Addendum 2 - Carman Park Roofing Project.pdf

PDF 57 KB Posted

Attached to
Carman Park Roof Replacement
Solicitation number
RFP GIS 190000002312 3
Issued by
Genesee County, Fife Lake Village, Michigan

About this file

This is Addendum No. 2 to the bidding documents for the G.I.S.D. (Grapevine-Colleyville Independent School District) Carman Park Building Roof Replacement project, prepared by TMP Architecture on May 30, 2019. The addendum modifies the existing contract documents by adding a clarification to Roof Plan Note #8 on Drawing No. AC1.2. The modification specifies that the Owner will be responsible for the re-alignment and re-supporting of all associated piping and conduit as part of the roof replacement work. This addendum contains no new drawings or attachments and represents the second modification issued to the original bidding documents for this roofing project.

No pricing information, set-asides, funding sources, or additional contract terms are addressed in this addendum. The document serves solely as an architectural clarification regarding the division of responsibilities between the contractor and the Owner regarding piping and conduit work associated with the roof replacement project.

View the file

Other files

File Type Posted
ADVERTISEMENT FOR BID-Carman Park Roof Replacement.docx DOCX document
Carman Park Roofing Project - Addendum 1.docx DOCX document

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TMP

Architecture

DATE: May 30, 2019

PROJECT: G.I.S.D. - Carman Park Building Roof Replacement

TMP PROJECT NO.: 19025

ADDENDUM NO.: Two (2)

The Bidding Documents are modified, supplemented or augmented as follows and this Addendum is hereby made a part of the proposed Contract Documents.

There are no Drawings or attachments issued with this Addendum.

ITEM NO. ARCHITECTURAL DRAW ING CHANGES

AD-1 Refer to Drawing No. AC1.2 (not reissued):

A. Added the following to Roof Plan Note #8:

“Re-alignment and re-supporting of associated piping and conduit will be performed by the Owner.”

**END OF ADDENDUM NO. 2**

o:\2019\19025\specs\addenda\add02\19025_190530_add02.docx

File details come from the government source that posted it. Updated .