Addendum No.1_City of Port Huron PS Repairs 2024.pdf

PDF 123 KB Posted

Attached to
MOC Parking Structure Rehabilitation Project
Solicitation number
G23-0010
Issued by
Monroe County, Michigan

About this file

Addendum No. 1 is issued by Walker Consultants for the City of Port Huron's Parking Structure Repairs 2024 project, with bids to be received by 3:00 p.m. on June 17, 2024. The addendum provides clarifications and requirements for the rehabilitation project, including specifications for supplier and installer qualifications, scheduling constraints, and work limitations. Key requirements include compliance with Specification Section 033818 for qualifications, concurrent work in evidence rooms, advance notice for work in specific areas, and restrictions on noise and dust-generating work during certain times.

The addendum addresses operational considerations for the parking structure, stipulating that contractors cannot impede access to fuel pumps, must provide advance notice before impacting certain areas like the drop-off station, and cannot perform work in or above occupied parking stalls. A submitted question regarding alternative repair methods (installing beams instead of post-tensioned cable repairs) was denied. The project appears to involve detailed rehabilitation of a parking structure with specific operational constraints to minimize disruption to the facility's ongoing use.

View the file

Other files

File Type Posted
00100Advertisement Bids.doc DOC document
2024-05-23_Port Huron Bidding _ Construction (Dwgs).pdf PDF
Addendum No. 2_City of Port Huron PS Repairs 2024.pdf PDF
Spec Book.pdf PDF

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

ADDENDUM NO. 1

CITY OF PORT HURON PARKING STRUCTURE REPAIRS 2024

WC PROJECT NO. 20-002368.00 JUNE 10, 2024

TO BID DOCUMENTS FOR

CITY OF PORT HURON

Parking Structure Repairs 2024 Port Huron, MI

The following changes, additions, and/or deletions shall be made to the Bid Documents for project listed above on which bids will be received by 3:00 p.m., June 17, 2024.

The information contained herein shall take precedence over the original documents and all previous addenda and is appended thereto.

The Contractor is to acknowledge receipt of this Addendum No. 1 on the Bid Form.

Certain changes in the Bid Documents which are outlined below are referenced to a specification section or drawing in which they appear conspicuously. The Bidder is to take note in its review of the documents and include these changes and clarifications as they affect work or details in other areas not specifically referenced here. Other changes or clarifications in this addendum have broader significance and may apply to more than one location and are not specifically referenced.

MODIFICATIONS:

1. None.

CLARIFICATIONS:

1. Contractor must comply with the Supplier and Installer Qualifications per Specification Section 033818, paragraph 1.7, and provide completed supporting qualification forms attached to this Section when submitting their bid.

2. Regarding Schedule/Phasing Requirements, Note 1, on Drawing sheet R-001, both evidence rooms will be emptied by the Owner prior to the start of work date provided in Specification Section 00310. Work in both evidence rooms shall occur concurrently to minimize the amount of time the evidence rooms are out of service.

3. Prior to performing Work that impacts the storage area on the lower-level (location approximately defined on the R-100 Series Drawing sheets by the rectangle created by column line G-3 to column line I-5), Contractor shall provide a minimum of 7 days advance notice to the Owner.

4. In addition to all other work hour restrictions provided in the Drawings or Specifications, the Contractor shall not perform any noise or dust generating Work after 4:00 p.m. on Thursdays in the month of August.

CITY OF PORT HURON PARKING STRUCTURE REPAIRS 2024

WC PROJECT NO. 20-002368.00 JUNE 10, 2024

5. Contractor shall not, at any given time, impede access to the fuel pumps located on the north vehicle ramp providing access to the lower level of the parking structure.

6. Prior to performing Work that impacts the use of the existing, upper-level drop-off station (approximately located at column line I-6, Drawing sheet R-102), Contractor shall provide a minimum of 7 days advance notice to the Owner.

7. Contractor shall not, at any given time, perform Work in or above a parking stall occupied by a vehicle. Contractor shall coordinate Work area capture with the Owner a minimum of 7 days advance.

ANSWERS TO SUBMITTED QUESTIONS:

1. Question: Would the Engineer and Owner consider revising the Scope of Work to install beams from column to column in lieu of performing post-tensioned cable repairs?

Answer: No.

Attachments and/or Enclosures:

None.