This document is Addendum No. 1 issued by U.P. Engineers & Architects, Inc. on November 1, 2022, for the Linton Creek Culvert Replacement project in McMillan Township, Luce County, Michigan. The addendum provides clarifications, modifications, and changes to the original plans and specifications for this project, which involves the replacement of culverts at four locations: Otto Brandt Creek, Penny Creek, Savage Creek, and Linton Creek. The addendum includes details on the pre-bid walk-through, soil borings, and a borrow pit that the contractor may utilize. It also specifies that the contractor is responsible for returning all roads to original or better condition and making any impassable roads accessible for construction.
The contract opportunity, identified as File No. 751/21232.ABG, is for Luce County's culvert and bridge replacement project. Bidders are required to submit their proposals through the SIGMA VSS system, and they may be asked to email their proposals if they experience issues with the electronic submission. The contract term and any renewal options are not specified in the provided information.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
707 Ashmun Street Sault Ste. Marie, MI 49783
906-635-0511 • 800-867-0511 • Fax: 906-635-0612
Offices also in:
Houghton
Iron Mountain Ishpeming Marinette
U.P. Engineers & Architects, Inc.
www.UPEA.com
[M12-02386]
ADDENDUM NO. 1
LINTON CREEK CULVERT REPLACEMENT
MCMILLAN TOWNSHIP, LUCE COUNTY, MI
ADDENDUM NO. 1 is issued November 1, 2022, to clarify, modify, and/or change the original plans and specifications issued by UP Engineers and Architects. This ADDENDUM NO. 1 is hereby made part of the Contract Documents for the contract noted below.
File No. 751/21232.ABG, Linton Creek Culvert Replacement
Please acknowledge receipt of this ADDENDUM NO. 1 on the appropriate blank on the Bid Form and also include this addendum with the bid package.
GENERAL
• See attached pre-bid walk-through sign-in sheet.
• The EGLE permit application has been submitted for each location and is still being reviewed by EGLE.
• See attached soil borings for each location.
• The contractor may utilize sand from the DNR owned borrow pit just west of Linton
Creek Crossing. The soil is considered to be MDOT Class II sand. Borrow pit shall be brought back to original condition. It will be the contractor's responsibility to return all roads to original or better condition. It will also be the contractor's responsibility to make any impassable roads accessible for the construction.
SPECIFICATIONS
• SECTION 00200 INFORMATION FOR BIDDERS – 7.1 Schedule of Values: Separate schedule of values shall be provided for each crossing. The schedule of values must be approved by the Professional and accepted……
PLANS
• G001 – Add the following notes.
o Otto Brandt Creek
A staging area is available directly to the east of the bridge.
o Penny Creek and Savage Creek
The existing steel bridges each weigh approximately 35,000 pounds.
o Savage Creek
The existing easement for this crossing is 66' or 33' each side of the centerline of the road
• OTTO BRANDT AND SAVAGE CREEK - C501 –
o Detail D4 SECTION @ ABUTMENT - 2” OAK OR DF WEAR COURSE o Detail A4 – ABUTMENT DETAIL – (3)/#6 BARS CONTINUOUS IN MDOT S1
CONCRETE POUR
END OF ADDENDUM NO. 1
Prepared by:
U.P. Engineers & Architects, Inc
FIELD LOG
mid
PROJECT Linton Creek Culvert DATE STARTED 6/15/22 DRILLER BM JOB NO. M12-02386 DTMB LOCATION Newberry, MI – Luce County DATE COMPLETED 6/15/22 HELPER EB BORING NO. SB-1
SAMPLE
NO.
DEPTH (ft) DRILLING
OR
SAMPLING
METHOD
SPLIT SPOON BLOWS
SAMPLE DESCRIPTION
FROM TO 0"-6" 6"-12" 12"-18" 18"-24"
SB-1 2.5’ 4.0’ S/S 2 1 3 Fine sand with trace silt
5.0’ 6.5’ S/S 6 6 11 Medium / Coarse sand w/ trace gravel – (stone in spoon tip)
7.5’ 9.0’ S/S 2 3 5 Coarse sand w/ trace gravel
10.0’ 11.5’ S/S 2 4 5 Coarse sand w/ trace gravel
15.0’ 16.5’ S/S 6 11 16 Clean uniform medium sand
20.0’ 21.5’ S/S 11 16 17 Clean uniform medium sand
25.0’ 26.5’ S/S 14 24 28 Clean uniform medium sand
30.0’ 31.5’ S/S 40* Mixed gravels & fractured Limestone – (spoon would not penetrate – bounce after 6”)
*31.0’ Tri-cone Could not advance Tri-cone bit (*refusal) – grind on solid rock
BACKFILL METHOD WATER LEVEL OBSERVATION
NATURAL SOILS WL: . WS or WB
CEMENT GROUT WL: . AFTER BORING
BENTONITE & CEMENT WL: . HRS/AFTER BORING
OTHER Pavement Patched w/ Blacktop PAGE OF
PROJECT Otto Brandt Bridge DATE STARTED 6/14/22 DRILLER BM JOB NO. M12-02386 DTMB LOCATION Newberry, MI - Luce County DATE COMPLETED 6/15/22 HELPER EB BORING NO. SB-1
DEPTH (ft) DRILLING
OR
SAMPLING
METHOD
SPLIT SPOON BLOWS
SAMPLE DESCRIPTION
FROM TO 0"-6" 6"-12" 12"-18" 18"-24"
SB-1 2.5’ 4.0’ S/S 1 1 1 Black silty / topsoil mixed with sand
5.0’ 6.5’ S/S 3 5 5 Clean white medium sand
7.5’ 9.0’ S/S 4 2 4 Saturated medium / fine sand
10.0’ 11.5’ S/S 1 1 2 10’-11’ sand / gravel 11’-11.5’ fine silty clay
15.0’ 16.5’ S/S 2 4 3 Fine Silty Clay
20.0’ 21.5’ S/S 1 1 1 Fine Silty Clay
25.0’ 26.5’ S/S 1 1 2 Fine Silty Clay
30.0’ 31.5’ S/S 1 0 1 Fine Silty Clay
35.0’ 36.5’ S/S 1 1 1 Fine Silty Clay
40.0’ 41.5’ S/S 1 0 1 Fine Silty Clay
42.5’ Auger Drilling starting to firm up (tighter / harder material)
*43.0’ Auger Could not advance drill steel (*refusal) grind on flat solid rock refusal
NATURAL SOILS WL: 7 . 58’ WS or WB
CEMENT GROUT WL: . AFTER BORING
PROJECT Penny Creek Bridge DATE STARTED 6/15/22 DRILLER BM JOB NO. M12-02386 DTMB LOCATION Newberry, MI - Luce County DATE COMPLETED 6/16/22 HELPER EB BORING NO. SB-1
DEPTH (ft) DRILLING
OR
SAMPLING
METHOD
SPLIT SPOON BLOWS
SAMPLE DESCRIPTION
FROM TO 0"-6" 6"-12" 12"-18" 18"-24"
SB-1 2.5’ 4.0’ S/S 8 19 14 Wood timber & dark silt
5.0’ 6.5’ S/S 1 1 1 Black silty material with organics
7.5’ 9.0’ S/S 4 6 5 7.5’-7.67’ dark silt – then medium sand to 9.0’
10.0’ 11.5’ S/S 3 3 4 Fine silty clay
15.0’ 16.5’ S/S 1 1 0 Fine Silty Clay
20.0’ 21.5’ S/S 1 1 2 Fine Silty Clay
25.0’ 26.5’ S/S 2 1 1 Fine Silty Clay
30.0’ 31.5’ S/S 0 1 1 Fine Silty Clay
35.0’ 36.5’ S/S 1 1 1 Fine Silty Clay (37’ – 40’ drilling had multiple firm seams – possible start of sand )
40.0’ 41.5’ S/S 16 24 26 Clean uniform light-colored medium sand
45.0’’ 46.5’ S/S 20 25 27 Clean uniform light-colored medium sand
50.0’ 51.5’ S/S 3 3 3 Fine Silty Clay
CEMENT GROUT WL: . AFTER BORING
PROJECT Savage Creek Bridge DATE STARTED 6/29/22 DRILLER BM JOB NO. M12-02386 DTMB LOCATION Newberry, MI - Luce County DATE COMPLETED 6/30/22 HELPER EB BORING NO. SB-1
DEPTH (ft) DRILLING
OR
SAMPLING
METHOD
SPLIT SPOON BLOWS
SAMPLE DESCRIPTION
FROM TO 0"-6" 6"-12" 12"-18" 18"-24"
SB-1 2.5’ 4.0’ S/S 3 6 9 Fine Sand with trace Gravel
5.0’ 6.5’ S/S 1 1 4 Wood / Fine Sand (old bridge ?)
7.5’ 9.0’ S/S 4 5 5 Fine / Medium Sand (saturated)
10.0’ 11.5’ S/S 4 4 4 Fine / Medium Sand
15.0’ 16.5’ S/S 3 2 3 Silty Fine Sand
20.0’ 21.5’ S/S 4 1 2 Silty Fine Sand
25.0’ 26.5’ S/S 4 4 5 Medium / Fine Sand
30.0’ 31.5’ S/S 1 0 1 Fine Silty Clay
35.0’ 36.5’ S/S 1 0 1 Fine Silty Clay
40.0’ 41.5’ S/S 0 1 1 Fine Silty Clay
45.0’’ 46.5’ S/S 0 1 1 Fine Silty Clay (drilling 46.5’ to 50’ had firm seams – possible start of tight fine sand)
50.0’ 51.5’ S/S 21 31 28 Uniform clean fine sand
CEMENT GROUT WL: . AFTER BORING
| Addendum No. 1 LINTON Final.pdf |
| END OF ADDENDUM NO. 1 |
| Insert from: "M12-02386 DTMB Linton Creek Culvert Replacement (4 locations).pdf" |
| Linton Creek Culvert |
| Otto Brandt Bridge |
| Penny Creek Bridge |
| Savage Creek Bridge |
File details come from the government source that posted it. Updated .