About this file
This document is Addendum No. 3 issued by the Commonwealth of Kentucky Department for Facilities and Support Services, Division of Engineering and Contract Administration, for Invitation to Bid (RFB-158-26) regarding a Room Upgrade-Reconfiguration project at Cumberland Falls State Resort in Corbin, Kentucky. The project involves reconfiguring 51 existing guest rooms into 39 rooms with modifications spanning both the 1950s wing and historic wing of the Lodge Building, including structural work, mechanical/electrical/plumbing upgrades, HVAC system replacement with new PTACs, complete bathroom plumbing services, new electrical lighting and data systems, sprinkler system rework, and exterior work including fire escape removal and siding repairs. The bid was due January 8, 2026, at 1:30 PM Eastern Time, with a project cost estimate of $6,123,915. The pre-bid meeting was held on December 16, 2025, with the final addendum deadline set for December 30, 2025, at noon. The last day for submitting questions was December 29, 2025, at 12:00 noon ET. Site visits must be arranged in advance by contacting the Park Manager or Park Operations. Notice to Proceed is anticipated 30 days after bid submission, with work likely beginning in early February 2026.
The contract specifies a 300-day completion timeframe with final completion in 30 days thereafter. Liquidated damages are assessed at $920 per day until Substantial Completion and $640 per day until Final Completion. The project is not subject to prevailing wage regulations. Bidders may propose equal or substitutable materials and products subject to approval by the purchasing officer in consultation with the architect or the director of DECA. All bids must be submitted through the Commonwealth's eComm e-procurement system, with bid bonds required for responsiveness. Parking and staging areas will be available on-site in the Lodge parking lot, as the Lodge will be completely closed to visitors during construction. Questions raised during the pre-bid meeting regarding fire watch requirements when sprinkler and alarm systems are down, potential asbestos presence, roof warranty, and general contractor responsibility for new roof penetrations will be addressed in a forthcoming addendum.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMMONWEALTH OF KENTUCKY
DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES
DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION
INVITATION TO BID NO: RFB-158-26
FOR: Room Upgrade-Reconfiguration Cumberland Falls State Resort Department of Parks Corbin, Kentucky
DATE: December 19, 2025
RFB-785-2600000274
ADDENDUM NO. Three (3)
RFB-785-2600000274
BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING
UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.
Item 1: Refer to attached addendum for all additions, deletions, and/or changes to specifications and/or drawings.
END OF ADDENDUM
Invitation to Bid No. RFB-158-26 For: Room Upgrade-Reconfiguration Cumberland Falls State Resort Department of Parks
Susan Ward, Statewide Procurement Analyst II Division of Engineering and Contract Administration
KENTUCKY STATE PARKS
CUMBERLAND FALLS ROOM RECONFIGURATION
INVITATION TO BID: RFB-158-26
ADDENDUM NO. 3 ADD 03 - 1
JOSEPH & JOSEPH ARCHITECTS
550 FOURTH AVENUE
LOUISVILLE, KY 40202
RECEIPT OF THE FOLLOWING ADDENDUM MUST BE ACKNOWLEDGED ON THE BID FORM.
Cumberland Falls Room Reconfiguration
Kentucky State Parks
ADDENDUM NO. 3
December 19, 2025
This addendum shall be considered part of the Contract Documents for the above-mentioned project as though it had been issued at the same time and shall be incorporated integrally therewithin. Where provisions of the following supplementary date differ front those in the original Contract Documents, this Addendum shall govern and take precedence.
Bidders are hereby notified that they shall make any necessary changes in their estimates on account of this addendum. It will be construed that each Bidder’s proposal is submitted with full knowledge of all modifications and supplemental data specified here within.
General
Item 1 Attached are minutes from Pre-Bid Meeting held on December 16, 2025.
END OF ADDENDUM NO. 3
Meeting notes represent to the best abilities the observations made, decisions reached and actionable items. Please respond in writing within 5 working days with additions, clarifications or differing opinions.
Meeting Notes
Project: Ky Parks Cumberland Falls Room Reconfiguration Date: December 16, 2025
Location: Cumberland Falls Lodge Commission #: A8884
IN ATTENDANCE
Roger White, Avery Roberts, Maggy Kniebel, David Bradley, Ed Kruger (see attached sign-in sheet)
NOTES
1. After introductions, Avery gave an overview of the Bid Procedures. Highlights include the following:
a. Project Cost Estimate is $6,123,915
b. Bid Date is January 8, 2026 at 1:30 PM ET
c. Last Day for Questions: December 29, 2025, at 12:00 noon ET. All questions to be emailed to Ed Kruger at Joseph & Joseph Architects (e.kruger@josephandjoseph.net)
d. Final Addendum to be uploaded to eComm by noon on December 30, 2025.
e. No changes are binding unless they are in written form by Addendum.
f. Avery went through many of the standard bid procedures, emphasizing that Bid Bonds need to be signed by the Contractor for Bid to be considered responsive.
g. Time for completion is 300 days, with final completion in 30 days. Liquidated damages are $920/day until Substantial Completion and $640/day until Final Completion is reached.
h. Substitutions: The Commonwealth has an “or equal” clause in its conditions, as stated below:
Unless otherwise indicated in the bidding documents, the materials, products and equipment described or referenced by manufacturers’ or vendors’ names, trade names and catalog numbers are intended to establish a standard of required function, dimension, appearance and quality. Unless otherwise stated, equal items may be furnished or used if approved by the purchasing officer in consultation with the architect or the director of DECA.
i. All bids must be submitted through the Commonwealth’s eprocurement system (eComm).
Companies must be registered well in advance of submitting the bid. All documents shall be transmitted through eComm.
2. Ed gave an overview of the project scope, Highlights include:
a. Minimal exterior work, except for removal of fire escape, infilling PTAC openings where abandoned, siding repairs, painting of siding, cleaning stone and concrete in some areas and removal of conduit feeds to the PTACs.
b. Guestrooms are being reconfigured; result will be 39 rooms in lieu of the 51 rooms today. In the 1950’s wing, groups of 3 rooms are being reconfigured to become 2 with bathrooms and mailto:e.kruger@josephandjoseph.net closets located in former center room. In the historic wing, modifications of walls and structure are more extensive. In most areas, demo is back to the stud walls.
c. Structural work includes infill of floor openings in some areas, new openings in existing CMU and wood-framed walls, and restructuring of the floors within the historic wing.
d. M/E/P scope includes:
HVAC: new PTACS and exhaust system in all guestrooms
Plumbing: completely new services to bathrooms with new fixtures
Electrical: new lighting, power and data to all guestrooms and public corridors
Sprinkler: rework existing system with new concealed piping to all guestrooms and corridor spaces
e. Almost all of the work is limited to the guestrooms and public corridor spaces in the Lodge Building. Exceptions include work above the ceilings in the dining room, kitchen and mechanical room for plumbing and electrical services to guestrooms above, new work in mechanical rooms, and work in the attic associated with the exhaust system
3. Timeframe: In response to a question about when Notice to Proceed might be given, we anticipate that it will take 30 days after bids are due for all paperwork to be completed. Work will likely begin in early February.
4. The project is not subject to Prevailing Wage regulations.
5. Parking & Staging: Parking will be available on site in the area of the Lodge, since the Lodge will be completely closed to Visitors during the Construction period. Staging for job and storage trailers can be in the parking lot closest to the lodge rooms.
6. Those that want to visit the site during the bid period need to contact Maggy Kniebel (Park Manager) or David Bradley (Park Operations) to arrange a time. Contractors should not show up without an appointment.
7. Several questions were raised that will be answered in an Addendum:
a. Possible need for fire watch when sprinkler and alarm systems are down?
b. Do we know if asbestos might be present?
c. Is there a warranty on the roof? Is the GC responsible for new penetrations?
ATTACHMENTS
Sign-In Sheet