AddenNo2_DCF ITB 2425 027-2.pdf

PDF 196 KB Posted

Attached to
Northeast Florida State Hospital (NEFSH) Life Safety Project 33020500
Solicitation number
ITB-10460
Issued by
Leon County, Florida

About this file

This is Addendum No. 02 for DCF ITB 2425 027-2, issued by the Florida Department of Children and Families Office of General Services for the NEFSH Life Safety Project #33020500, which involves Civil Site Building Fire Sprinkler Water Line, Fire Riser Room and Mechanical Exhaust Work. The response due date is November 21, 2024, and the addendum was issued on November 6, 2024. The addendum addresses a question from Williams & Rowe Company, Inc. regarding mechanical exhaust fan work and duct work in Buildings 12 and 13.

The Department's response clarifies the work process, stating that one wing on one floor will be unoccupied and closed for Mechanical Work at a time. Once work is completed in that area, the Department will reoccupy it and make another wing available on that floor or another floor for continued Mechanical Work. This process will continue until all Mechanical Work is completed, ensuring minimal disruption to facility operations while maintaining project progress.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum No. 02

DCF ITB 2425 027-2

NEFSH Life Safety Project Office of General Services

Solicitation Number: DCF ITB 2425 027-2

Solicitation Title: NEFSH Life Safety Project #33020500 | Civil Site Building Fire Sprinkler Water Line, Fire Riser Room and Mechanical Exhaust Work

Response(s) Due Date: November 21, 2024

Addendum Number: 02

Addendum Date: November 6, 2024

FAILURE TO FILE A PROTEST WITHIN THE TIME PRESCRIBED IN SECTION 120.57(3), FLORIDA STATUTES, OR FAILURE TO POST THE BOND OR OTHER SECURITY REQUIRED BY LAW WITHIN THE

TIME ALLOWED FOR FILING A BOND SHALL CONSTITUTE A WAIVER OF PROCEEDINGS UNDER

CHAPTER 120, FLORIDA STATUTES.

DCF ITB 2425 027-2 is hereby amended as follows, all other terms and conditions of the solicitation remain in effect. All additions are highlighted in yellow, and words stricken are deletions:

Question

Vendor Name

Solicitation Section

Question Department Response

Williams & Rowe

Company, Inc.

General

In Building 12 and 13, the mechanical scope exhaust fan work and duct can we shut these restrooms down while we are working on them?

The Department will have one wing on one floor unoccupied and closed for the Mechanical Work. Once Work in that area is complete, the Department will reoccupy and make another wing available on that floor, or another floor, for the Mechanical Work to continue. This process will repeat until the all the Mechanical Work is completed.