICE OF INTENT TO AWARD SOLE SOURCE.pdf PDF

On GovTribe

Work with this file on GovTribe

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

CONTROLLED UNCLASSIFIED INFORMATION

Single Source Justification {Simplified Acquisition)

Section A: General Contract Information

Is this a Bridge Action as defined in the AF Bridge Action Reduction Plan?

Contracting Activity: -

Project/Program Name: AFIT/EXA PDS Drop Box Ill

Purchase Request / Local ID Number:

Estimated Contract Cost (including Options): -

D Yes

Section B: Description of the Supplies/Services Required

Purchase and installation of a third centrally managed alarmed Protected Distribution System (PDS) drop box. Contractor will install one (1) PDS drop box with appropriate hardware to support the SIPRNet desktop computer in - where the fiber optic patch panel, Interceptor, Stoplight, TACLANE, and network switch reside. Contractor will use on-hand interlocking armored fiber optic cable between the IPS container and the PDS drop location.

Contractor installation will comply with Air Force Systems Security Instruction (AFSSI) 7702 and AFSSI 7703 requirements.

Section C: Justification for Soliciting from a Single Source or Brand Name

Network Integrity Systems has already installed two Protected Distribution Systems on Kirtland AFB that allows AFIT/EXA to connect to AFIA's servers and participate in the vendor's 24/7 service contract with AFIA. This will save $70,000 in up front server costs, plus an additional $10,000 every year (beginning in Year 1) in 24/7 service-related costs.

Section D: Efforts to Obtain Competition

Previous requirements for this system have been solicited via 2GIT with no responses, and then solicited via SAM with only one response. New research has been conducted and revealed that neither 2GIT nor GSA offers what the customer requires.

However, the contractor currently has systems connected to an already existing network and already has the compatible equipment. It is not feasible to go with another contractor to set-up a different system that is not compatible with an already existing system.

Section E: Steps to Preclude Future Single Source or Brand Name Awards

At this time there is no indication that the AFIT will require more of this product. It is without its full operational capability for as long as the College does not have a PDS that satisfies (S) PDAFI 33-214 Volume 1, (S) Emission Security Assessments (U) (formerly Air Force Systems Security Instruction (AFSSI) 701 O) requirements. Any other products and services from any other vendor will require additional time and runs the risk of using a vendor that has no prior successful experience installing a PDS on an Air Force installation. If the requirement does recur in the future, the CO will evaluate current systems and maintenance contracts in place to determine feasibility of other options.

April 2021 CONTROLLED UNCLASSIFIED INFORMATION Page 1 of2