Addendum No. 1 Ray St Water Sewer Replacement.pdf
PDF 110 KB Posted
- Attached to
- RAY STREET WATER AND SEWER REPLACEMENT PROJECT CDBG-I Project Numbers: 19-I-3648 and 21-I-4004
- Solicitation number
- 498-0003282025
- Issued by
- Pender County, North Carolina
About this file
Addendum No. 1 is a document issued by Johnson, Mirmiran & Thompson for the City of Elizabeth City's Ray Street at Brooks Avenue Water and Sewer Replacement project, dated March 31, 2025. The addendum provides clarifications and amendments to the original bid documents, addressing multiple technical specifications, drawing details, and questions raised during the pre-bid process. Key clarifications include confirmation that water service lines are not limited to copper, specifications for sanitary sewer precast concrete manholes requiring interior epoxy coating, confirmation of new meter setters and water meters (to be furnished by the City of Elizabeth City with AMI remote reading capabilities), and allowances for asphalt surface course replacements.
The addendum indicates the project will follow Davis-Bacon wage determination for Heavy Construction, with the wage determination number NC20250069 dated 01/03/2025. The document specifies that the Prime Contractor must submit a Section 3 plan with the bid package and provides guidance on various technical requirements, including pipe bedding, water service connections, and pavement restoration. The addendum emphasizes the need for coordination with the City of Elizabeth City and provides detailed responses to technical questions that potential bidders may have about the project's specifications, drawings, and implementation requirements.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM NO. 1
To Bid Documents for Ray Street at Brooks Avenue Water and Sewer Replacement
The City of Elizabeth City, NC
March 31, 2025
To All Concerned:
The original Bid Documents for the City of Elizabeth City Department of Public Utilities Ray Street at Brooks Avenue Water and Sewer Replacement are amended as noted in this Addendum No. 1, and the Addendum shall become part of the Bid Documents. Bidders must acknowledge receipt of this Addendum during the bidding process by signing the Bid Proposal/Contract Forms when submitting proposals.
Pertaining to the Specifications
Question - Can 2-inch milling be replaced with 2-inch overlay?
Answer – A 2-inch overlay is defined as Asphalt Surface Course SM-9.5 Bid Item No. 6.
See Technical Specifications for Asphalt Surface Course requirements.
Question – Is a Section 3 plan provided within the Contract Specifications?
Answer – No. A Section 3 plan will be provided in Addendum No.1. The Prime
Contractor shall fil out and submit with the Bid Package.
Contract Specifications
Delete Contract Specifications and Replace with the attached amended Contract Specifications in whole.
Question – Are the water service lines only to be copper?
Answer – No. See Technical Specification Water Mains and Appurtenances 3/4-inch to
2-inch Services for Water Distribution and 3/4-inch to 8-inch Water Meters Subsection 06. Pipe for Service Lines.
Question – How will certified payrolls be handled?
Answer – See Contract Specifications; Davis-Bacon Wage Determination and
Standards Guide and HUD-4010 Federal Labor Standards Provisions for requirements.
Question – What was the wage determination for this project?
Answer – Heavy Construction. See Contract Specifications Davis-Bacon Wage
Determination “General Decision Number: NC20250069 01/03/2025”.
Note: Unlisted classifications may be added as per this specification section.
Question – What is the project schedule for this project?
Answer – Please see Specification “Agreement Between Owner and Contractor for
Construction Contract” Page C-520 Article 4 – Contract Times Subsection
4.02 Contract Times: Days.
Question – Is an insertion valve required? If so, it is recommended to provide an alternative bid item.
Answer – Please see Bid Form Article 5 Basis of Bid Item No. 12: Temporary Line Stop or Insertion Valve.
Pertaining to the Drawings
Sheets 5 – 7 of 9.
Question – Is the new sanitary sewer alignment the same as the existing sewer?
Answer –Yes Horizontally. No Vertically as new alignment is deeper.
See sheets 5 – 7 of 9.
Question – Are new meter setters required?
Answer – Yes. See sheets 5 – 7 of 9.
Sheet 9 of 9 Question – Do the new sanitary sewer precast concrete manholes require an interior epoxy coating?
Answer – Yes. A high Build SikaGard 62 or Kaufman SurePoxy HiBild at 16 mils wet shall be applied by the Precast Concrete Company.
See amended sheet 9 of 9.
Question – Are new water meters required?
Answer – Yes. The City of Elizabeth City shall furnish and install. Note: New water meters will be AMI and module for remote reading.
See amended sheet 9 of 9. Coordination with the City of Elizabeth City is required.
Sheets 1 and 9 of 9.
Question – Can the 2” of Type I 19B intermediate course be replaced with 2” of Type
9.5A surface course?
Answer – Yes. Please see Note #10 on Sheet 1 of 9 and see amended sheet 9 of 9.
Sheet 9 of 9
DELETE sheet 9 of 9 and REPLACE with the attached amended Sheet 9 of 9. See amended Manhole detail SEW-05, Pipe Bedding/Open Cut Patch for Asphalt Pavement and Soil detail SEW/WAT-01, and Water Service Connection detail WAT-04.
Pertaining to the March 6, 2025 Pre Bid Meeting Minutes
DELETE Mandatory Pre-Bid Meeting Minutes dated 3/14/2025 and REPLACE with the amended Meeting Minutes attached herein with Addendum No.1.