Affdavit_of_Release_and_Guarantee.pdf
PDF 73 KB Posted
- Attached to
- Reconstruct Airport Perimeter Fence Phase 2-PIE
- Solicitation number
- 26-0618-ITB-C
- Issued by
- Pinellas County, Clewiston City, Florida
About this file
This is an Affidavit of Release and Guarantee document related to the St. Pete-Clearwater International Airport's Reconstruct Airport Perimeter Fence Phase 2 project in Florida. The affidavit serves as a formal declaration ensuring that the contractor or party executing the document releases any claims against the project owner and guarantees completion of work according to contract specifications. The document establishes legal accountability and protection for the airport authority by requiring the signatory to affirm that all work will be performed in compliance with project requirements, particularly the installation of 8-foot tall prefabricated non-scalable fencing topped with razor wire and wildlife deterrent skirts to match Phase 1 installations.
The affidavit functions as a binding guarantee mechanism within the contract framework, ensuring that the executing party acknowledges their obligations and waives potential disputes or claims that could arise during or after project completion. This document is a standard contractual requirement for airport security and perimeter fence projects, providing the airport with legal recourse and confirmation that the contractor understands the critical nature of the work related to Air Operations Area safety and security enhancement.
View the file
Other files
Show all 30
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
AFFIDAVIT OF RELEASE AND GUARANTEE
AFFIDAVIT OF RELEASE AND GUARANTEE
STATE OF FLORIDA
COUNTY OF ________
Before me, the undersigned authority, personally appeared ___________________________________________________________ who after being duly sworn, deposes and says:
All charges for labor, materials, supplies, lands, licenses and other expenses arising from
Bid Title: _________________________________________________________________________________________
Bid No: __________ for which a lien or a demand against any payment bond might be filed, have been fully satisfied and paid or will be fully satisfied and paid promptly upon receipt of payment by the Contractor. The Contractor will fully indemnify, defend and save harmless the County from all demands, suits, actions, claims of lien or other charges filed or asserted against the County in connection with matters certified to herein.
On behalf of itself and its subcontractors, suppliers, material men, successors and assigns, the Contractor releases and waives all claims, demands, damages, costs and expenses, against the Board of County Commissioners of Pinellas County, relating in any way to the performance or payment of the above-numbered Agreement, for the period from the date of execution of the Agreement through and including the date of acceptance of Final Payment.
The Contractor is aware of contractual provisions for warranties and guarantees contained in the General Conditions of the above numbered Agreement, and acknowledges that those provisions shall have the same force and effect as if this Affidavit had not been executed, and understands that the County’s remedies are not limited by same but are in addition to any other remedies provided by law.
This Affidavit is given in connection with the Contractors application for Final Payment.
FURTHER AFFIANT SAYETH NAUGHT.
(Affiant)
STATE OF FLORIDA
COUNTY OF __________
The foregoing instrument was acknowledged before me this
By _________________________ who is Personally known to me and/or has produced
______________________________ As identification.
Signature of Person Taking Acknowledgement
Name of Acknowledger Types, Printed or Stamped
| Bid Title: |
| Affiant: |
| As identification: |
| Name of Acknowledger Types Printed or Stamped: |
| Witness: |
| Bid Number: |
| County: |
| Date: |
| Personally known to me: |