Addendum No. 1 - On Site Sewage System Study.pdf
PDF 3 MB Posted
- Solicitation number
- RFP-171-190000003008-2
- Issued by
- Michigan
About this file
This is an addendum to a Request for Proposal (RFP) issued by the Michigan Department of Technology, Management and Budget's State Facilities Administration, Design and Construction Division for a new sewage disposal system study at Bewabic State Park (File Number 751/19158.RAA). The addendum, issued on September 9, 2019 with proposals due September 19, 2019, includes several modifications to the original RFP scope. Key changes include: extending the Phase 100 completion date to November 30, 2020; adding effluent concentration testing requirements under a $5,000 owner's directed allowance; removing the Contact Station/Beach House drain fields evaluation from scope; adding conversion of campsites 119-128 to full hookup sites to the design basis; and requiring consideration of a 45-day archaeological exploration permit application process in the project schedule.
The addendum includes revised travel reimbursement and billing rate requirements per DTMB-430 Minor State Capital Outlay Projects Billable Rate guidelines. Additional attachments provided include a mandatory PSC walkthrough attendance list, a concept map showing the combination of two toilet shower buildings into one, and DEQ Public Act regulations governing campgrounds. The document package also contains extensive technical specifications and requirements for campground facilities, sewage systems, and operations as outlined in the Michigan Public Health Code and Department of Environmental Quality administrative rules.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DTMB-0414 RFP (Rev 6/16)
DEPARTMENT OF TECHNOLOGY, MANAGEMENT AND BUDGET
State Facilities Administration Design and Construction Division
REQUEST FOR PROPOSAL ADDENDUM NO. Enter No.
This form identifies an Addendum to a Request for Proposal for Professional Services, and incorporates interpretations or clarifications, modifications, and other information into the Request for Proposals. Addenda will be numbered by the Project Director and distributed through www.michigan.gov/SIGMAVSS as an attachment.
TO:
ALL PROPOSERS
DATE ISSUED
9/9/2019
PROJECT NAME
Bewabic S.P. New Sewage Disposal System Study
FILE NUMBER
751/19158.RAA
PROJECT DIRECTOR
Jeff Barsch
PROPOSAL DUE DATE:
9/19/2019
ADDENDUM ITEMS: (attach additional sheets and drawings if required)
Item 1-Mandatory PSC Walkthrough attendance list is attached.
Item 2-proposed PSC Schedules for implementation of the study shall take into account the 45 day archeological exploration permit application process.
Item 3-The Phase 100 Completion Date has been revised and shall now be November 30, 2020. Proposed Schedules included with proposals shall reflect this new completion date.
Item 4-Include an itemized cost for effluent concentration testing under the Owners Directed $5,000 allowance. This testing shall take place within the existing system and at the last point prior to discharge as recommended by the PSC. Sampling shall include but may not be limited to:
BOD levels, phosphorus, ammonia, and formaldehyde. Anticipate a minimum of 4 sample sets (4 peak and 2 non-peak), the proposed schedule shall reflect this testing to occur following the Memorial Day & Forth of July Holidays.
Item 5-Evaluation of the Contact Station/Beach House drain fields shall be eliminated from the scope of work for this study.
Item 6-Inclusion of converting campsites 119-128 (10 total) to full hookup sites shall be added to the on-site sewage disposal basis of design for this study.
Item 7-On the project statement under additional requirements revise item 1 to state: Travel reimbursements and billing rates shall be in accordance with the attached DTMB-430 Minor State Capital Outlay Projects Billable Rate Request for Proposals from Professional Service Contractors.
Item 8 – Concept map of combining 2 toilet shower buildings into one is now attached.
Item 9 -DEQ Public Act Governing Campgrounds are attached.
APPROVED BY:
DATE: 9/9/2019
http://www.michigan.gov/SIGMAVSS cadeaue Polygon cadeaue Callout Potential development concept (Demolish two existing toilet shower buildings (shown in black) construct one new toilet shower building with sufficient fixtures to meet DEQ campground rules for 130 campsites.
cadeaue Callout Potential development concept (Demolish two existing toilet shower buildings) cadeaue Line