Addendum No. 2 to Contract T-1472-0150 for the LIGHT RAIL HOWARD STREET EMBEDDED TRACK project was issued by the Maryland Transit Administration. This addendum provides information regarding a third site visit scheduled for June 15, 2022 at 9:00 AM EST due to inclement weather during the second site visit. It also includes the sign-in sheet from the second site visit. All other terms and conditions of the contract remain unchanged.

The LIGHT RAIL HOWARD STREET EMBEDDED TRACK contract is for the reconstruction of light rail tracks in Howard Street in the Central Business District area of Baltimore City, Maryland. The project limits extend from the intersection of Howard Street and Camden Street to the intersection of Howard Street and Martin Luther King Jr. Boulevard.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

TO: All Prospective Proposers

FROM: Maryland Transit Administration

SUBJECT: Addendum No. 2

T-1472-0150 – LIGHT RAIL HOWARD STREET EMBEDDED TRACK

DATE: June 14, 2022

Addendum No. 2 is two (2) pages and includes the following:

ITEM No. 1 --- Provides a third site visit on June 15, 2022 @ 9:00 AM EST, due to inclement weather during the second site visit held on June 14, 2022. The site visit will begin at the intersection of Howard Street and Martin Luther King Blvd. All attendees must wear a safety vest.

ITEM No. 2 –Provides the second site visit sign-in sheet.

All other terms and conditions remain unchanged.

Sincerely, Christie Williams Christie Williams Procurement Administrator Procurement Division Maryland Transit Administration

Acknowledgement of receipt of Addendum No. 2 to T-1472-0150

Vendor Name: ___________________________________________________________

Authorized Representative’s Signature Date

This is the end of Addendum No. 2

File details come from the government source that posted it. Updated .