This is Addendum Three to an Invitation to Bid (RFB-218-23) issued by the Commonwealth of Kentucky Department for Facilities and Support Services, Division of Engineering and Contract Administration, for the Bobby Reid Drainage AML (Abandoned Mine Land) Reclamation Project in Johnson County, Kentucky. The addendum, dated April 12, 2023, announces critical changes to the original bid specifications and timeline. The revised official bid date has been moved to April 24, 2023, at 10:30 A.M. Eastern Time. The project scope encompasses site preparation, drainage infrastructure installation, erosion control, and landscape reclamation work across approximately 6 acres, including the installation of various pipe sizes (18" to 36" diameter HDPE), concrete structures such as drop boxes and headwalls, reinforcing steel work, and final seeding and mulching. The engineer's estimate includes 32 line items with quantities ranging from 1.0 lump sum for mobilization to 2,820 linear feet of subdrain installation and 43,300 pounds of reinforcing steel.
The addendum identifies three allowances totaling $105,000 that must be included in the contract amount: Utility Relocation/Replacement ($50,000), Landscape Allowance ($15,000), and Structure Removal/Replacement ($40,000). These allowances cover all materials, delivery, installation labor, tools, and equipment necessary to complete the specified work, with actual costs to be reconciled through change order upon completion. Bidders must reference a separate addendum to be distributed by Lynn Imaging for additional specifications and drawing changes, and the Authentication of Bid and Statement of Non-Collusion and Non-Conflict of Interest page must be properly executed for the bid to be valid. The contractor's overhead, profit, insurance, bonds, and administrative costs are incorporated within the prescribed markup permitted under Article 14 of the General Conditions and are not to be included separately in the allowance amounts.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMMONWEALTH OF KENTUCKY
DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES
DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION
INVITATION TO BID NO: RFB-218-23
FOR: Bobby Reid Drainage
AML Project Johnson County, Kentucky
DATE: April 12, 2023
RFB-785-2300000608
ADDENDUM NO. Three (3)
BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING
UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.
Item 1: Refer to addendum to be distributed by Lynn Imaging for all additions, deletions, and/or changes to specifications and/or drawings.
Item 2: Revised Engineer Estimate sheet
Item 3: Official Bid Date have changed to April 24, 2023 @ 10:30 A.M. Eastern Time
END OF ADDENDUM
Invitation to Bid No. RFB-218-23 For: Bobby Reid Drainage
AML Project Johnson County, Kentucky
Susan Ward, Statewide Procurement Analyst II Division of Engineering and Contract Administration
22028AMLBAML BOBBY REID AML RECLAMATION PROJECT
JOHNSON COUNTY, KENTUCKY
ENGINEER'S ESTIMATE
NO. ITEM QUANTITY UNIT
1 MOBILIZATION 1.0 L.S.
2 *UTILITY RELOCATION/REPLACEMENT 50,000.0 A.C.U.
3 *LANDSCAPE ALLOWANCE 15,000.0 A.C.U.
4 *STRUCTURE REMOVAL/REPLACEMENT 40,000.0 A.C.U.
5 SITE PREPARATION 6.0 ACRE
6 SITE PREPARATION- WASTE AREAS 1.0 ACRE
7 60 KSI REINFORCING STEEL 43,300.0 LBS
8 CONCRETE- FORMED & FINISHED 860.0 CY
9 FILTER FABRIC 280.0 SY
10 NO. 57 STONE BACKFILL 50.0 TON
11 SILT BARRIER - BALES & FENCE 400.0 LF
12 HOE RAM 40.0 HOUR
13 EROSION CONTROL BLANKET- ECB 360.0 SY
14 CLASS II / III 275.0 TON
15 NON-VEHICUAR GRATE AND ANCHOR (FOR RECTANGULAR CONCRETE DITCH) 1,750.0 LF
16 VEHICULAR GRATE AND ANCHOR (FOR RECTANGULAR CONCRETE DITCH) 460.0 LF
17 SUBDRAIN 2,820.0 LF
18 36" DIA. HDPE PIPE- STANDARD 1,740.0 LF
19 18" DIA. HDPE PIPE- STANDARD 100.0 LF
20 24" DIA. HDPE PIPE- STANDARD 540.0 LF
21 DROP BOX- CONCRETE 15.0 EACH
22 CONCRETE HEADWALL- MULTI-BARREL 3.0 EACH
23 CULVERT DEBRIS BARRIER 3.0 EACH
24 POLYEURTEHANE FOAM 10.0 CY
25 PORTAL CLOSURE 4.0 EACH
26 SEEDBED PREPARATION 6.0 ACRE
27 AGRICULTURAL LIMESTONE 75.0 TON
28 FERTILIZER 3.0 TON
29 SEED 480.0 LBS
30 MULCH- STRAW & HAY 6.0 ACRE
31 ROADWAY STONE 500.0 TON
32 BITUMINOUS REPAIR 725.0 TON
NOTE: THE AUTHENTICATION OF BID AND STATEMENT OF NON-COLLUSION
AND NON-CONFLICT OF INTEREST PAGE MUST BE PROPERLY EXECUTED
FOR THE TOTAL BID AMOUNT TO BE VALID.
** Allowances included in the Contract Amount: The Contractor is required by Article ’30 of the General Conditions to include in the Contract Amount the following Allowances:
*UTILITY RELOCATION/REPLACEMENT $ 50,000.00
*LANDSCAPE ALLOWANCE $ 15,000.00
*STRUCTURE REMOVAL/REPLACEMENT $ 40,000.00
Allowances shall include all necessary materials, costs of delivery, installation labor, tools and equipment necessary to provide the item or services indicated in the Allowance. When the item of work or service is completed, the Contact Amount is modified by Change Order to reconcile the Allowance with the actual cost of the item or service provided. The contractor’s overhead, profit, insurance and bonds, and administrative costs are included in the prescribed markup permitted by Article ’14 of the
General Conditions “Changes in the Work” and are not to be included in the
Allowance.
REVISED 4/12/2023