Eielson Mixed-Use Slide Deck.pdf
PDF 3 MB Posted
- Solicitation number
- AFCEC26R0009
About this file
This is a presentation document for the Eielson Air Force Base Mixed-Use Virtual Industry Day webinar held on July 22, 2026.
The Department of the Air Force is seeking development proposals through Enhanced Use Leases (EULs) for four sites at Eielson AFB in Alaska: Dyke Range (off-installation, 174.89 acres), Housing (on-installation, approximately 124 acres across six parcels), South Eielson (off-installation, 214.22 acres), and E-Hill (on-installation, 3,474.58 acres). EULs are lease agreements whereby the Air Force monetizes non-excess, underutilized land through private commercial development in exchange for cash payments or in-kind consideration meeting or exceeding fair market value. Development must be self-sustaining without Air Force financial support, market-driven, and compatible with Air Force mission requirements including encroachment management and buffer zones. Proposals are evaluated through a competitive Source Selection Evaluation Board process and must follow a FAR-like competition posted on SAM.gov. Key submission requirements include demonstration of project viability through market demand and feasibility analysis, detailed pro forma financial models with flexible assumptions, evidence of financing availability from debt and equity sources, and clear lease consideration structures. Offerors must account for Alaska-specific constraints including remote location supply chain issues, arctic climate requirements, limited construction seasons (4-5 months), elevated costs reflected in RSMeans location factors, and extreme weather conditions requiring specialized building systems. Proposals are due August 10, 2026, with offerors required to notify the Air Force of intent to submit by July 24, 2026. A site visit is scheduled for July 30, 2026, with RSVP due July 27, 2026. Questions should be submitted through the provided QR code or form link, with responses posted on SAM.gov.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
EIELSON AFB MIXED-USE
VIRTUAL INDUSTRY DAY
Wednesday, July 22, 2026 |1:00 p.m. Central Time (US & Canada) (AKDT- 10:00 a.m.)
Your Success is Our M ission!UNCLASSIFIED
Air Force Installation & Mission Support Center
WELCOME
Ms. Renee Ayala
Chief, Real Estate Development Division
Ground Rules
■ Cameras are optional for presenters; attendees will remain off-camera.
■ All questions must be submitted through the QR Code or the link provided on the final slide of the presentation. Please fill out all the requested contact information, question responses will be posted on sam.gov.
■ Should you have technical issues with the link provided you may submit your questions by email at: Alaska.eul@specprosvcs.com
■ Chat will remain muted to avoid disruptions.
■ The session is being recorded for internal use and documentation.
■ A copy of today's slides can be provided upon request using the Q&A or link.
Agenda
Time (CDT) Agenda Item Briefer / Panelists
1:00 PM Webinar Check-in Begins SpecPro (Contractor)
1:05 PM Opening Remarks Ms. Renee Ayala
Chief, Real Estate Development Division
1:10 PM Honorary Speaker Mr. Robert Moriarty
Deputy Assistant Secretary of the Air Force for Installations
1:20 PM DAF EUL Program Overview Mr. Dave Mairs
Branch Chief (Acting), Enhanced Use Leases
1:35 PM Eielson AFB Site Overview Captain Richard Wilkens
Deputy, Installation Management Flight
1:45 PM Request for Lease Proposal - Key Focus Areas
Mr. Ben Helm
Program Advisor (JLL)
2:00 PM Closing Remarks / End of Industry Forum
Mr. Dave Mairs
Branch Chief (Acting), Enhanced Use Lease
Honorary Speaker
Mr. Robert Moriarty Deputy Assistant Secretary of the Air
Force for Installations
DAF EUL PROGRAM OVERVIEW
Mr. Dave Mairs Moderator & Branch Chief (Acting), Enhanced
Use Leases
Your Success is Our M ission!
UNCLASSIFIED
DAF EUL Program – What to Know!
An EUL is a lease agreement between the Air Force (AF) and a third-party for the development of non-excess, underutilized land located at an installation under the direct control of the Secretary of the Air Force.
EULs Are
EUL development proposals are self-sustaining;
developer proposal cannot rely on the AF for financial viability or AF subsidization
Self-sustaining
Development projects are market driven and at highest and best use; developer is responsible for development proposal not the AF
Market Driven
AF receives cash payments and/or IKC for right to develop leased property; value received by the AF is dependent on the property valuation
Beneficial to the AF
Lessee is responsible for project utilities, infrastructure and services and state and local government taxes
Developer Operated
DAF EUL Program – What to Know!
(Cont.)
EUL Monetize Non-excess AF Real Estate Where and When it Makes Sense
Maximize benefit/return to AF Purse projects compatible with AF mission Long-term viable projects (self-sustaining and financially independent) Identify and develop real property value-based transactions (VBTs) Provide long-term oversight to ensure compliance with statutory requirements and lease documents
Requirements
• Property must be non-excess, underutilized land as defined by 40 USC § 102
• DAF retains ownership of the real estate to meet future missions
• Development must be compatible with AF encroachment management, mission sustainment, buffer zones, AICUZ, etc.
• Commercial development must support community development needs
• Must be competed following a FAR-like process with Requests for Information or
Lease Proposals posted at SAM.gov; proposals evaluated by SSEB
General
• DAF “Consideration ($$)” must meet at least or exceed Fair Market Value
• Consideration is defined as cash payments or in-kind consideration or a combination of cash payments and IKC to the installation
• Payment and schedule to be determined through lease negotiations and documented in the final lease
Consideration
UNCLASSIFIED 11
Source Selection
■ Multi-functional Source Selection Evaluation Board (SSEB) led by the AFCEC Program Manager evaluates and rates proposals; SAF/IEI is the SSEB approval authority.
■ One of two outcomes:
■ Selection of a successful offeror to engage in lease negotiations
■ None of the developer proposals are selected; Government (DAF) may decide to
■ Re-advertise the RFLP (if in the best interest of the DAF)
■ Cancel the RFLP and terminate the project
■ AF negotiation objectives
■ Improve / optimize Offeror’s submitted proposal, value, and terms and conditions
■ Successfully execute a Site Development Lease between the Offeror and DAF
EUL Program Basics – Process Milestones
KEY MILESTONES
Submit Phase 0 Checklist
Site Visit Submit to IC for Approval
Congressional Notification to Release RFLP
RFLP Submittal & Evaluation Negotiations
Congressional Notification to Sign Lease
Lease Execution
Project Design, Construction, & Portfolio Management
LEASE TERM16 – 18 MONTHS FROM PROJECT INITIATION TO LEASE EXECUTION
Project Charter
EBS / NEPA / OSD Cert
Strategic Basing & Encroachment Approval
Draft Request for Lease Proposals (RFLP)
Final RFLP to developer
Developer Responds to RFLP
Source Selection Evaluation & Approval
NEPA
Negotiation Strategy
Draft Term Sheet
Finalize & Approve Term Sheet
Complete NEPA
Lease Documents
Lease Signing
Project Design & Construction
Oversight (Lease Compliance)
Reporting & Metrics
Appraisal
Phase 0 Package to Investment Committee
(IC)
IC Briefing / Approval
PHASES & DELIVERABLES
PHASE 0
Project Initiation
PHASE I
Project
Definition
PHASE II
EUL Source Selection
PHASE III
Negotiations & Closing
PHASE IV & V
Post-closing Management
Success Stories
Commercial EUL projects Hotels – Eglin & Wright-Patterson Business/ Aviation Parks – Kirtland & Grand Forks Sports Complex – Seymour Johnson Solar photovoltaic array projects – multiple installations Waste Reclamation Facilities – Eglin & Nellis Mixed-use commercial development – multiple installations In-kind Consideration (to AF)
Fitness Center - Nellis AFB Security Gate & Security Forces Building - Hill Fire Fighting Training Facility - Eglin Sustainment, repair and maintenance (SRM) – multiple installations Controlled Space – Wright-Patterson
USAFA – Visitor Center
Tinker – Natural Gas Peaking Plant
Eglin - Emerald Breeze Resort
Edwards – Solar Array
Nellis AFB Fitness Center
Summary
Purpose is to monetize non-excess, underutilized AF real estate through the lease of Government-owned, AF-managed real estate to a private developer for commercial development in exchange for cash rent and / or IKC to the AF.
Statutory Authority for Enhanced Use Leases: 10 United States Code Section 2667
Development is market driven and support the needs of the local community, county or state. Projects must be self-sustaining and not rely on the AF. EULs are not a substitute for the military construction program.
DAF seeks cash lease payments; value to be determined during lease negotiations and documented in the lease.
EIELSON - SITE OVERVIEW
Capt. Richard Wilkens Deputy, Installation Management Flight
Ready – Resilient – Lethal
UNCLASSIFIED
Action Status % Complete Requirement/Next Step
Proof of USAF Control 80% Working 1354 Transfer from Army; (PLO 1521, PLO 1541, PLO 1688 (Dept of AF), 25_44LD513 Flood Control (USACE))
DAF Form 813 10% In Review, ETA 28 May
Environmental Baseline Survey 0% ~$200K, recommend determining site first
Biological Survey 0% ~$100K, recommend determining site first
Wetland Survey 0% ~$100K, recommend determining site first
Cultural Survey 0% ~$100K, recommend determining site first
NEPA Process 0% ~$250K, recommend determining site first
Confirmation of Legislative Jurisdiction 40% Coordinating with USACE for specific parcels
Solar Glare Hazard Analysis 10% Coordinating w/ 354OSS & AFCEC for How
Mission Compatibility 30% Being staffed currently
Memorandum of Lease Authority 10% Working Draft/Coordinating w/ SAF/GCN-SA
Concurrence w/ AFCEC, AFSVC, AAFES 10% Coordinating with Dave Mairs
Appraisal Ordered 0% ~$20K, recommend determining site first
Compatible Use Plan 100% Complete
Space Optimization Study 100% Complete
AICUZ Compatibility 100% Complete
Dyke Range (Off-Installation)
UNCLASSIFIED
Action Status % Complete Requirement/Next Step
Proof of USAF Control 100% PLO 577, PLO684, PLO 794, PLO1203
DAF Form 813 10% In Review, ETA 28 May
Environmental Baseline Survey 0% ~$200K, recommend determining site first
Biological Survey NA Not Required
Wetland Survey 0% ~$20K, recommend determining site first
Cultural Survey NA Not required for previously disturbed lands
NEPA Process 0% ~$200K, recommend determining site first
Confirmation of Legislative Jurisdiction 40% Coordinating with USACE for specific parcels
Solar Glare Hazard Analysis 10% Coordinating w/ 354OSS & AFCEC for How
Mission Compatibility 30% Being staffed currently
Memorandum of Lease Authority 10% Working Draft/Coordinating w/ SAF/GCN-SA
Concurrence w/ AFCEC, AFSVC, AAFES 10% Coordinating with Dave Mairs
Appraisal Ordered 0% ~$20K, recommend determining site first
Compatible Use Plan 100% Complete
Space Optimization Study 100% Complete
AICUZ Compatibility 100% Complete
Housing (On-Installation)
UNCLASSIFIED
Action Status % Complete Requirement/Next Step
Proof of USAF Control 100% PLO 577, PLO684, PLO 794, PLO1203
DAF Form 813 10% In Review, ETA 28 May
Environmental Baseline Survey 0% ~$200K, recommend determining site first
Biological Survey 0% ~$100K, recommend determining site first
Wetland Survey 0% ~$100K, recommend determining site first
Cultural Survey 0% ~$100K, recommend determining site first
NEPA Process 0% ~$250K, recommend determining site first
Confirmation of Legislative Jurisdiction 40% Coordinating with USACE for specific parcels
Solar Glare Hazard Analysis 10% Coordinating w/ 354OSS & AFCEC for How
Mission Compatibility 30% Being staffed currently
Memorandum of Lease Authority 10% Working Draft/Coordinating w/ SAF/GCN-SA
Concurrence w/ AFCEC, AFSVC, AAFES 10% Coordinating with Dave Mairs
Appraisal Ordered 0% ~$20K, recommend determining site first
Compatible Use Plan 100% Complete
Space Optimization Study 100% Complete
AICUZ Compatibility 100% Complete
South Eielson (Off-Installation)
UNCLASSIFIED
Action Status % Complete Requirement/Next Step
Proof of USAF Control 100% PLO 577, PLO684, PLO 794, PLO1203
DAF Form 813 10% In Review, ETA 28 May
Environmental Baseline Survey 0% ~$200K, recommend determining site first
Biological Survey 0% ~$100K, recommend determining site first
Wetland Survey 0% ~$100K, recommend determining site first
Cultural Survey 0% ~$100K, recommend determining site first
NEPA Process 0% ~$250K, recommend determining site first
Confirmation of Legislative Jurisdiction 40% Coordinating with USACE for specific parcels
Solar Glare Hazard Analysis 10% Coordinating w/ 354OSS & AFCEC for How
Mission Compatibility 30% Being staffed currently
Memorandum of Lease Authority 10% Working Draft/Coordinating w/ SAF/GCN-SA
Concurrence w/ AFCEC, AFSVC, AAFES 10% Coordinating with Dave Mairs
Appraisal Ordered 0% ~$20K, recommend determining site first
Compatible Use Plan 100% Complete
Space Optimization Study 100% Complete
AICUZ Compatibility 100% Complete
E-Hill (On-Installation)
EIELSON - SITE VISIT
Capt. Richard Wilkens Richard.Wilkens@us.af.mil
Site Visit: 30 July 2026 RSVP Due: 27 July 2026
REQUEST FOR LEASE PROPOSAL
KEY FOCUS AREAS
Mr. Ben Helm Program Advisor (JLL)
Provide What is Asked
Read RFLP closely for specific requirements
Include responses to all requirements
Don’t make the Air Force guess at your intentions
If specific information is not available, explain why
Proposals with missing information will be evaluated less favorably and may be deemed non-compliant and not considered for award
This is an EUL not an MHPI transaction
See Section 4.1.m of the RFLP for specific restrictions
This is an EUL not an MHPI transaction
Provide facts, data, and analysis to describe the current market demand for your proposed project
Section 4.5: “… explicitly document the market demand and market feasibility analysis for the proposed Project; explicitly demonstrating that the proposed Project is viable without any direct Air Force financial support or financial guarantee…”
Not looking for pilot projects or projects reliant on AF funding—need commercial viability
Address the viability of the parcel(s) you are proposing What attributes make them attractive (location, proximity to utilities, size, etc.)
Any concern of an unknown factor, that if confirmed, would make the project unfeasible
Be transparent and show you have a clear understanding of the market and the site
Demonstrate Project Viability
Alaska Considerations
Remote Alaska location creates supply chain constraints, extended procurement lead times, and elevated logistical costs
Arctic climate requires specialized building systems, resilient infrastructure, and cold-weather construction practices
Short 4-5 month construction season necessitates phased, multi-year development and extended delivery timelines
Fairbanks' high-cost environment is reflected by an elevated RSMeans Location Factor with above-market wages, premium utility costs, and elevated construction expenditures
Extreme a conditions (temperatures below -40°F) drive enhanced building envelope, mechanical, and foundation requirements
Lease Consideration
10 USC 2667 requires the Air Force receive at least fair market value (FMV)
Consideration will be Cash Only for this project
Show both timing and size of payments to the Air Force
Payments can be base rent and/or some form of participation rent
Air Force will discount any participation rent proposed based on location in the waterfall and the payment calculation
Speed is a priority, expectation that ground rent is paid during the development period and that work begins immediately upon lease signing
Pro Forma
Don’t Leave the Air Force Guessing, cash flows should be clear in the pro forma
RFLP has specific instructions regarding the proforma in Section 4.10
AF will be evaluating Pro-Forma assumptions for reasonableness
Do not hardcode entries, Air Force needs to be able to change numbers and see results
Sources of Funds
Section 4.12.b: Provide evidence of ability to secure sufficient funds or financing Provide letters of support or interest for debt Provide evidence that equity exits and will be forthcoming Assume no Air Force financial assistance of any kind
Can you provide examples of past performance securing funds or financing for projects of similar scope
Specific information regarding the willingness of capital providers and availability of funds will help strengthen your proposal
Submission
Proposals due 10 Aug
Per Section 4.3, let the Air Force know if you intend to submit by 24 Jul
Air Force will provide instructions to upload responses to a secure site
Questions https://forms.osi.apps.mil/Pages/ResponsePage.aspx?id=jbExg4ct70ijX6yIGOv5tMObGamZdYBLniCjApYZa SlUMzZaMTBQM0pLRjJZVkNPUEhPMkZUOUs3NC4u
QR Code:
Link:
https://forms.osi.apps.mil/Pages/ResponsePage.aspx?id=jbExg4ct70ijX6yIGOv5tMObGamZdYBLniCjApYZaSlUMzZaMTBQM0pLRjJZVkNPUEhPMkZUOUs3NC4u https://forms.osi.apps.mil/Pages/ResponsePage.aspx?id=jbExg4ct70ijX6yIGOv5tMObGamZdYBLniCjApYZaSlUMzZaMTBQM0pLRjJZVkNPUEhPMkZUOUs3NC4u
THANK
YOU
| Slide Number 1 |
| Slide Number 2 |
| Slide Number 3 |
| Ground Rules |
| Agenda |
| Honorary Speaker |
| DAF EUL PROGRAM OVERVIEW |
| DAF EUL Program – What to Know! |
| DAF EUL Program – What to Know!�(Cont.) |
| Requirements |
| Source Selection |
| EUL Program Basics – �Process Milestones |
| Success Stories |
| Summary |
| EIELSON - SITE OVERVIEW |
| Slide Number 16 |
| Dyke Range (Off-Installation) |
| Housing (On-Installation) |
| South Eielson (Off-Installation) |
| E-Hill (On-Installation) |
| EIELSON - SITE VISIT |
| REQUEST FOR LEASE PROPOSAL �KEY FOCUS AREAS |
| Provide What is Asked |
| This is an EUL not an MHPI transaction |
| Demonstrate Project Viability |
| Alaska Considerations |
| Lease Consideration |
| Pro Forma |
| Sources of Funds |
| Submission |
| Questions |
| Slide Number 32 |