Addendum No.2 - ITB 26-032-PW.pdf

PDF 147 KB Posted

Attached to
26-032-PW Myoak Drive and River Road - Water Main
Solicitation number
S-P00140-00016186
Issued by
Lane County, Oregon

About this file

This is Addendum No. 2 to Invitation to Bid 26-032-PW issued by the Eugene Water & Electric Board (EWEB) for the Myoak Drive and River Road Water Main Replacement project in Lane County, Oregon. The addendum clarifies that EWEB will be responsible for all service tie-ins and abandoning old services to houses per Specification Section 01014, and specifies that concrete and gravel quantities are estimated based on field conditions and therefore are not detailed on project plans. The bidding documents remain otherwise unchanged, with a closing date and time maintained as originally stated. The project scope includes approximately 1,150 linear feet of 8-inch diameter ductile iron pipe water main installation, five 8-inch diameter gate valves, 400 linear feet of 2-inch diameter HDPE pipe, two fire hydrant assemblies, 26 service connections, sanitary and storm sewer line repairs totaling 130 linear feet, and concrete and asphalt restoration work with erosion control measures. The Notice to Proceed is anticipated for April 10, 2026, with substantial completion required by August 31, 2026, and final completion by September 30, 2026.

Bidders must acknowledge receipt of this addendum by signature and return it with their bid response or by circling the addendum number on the bid form, as this constitutes a material change to the bid documents. Contractors must be registered and bonded with the Oregon Construction Contractors Board or Landscape Contractors Board at time of bid submission and demonstrate three projects each involving ductile iron pipe installation and waterline installation in a roadway within the past five years. A bid bond of 10 percent of the total bid amount is required for bids exceeding $100,000, with performance and payment bonds required at 100 percent of contract value upon award. Liquidated damages are assessed at $400 per day for failure to achieve substantial completion and an additional $400 per day for failure to achieve final completion. The engineer's estimate for the project is approximately $400,000. The project is subject to Oregon prevailing wage requirements and equal employment opportunity and affirmative action requirements applicable to all public works contracts.

View the file

Other files

File Type Posted
ITB 26-032-PW Bid Tab.pdf PDF
Addendum No.1 - ITB 26-032-PW.pdf PDF
ITB 26-032-PW Myoak Dr Main Replacement.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Rev 4-21-20

March 16, 2026

ADDENDUM #2

Myoak Drive and River Road – Water Main Replacement

ITB 26-032-PW

This addendum modifies the bidding document(s) for work only to the extent indicated herein. All other areas not specifically mentioned or affected by this addendum shall remain in full force. This addendum shall be added as a part of the original bidding document and shall become part of the work required.

Questions and Answers Q. Will EWEB be completing the service tie-ins and abandoning old services to the house?

A. Yes, EWEB will be performing the service connections and abandoning old services, per Specification Section 01014.

Q. Are there any plans showing the concrete driveway work?

A. The concrete and gravel quantities are estimated quantities for as-needed work depending on field conditions and therefore not called out on the plans.

CLOSING DATE AND TIME

Remains unchanged.

This addendum constitutes a MATERIAL CHANGE to the bid. ITS RECEIPT BY THE BIDDER IS TO BE ACKNOWLEDGED BY A SIGNATURE AND RETURNING A COPY OF THE ADDENDUM WITH ITS RESPONSE OR BY CIRCLING THE ADDENDUM

NUMBER IN THE APPROPRIATE AREA ON THE BID FORM.

Addendum prepared by:

Wendy Lopez, Purchasing Analyst

The undersigned hereby acknowledges receipt of this Addendum and agrees to be bound by the conditions therein.

Company Name: ________________________________

Signature: ______________________________________ Date __________________________

End of Addendum