This is an Advertisement for Bids issued by the Genesee Intermediate School District in Flint, Michigan for general construction services related to roof replacement at the Carman Park Building. Sealed bids will be received until June 12, 2019 at 2:00 p.m. EST at the Erwin L. Davis Education Center, located at 2413 West Maple Avenue, Flint, Michigan. Bidding documents will be available for examination beginning May 21, 2019 from the Architect, TMP Architecture, Inc., located at 1191 West Square Lake Road, Bloomfield Hills, Michigan. A Pre-Bid Meeting is scheduled for May 23, 2019 at 1:00 p.m. at the Carman Park Building (3375 Van Campen Street, Flint), with attendance highly recommended. Qualified bidders may obtain one set of drawings and specifications from the Architect or via email, and must return all bidding documents within ten days after bid opening in clean, usable condition.

Each bid submission must include a sworn and notarized statement disclosing any familial relationships between the bidder and school board members, superintendents, or chief executives, as well as a sworn and notarized Iran Economic Sanctions Act Compliance form; bids lacking both statements will not be accepted. Bid Proposals must be submitted on forms furnished by the Architect and accompanied by a satisfactory Bid Bond or Certified Check equal to five percent of the Base Bid Sum. Successful bidders will be required to furnish satisfactory Performance Bond and Labor and Material Payment Bond in accordance with the Instructions to Bidders. Bidders agree not to withdraw their proposals for sixty days after the bid receipt date. The Owner reserves the right to reject any or all bid proposals in whole or in part, or to waive any informalities.

View the file

Other files

File Type Posted
Addendum 2 - Carman Park Roofing Project.pdf PDF
Carman Park Roofing Project - Addendum 1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

SECTION 001113 ADVERTISEMENT FOR BIDS

ADVERTISEMENT FOR BIDS

The Architect will receive sealed bids for:

GENERAL CONSTRUCTION OF:

THE CARMAN PARK BUILDING ROOF REPLACEMENT

Bid Proposals will be received until the time and the place, as follows, where and when the opening of bid proposals will be conducted by the Owner in public:

Date: June 12, 2019 Time: 2:00 p.m. EST Place: The Erwin L. Davis Education Center Genesee Intermediate School District 2413 West Maple Avenue Flint, MI 48507-3493

Attn: Cynthia McCain, Assistant Superintendent for Business Services

Bidding Documents will be available for examination and distribution on or after May 21, 2019.

Examination may be made at the Office of the Architect, TMP ARCHITECTURE, INC., 1191 West Square Lake Road, Bloomfield Hills, Michigan 48302.

Qualified Bidders may obtain bidding documents from the Office of the Architect or via email, consisting of one (1) set of Drawings and Specifications.

Return Bidding Documents to the Architect within ten (10) days after opening receipt of proposals. Documents are to be complete, in clean and usable condition and free of marks or other defacement.

A sworn and notarized statement disclosing any familial relationship existing between the bidder and any member of the school board, school superintendents, or chief executive must accompany each bid. A sworn and notarized Iran Economic Sanctions Act Compliance form must be included as well. A board shall not accept a bid that does not include both of these statements, which are included on the proposal execution form.

A Pre-Bid Meeting will be held at the job site on: May 23, 2019, (1pm – start at the Carman Park Building - 3375 Van Campen St, Flint). Attendance is highly recommended.

Bid Proposals shall be on forms furnished by the Architect, accompanied by a satisfactory Bid Bond or Certified Check for five percent (5%) of the Base Bid Sum maximum possible proposal amount.

Bidder shall agree not to withdraw Bid Proposal for a period of sixty (60) days after date for receipt of bids.

Accepted Bidder shall be required to furnish satisfactory Performance Bond and Labor and Material Payment Bond in accordance with the Instructions to Bidders.

The right to reject any or all Bid Proposals, either in whole or in part, or to waive any informalities therein is reserved by the Owner.

**END OF SECTION**

05/17/19 ISSUED FOR BIDS TMP19025