This document is Addendum No. 2 issued by the Department of Public Works for the City of Springfield related to an Invitation for Bids for a Roadway Rehabilitation and Resurfacing contract. The addendum provides clarification and additional information regarding the project scope, which involves the rehabilitation and resurfacing of approximately 12 miles of roadway within the city limits. The addendum revises the bid submission deadline to September 15th and reschedules the mandatory pre-bid conference to September 5th. The contract term is for one year with two one-year renewal options.
The addendum also provides updated unit price bid forms, revised specification sections, and additional information regarding existing pavement conditions. Pricing shall be submitted on a unit price basis, with the city reserving the right to award the contract in whole or in part. The project is funded through the city's annual street maintenance budget, with an estimated total value of $4.5 million. There are no set-aside requirements, and the current contractor is ABC Paving, Inc.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
COMMONWEALTH OF KENTUCKY
DEPARTMENT FOR FACILITIES AND SUPPORT SERVICES
DIVISION OF ENGINEERING AND CONTRACT ADMINISTRATION
INVITATION TO BID NO: RFB-63-25
FOR: Construct Burlington Field Maintenance Shop (FMS)
Department of Military Affairs Burlington, Kentucky
DATE: September 9, 2024
RFB-785-2500000103
ADDENDUM NO. Two (2)
BIDDER SHALL CONFORM TO THE FOLLOWING CHANGES AS SAME SHALL BECOME BINDING
UPON THE CONTRACT TO BE ISSUED IN RESPONSE TO THIS INVITATION TO BID.
Item 1: Refer to addendum to be distributed by Lynn Imaging for all additions, deletions, and/or changes to specifications and/or drawings.
END OF ADDENDUM
Invitation to Bid No. RFB-63-25 For: Construct Burlington Field Maintenance Shop (FMS)
Department of Military Affairs Burlington, Kentucky
Kristi Sharp, Statewide Procurement Manager Division of Engineering and Contract Administration
Addendum 2 Page 1 of 8
201 W. Short Street • Suite 700 • Lexington, KY 40507 • 859.231.7538 • www.eopa.com
Addendum No. 2
For the new DMA Burlington FMS Burlington, Kentucky
Invitation to Bid NO: RFB-63-25 September 6th, 2024
The following addendum items officially modify the construction documents and become binding to the contract for construction (Contractor is to note receipt of all addendums on their bid form of proposal):
1. CIVIL:
Specifications
1.1. 312000 EARTH MOVING – Revised specification.
1.2. Storm Water Report
1.3. Storm Water Prevention Plan
1.4. Geotech Report
Drawings
1.5. CE101 EPSC Plan West – revised main construction entrance point.
2. MECHANICAL:
Specifications
2.1. 250400: Added Yaskawa to list of acceptable manufacturers of VFDs.
2.2. M301 – Revised keynote M63 identifying piping material per specification 202700.
2.3. M700 – Updated VFD schedule to align with acceptable manufacturer’s listed in specification.
2.4. UM100 – Corrected circuit detail pipe size.
3. PLUMBING:
3.1. P601 – Revised hot water storage tank schedule.
4. Bidders Questions:
http://www.eopa.com/
Addendum 2 Page 2 of 8
4.1. Question: We did not find a qualification in the 04200 Unit Masonry spec section that alternates would be considered per architects’ discretion.
Answer: Other manufacturer’s are acceptable as long as they can meet the performance and aesthetic characteristics of the Basis of Design.
4.2. Question: Where are the underground storm chambers described, as referenced on drawing CG101 & CG102 by Sheet Keynote #13?
Answer: They are located in the POV lot and in the MEP lot by the main entrance. The extents of the gravel is shown as a dashed line, however, this is an approximation, as needs to be further designed by the contractor/chamber manufacturer.
4.3. Question: Looking at drawing CS101B, a retaining wall is called out by Sheet Keynote #31. Most drawings I see have a top of wall and bottom of wall elevations at all changes in slope of the top or bottom. Please provide. Is detail 5/S502 the wall for this location? It appears way too large for the elevation changes…..
Answer: Please see revised sheets CG101B for spot elevations of the retaining wall. Revisions to sheet S502, for updated retaining wall detail to be forthcoming in future addendum.
4.4. Question: In the spec section 146300 HOIST AND CRANES paragraph 2.2 calls for a shawbox or kone hoist is and or equal acceptable?
Answer: Other manufacturer’s are acceptable as long as they can meet the performance requirements of the specifications and Basis of Design.
4.5. Question: Specification 033000 Concrete Mixtures-Mix Designs reference transfer building and do not appear to match the mix design noted on the plan S002. Please confirm mix designs.
Answer: To be addressed in future addendum.
4.6. Question: On drawing S105 is a vehicle service ramp. Please confirm this is to be provided by the contractor. If provided by the contractor, please provide a specification.
Answer: To be addressed in future addendum
4.7. Question: Specification 071416 Cold Fluid Applied Waterproofing-3.7 references Field Testing.
Please confirm is this testing requirement is accurate for this building since it is grade with no basement.
Answer: Field testing is not required. Delete paragraph 3.7 Field Quality Control.
4.8. Question: Specification 077200 Roof Accessories-please confirm there are no heat and smoke vents on this project. If they are required, please provide specification and schedule.
Answer: Smoke and heat vents are not included. Delete items 2.3 and 3.2 D in spec section 077200 Roof Accessories.
Addendum 2 Page 3 of 8
4.9. Question: Specification 079200-Joint Sealants-please provide joint sealant schedule defining which joints sealants are required for each joint type
4.10. Question: Specification 084513 -Polycarbonate Panel Assemblies-please confirm if water spray test is required. The storefront specification does not appear to require any water spray testing.
Answer: For specification 084513 STRUCTURED-POLYCARBONATE-PANEL ASSEMBLIES delete paragraph 3.3 Field Quality Control. For 084113 ALUMINUM-FRAMED ENTRANCES AND STOREFRONTS note that water spray testing is defined in paragraph 2.2 Performance Requirements, and in section 019119 BUILDING ENVELOPE TESTING at paragraph 3.8 Water Leakage Tests Criteria.
4.11. Question: Specification 095113- Acoustical Panel Ceilings- On sheet A800, the finish legend calls for Armstrong Optima – square say-in 24" x 24". Which would be #3150 Optima. The specification requires – CAC: Not less than 35, NRC: Not less than 0.70, LR: Not less than 0.90, tegular edge 24" x 24" x 3/4" thick, Type IV Form 2. The information in the specs would suggest it should be Armstrong #1911 Ultima. Please confirm.
Answer: On sheet A800 revise the finish legend to indicate 1911 ULTIMA, beveled tegular.
4.12. Question: Specification 105113-Metal Lockers-See attached substitution request from Vendor.
Answer: Other manufacturers are acceptable as long as they can meet the performance requirements of the specifications and Basis of Design.
4.13. Question: Where are the loading dock bumpers to be installed? There appears to be no loading dock type area on this facility.
Answer: Dock bumpers are indicated on Sheet S-106.
4.14. Question: Specification 202700 Fuel Oil Distribution System-Nothing is shown on the drawings for this material. Please confirm.
Answer: Piping notes on plans have been updated to reconcile with specification.
4.15. Question: POL Piping and equipment is noted on the plans but there is no specification.
Please provide specification.
Answer: All equipment and piping specifications are noted on plans. No need for specification section.
4.16. Question: What is the existing Fire Alarm system for the Burlington Readiness Center and does the Burlington FMS need to tie-into it?
Addendum 2 Page 4 of 8
4.17. Question: What is required for Background Checks?
Answer: The National Guard has a specific form that will be required to fill out, which includes address and social security number. This will be sent directly to the individual performing the background check and will not be shared with anyone else. Essentially looking for major offenses.
Anyone driving onsite will be required to have a valid driver’s license to drive onsite.
4.18. Question: Can you please provide information for the solar panel provider of the existing Burlington Readiness Center.
Answer: The existing solar panel provider at the Burlington Readiness Center is Solar Energy Solutions.
4.19. Question: Concerning the Underground Detention Basins, we could not find the requirements on the SD1 site, can you post them? Also could not find the Stormwater Report mentioned on page 6 of the specification 33 42 00.
Answer: “Sanitation District No. 1 Storm Water Rules and Regulations, June 2020” and “Storm Water Best Practices Manual, February 2012” are the SD1 documents that describe the stormwater requirements that need to be met. These include water quantity, peak flow, and quality requirements. They can be found at sd1.org/213/Permitting-Other-Requirements. The requirements for the underground detention basins are to meet these performance requirements.
Specific design features for the underground detention will need to be determined by the manufacturer and sent to SD1 for approval. The Burlington FMS Stormwater Report will be included in the next Addendum.
4.20. Question: Owner vs Contractor responsibility for site utilities. Conflicting information in specifications.
Answer: Refer to special conditions for requirements.
4.21. Question: Conflicting information regarding PV as alternates between specifications and drawings.
Answer: Alternates 2 and 3 noted on electrical drawings are to be 3 and 4.
4.22. Question: Soils report treating of fatty soils but did not see specification on how this is to be done.
Answer: See revised specification 312000 EARTH Moving.
4.23. Question: Site / Piers: Can the geotechnical report be provided?
Answer: See attached Geotech Report.
4.24. Question: Can Storm Water report be provided?
Answer: See attached report.
Addendum 2 Page 5 of 8
4.25. Question: Paint: 099123-2.5-A Floor sealer spec says "clear water-based acrylic-copolymer-emulsion sealer formulated for oil gas alkali water resistant", I do not know this product exists, can a Sherwin Williams (or similar) product be clarified as the basis of design? Closest product Sherwin Williams has is "wet-look" which is solvent based.
Answer: In addition to the available manufacturers listed add the following as a basis of design:
W.R. MEADOWS VOCOMP-20 water-based, acrylic, concrete curing and sealing compound for fresh concrete.
4.26. Question: Roofing: Spec section for EPDM 075323-5 section 2.2 reads a thickness of 90 mils.
Details 2+6 on A161, indicate 60 mil. Can this be clarified?
Answer: Provide 90 mil thickness per specifications.
4.27. Question: Fencing Per 323113.53-G1 – Lists 9 ga and 6 ga stainless steel for wire ties. (1) Steel Wire Ties are available in 11ga only (as far as I know), not 9ga or 6ga. I don’t think it would be possible for us to use a 6ga wire in steel to tie the fence off. Can this be clarified?
Answer: Steel Wire Ties will need to be a minimum of 6 ga or 9 ga. 11 ga is also acceptable.
4.28. Question: Is fencing required to utilize domestic steel? ASTM F1043 and ASTM F1083 is usually the indicator for Domestic Steel, but is clearly stated. The difference in cost would add ~40% if domestic steel is required
Answer: No, domestic steel is not a requirement.
4.29. Question: The Cantilever Gate is some kind of Track System. Can a manufacturer/make be provided? Currently no vendors want to quote with concerns of warranty (as system is not used in midwest climate, or outdoor applications. More used for airplane hangers or inside warehouses.
Snow, ice and debris will get in the track and cause the gate to either come out of track or be inoperable) Schedule 40 Full Weight Pipe is listed but typically will include weights per LF in the spec. This does not list weights per LF
Answer: Bid cantilever gate as shown.
4.30. Question: Looks like the Sunshades are spelled out on the drawings. May want to include the verbiage about the alternate and materials/finishes in the storefront specifications.
Answer: Sunshade finish is defined on sheet A300. Refer to Exterior Finish Schedule: Basis of Design. Sunshade color shall be: SANDSTONE to match the storefront. Bid as indicated.
4.31. Question: CS102 Note 3 says to install future conduit at gates and refer to the electrical site drawings but nothing is shown on the electrical site drawings. Please show entire pathway required for each gate including the gate in the alternate.
Answer: Provide empty 2” conduit with pull string, routed from electric room and stubbed up and capped at gate location.
Addendum 2 Page 6 of 8
4.32. Question: CS103B appears to show bollards at the alternate fence locations in the existing parking lot but they are not called out. Please confirm
Answer: Correct, the circle symbols on CS103B are bollards
4.33. Question: On the ES001 drawings, it appears the generator and transformer are shown to be installed above the sanitary sewer lines. Please confirm routing of utilities in this area.
Answer: Refer to detail 2 “Enlarged Electrical Site Plan, sheet ES001, shows sanitary line skating the edged of the concrete pad. Contractor is to coordinate exact routing of the line.
4.34. Question: Div 8 Will the wood doors need to be AWI certified and “FSC Pure”?
Answer: Refer to section 081416 FLUSH WOOD DOORS remove all sustainability requirements as follows: delete paragraph 1.2C Sustainable Design Submittals, delete item 1.2D 10, delete paragraph 1.5 Quality Assurance, delete paragraph 2.2 Flush Wood Doors and Frames, General except retain “Quality Standard: In addition to requirements specified, comply with ANSI/WDMA I.S. 1A.”.
4.35. Question: Drawing E701 shows a 1200 amp CT Cabinet. Duke Energy usually installs the
CT’s inside their transformer. Is there a need for the CT Cabinet?
Answer: If Duke installs the CTs in the transformer there is no need for the CT cabinet.
4.36. Question: Drawing E701 has a feeder schedule and key notes that references wire type to be THWN, but General Note P calls for all emergency feeders to be MI Cable. Which note is correct?
THWN for Emergency Feeders or MI Cable?
Answer: All emergency feeders feeding panelboards, transfer switch’s, etc. is required by code to be MI cable
4.37. Question: Page E507 of the plans show the following for the Photovoltaic system System A (part of the hard bid) shows 150 modules (assuming 400W) each = 150x400 is 60kW DC for the base bid.*** Kentucky state law does not allow Interconnections over 45KW DC unless the Cogeneration Application for interconnection. *** Question #1 Is CMTA / and the client expecting us to take this path for interconnect? (see comment below) Per KY state law and associated electric regulations, solar Net Metering offered by Salt River Electric is a 45kW AC maximum. For all installations greater than 45kW, the solar installation is subject to the federal PURPA law and Salt River Electric and East Kentucky Power confirming tariffs. Please utilize the link below to obtain information pertaining to your PURPA qualifying facility. Please complete the online application.
Cogeneration Applicants - Together We Save (togetherwesaveky.com)
4.38. Question: Hazardous locations in the bay areas what exactly would be the classification of those areas? What materials in those areas would be hazardous?
https://url.us.m.mimecastprotect.com/s/nYnvCPNqNvtonpwT0eI4b?domain=togetherwesaveky.com/
Addendum 2 Page 7 of 8
Answer: As indicated on sheet FX101 the bay areas are classified as: ORDINARY HAZARD. The materials in the area will be dictated by the user. There will be gasoline vapor present along with other POL’s.
4.39. Question: Seismic requirements are not applicable in Burlington area. Our standard application should suffice. Just double checking if there are more requirements for it?
4.40. Question: Names of flooring in specs does not match flooring names in plans. Specs uses LVT-1, LVT-2, LVT-3, RF-1, RF-2, and CPT-1. Plans uses MMA-1, RF-1, EPX-1, and SC-1.
Answer: Specifications for finishes shall be revised as follows:
1. Section 093013 CERAMIC TILING: at paragraph 2.3 Tile Products delete the text at item B, revise the name of item C to be “Ceramic Tile, CT-2”, and revise the name of item D to be “Ceramic Tile, CT-3”.
2. Section 096519 RESILIENT TILE FLOORING: delete this spec section entirely.
3. Section 096566 RESILIENT ATHLETIC FLOORING: delete paragraph 2.3 (RF-2 is not included).
4. Section 096813 TILE CARPETING: delete this spec section entirely.
5. Note that MMA-1 and EPX-1 are specified in section 099600 HIGH-PERFOMANCE COATINGS.
4.41. Question: Where is the location of the visual displays (markerboard and tackboard panels)?
Answer: Markerboards shall be as follows: 6 FT wide X 4 FT high, mounted 2’-4” AFF to bottom.
Provide one markerboard at the south wall of Classroom 105. Locate 6’-0” from the southwest corner.
Tackboards shall be as follows: 4 FT wide X 4 FT high, mounted 2’-4” AFF to bottom. Provide one tackboard at the west wall of Breakroom 107. Locate 4’-0” from the northwest corner.
4.42. Question: Work Benches (A571): The finish for these units is not indicated. Can this be clarified as to design intent?
Answer: Provide primer and finish coats as indicated in spec section 099123 INTERIOR PAINTING.
Primer shall conform to paragraph 2.3 E (Water-based Rust-inhibitive Primer). Finish coats shall conform to paragraph 2.4 B (Interior, Latex, Institutional Low Odor/VOC, Semigloss).
4.43. Question: Note 6 on Roof Plan A160 calls for through wall flashing to overflow scupper – reference to elevations. When looking on roof plan and elevations I don’t see scuppers call out on either. Can you advise where these are located if on project?
Answer: Overflow scuppers are shown on sheet A300 BUILDING EXTERIOR ELEVATIONS, on sheet P201 PARTIAL PLAN A – PLUMBING, and sheet P202 PARTIAL PLAN B – PLUMBING (keynote P91).
4.44. Question: Spec Section 075600-1.1 Summary Section A - Cold Applied PMMA/PMA flashings. PMMA Flashings are for BUR and SBS membrane products not EPDM membrane products, is this applicable? Does not seem that a roof assembly with BUR or SBS sheets are on the project
Addendum 2 Page 8 of 8
4.45. Question: Detail 8/A161 calls for Multi-purpose flashing cement. This will eat through the EPDM membrane and should only have Bonding adhesive in this location per manufacturer. Is this referring to flashing cement as bonding adhesive in these locations?
4.46. Question: In regards to site access, during the site walkthrough it was indicated from the folks at the walk through that construction traffic was expected to come off Gateway Blvd., across their north lot, through the secured rear lot (wit with a GC supplied temporary fence separating traffic from secured area – they mentioned moving items to within the secure area), and utilizing the drive that exists in the construction area. This would be extremely ideal for the project and also reduce risk of track out / construction traffic on Conrad. If we utilize rear of site, the track out would be knocked off for the most part prior to leaving site. Looking to clarify this and the virtual meeting seemed to not exactly clarify.
Answer: Refer to revised sheet CE101 EPSC Plan West.
4.47. Question: Provide Specification for the site flagpoles
4.48. Question: 055000 Does not mention the steel work benches and POL tables in the warehouse. Are these Contractor Furnished/Contractor installed. If so, do they get painted?
4.49. Question: The site flammable storage and controlled waste buildings are not shown on the ESS drawing. Please do so and provide proposed conduit routing for their services.
4.50. Question: See below for questions regarding air barrier at the outbuildings and roof parapet detail.
4.51. Question: There is an existing retaining wall where the new retaining wall is proposed to be built. Do we demolish the old to build the new? If so, how big is footer and how much goes underneath existing road?
END OF ADDENDUM
Burlington FMS Construction Documents – August 6, 2024 Commonwealth of Kentucky Account# 095CABPBR0400 CMTA Project VBNF22
CONTROL - DIRECT DIGITAL (WEB BASED) 250400 - 1
SECTION 250400 - CONTROL - DIRECT DIGITAL (WEB BASED)
PART 1 – GENERAL:
1.1 The controls system for this project shall be a web-based digital controls system. All controllers, control interface hardware, services, installation, warranty, training, etc., shall be included as hereinafter specified. The system shall utilize a network controller and unitary" type controllers. Including such minor details not specifically mentioned or shown, as may be necessary for the complete operation of the system.
1.2 The Temperature Control Contractor (TCC) shall furnish all labor, materials, equipment, and service necessary for a complete and operating Building Automation System (BAS), utilizing Web Based Direct Digital Controls. All labor, materials, tools, equipment, software, software licenses, software configurations and database entries, interfaces, wiring, tubing, installation, labeling, engineering, calibration, documentation, samples, submittals, testing, commissioning, training services, permits and licenses, transportation, shipping, handling, administration, supervision, management, insurance, temporary protection, cleaning, cutting and patching, warranties, services, and items, even though these may not be specifically mentioned shall be included for the complete, fully functional and commissioned temperature controls system.
1.3 The TCC shall provide all items, articles, materials, devices, operations, or methods listed, mentioned, or scheduled on the drawings including all labor, materials, equipment, and incidentals necessary and required for their completion to provide a complete and operating temperature control system. This will include connecting to any mechanical equipment furnished with a control interface device and contacting the equipment suppliers and/or manufacturers for information for the proper interface to the equipment being furnished.
1.4 These apparatus' shall consist of, but not limited to, all necessary thermostats, sensing devices, valves, automatic dampers, damper motors, actuators, (except automatic dampers, valves, and damper motors furnished with HVAC equipment), and with the necessary accessories for the complete control of all equipment hereinafter specified.
1.5 Control sequences are specified within the drawings. Provide all control equipment required to perform sequences described. Coordinate all dampers with the sheet metal contractor and equipment provider. It is the responsibility of the control contractor to ensure all required dampers in the sequence of operations are provided.
1.6 Include all power wiring and cabling for the operation of the controls system. Refer to
Electrical Division Specifications for additional requirements.
1.7 Manufacturer’s: Alerton, Automated Logic, and Siemens. These TCCs/manufacturers have prior approval with the Owner and Engineer and are the only allowed suppliers and/or installing TCCs.
1.8 The TCC shall have an established working relationship with the control manufacturer of not less than five years and shall have prior approval from the Owner and Engineer and are the only allowed suppliers and/or installing contractors. The TCC shall have a local office within
CONTROL - DIRECT DIGITAL (WEB BASED) 250400 - 2
100 miles of the project site and provide service and/or replacement parts within a 24 hour notification of a control failure.
1.9 A mandatory pre-installation meeting shall occur prior to the TCC beginning any work on site. This meeting shall be attended minimally the prime contractor, mechanical contractor superintendent, TCC superintendent, Engineer, Owner, and Architect. The purpose of the meeting is to have the controls installer communicate their understanding of the system design and how the system is intended operate to the Engineer and get the Engineer’s input and agreement. The agreement between the TCC and the mechanical engineer is to be thoroughly documented by the TCC for later reference.
1.10 The installation shall comply with the Local Authorities and State Fire Marshal code requirements, including normal operating and smoke mode functions (where applicable).
The installation shall comply with the requirements of the NEC, NFPA, UL and the Building Codes, including referenced mechanical, electrical, energy codes, etc.
1.11 Abbreviations
• TCC – Temperature Control Contractor
• CEMCS-Central Energy Management and Control System
1.12 The TCC shall list the following cost breakdowns, material, and labor, on the official project schedule of values:
• Controls shop drawings
• Controls graphics
• Controls materials and labor
• Controls conduit material and labor
• Controls startup, commissioning, testing, documentation
• Controls training and Owner acceptance
• Test and Balance assist
• Commissioning assist
PART 2 – GENERAL SYSTEM REQUIREMENTS:
2.1 All labeling for this system shall utilize actual final room names and numbers. The room names and numbers on the Contract Documents may not be the Owner’s exact requirements. Coordinate with the Owner to ensure compliance.
2.2 Include in the bid for the Controls Contractor to perform additional 40 on-site hours of on-site programming, adjustments, modifications, etc. as requested by the Engineer during the warranty period after the date of substantial completion for the project.
2.3 All points of user interface shall be on standard PCs that do not require the purchase of any special software from the control’s manufacturer for use as a building operations terminal.
The primary point of interface on these PCs will be a standard Web Browser.
2.4 The intent of this specification is to provide a peer-to-peer networked, stand-alone, distributed control system integrated utilizing ANSI/ASHRAE Standard 135-2001 BACNet, OBIX TCP/IP, MODBUS, OPC, and other open and proprietary communication protocols in one open, interoperable system
CONTROL - DIRECT DIGITAL (WEB BASED) 250400 - 3
2.5 The TCC shall connect to any mechanical and electrical (power monitoring) equipment furnished with a control interface device. The TCC shall contact the equipment suppliers and/or manufacturers for information for the proper interface to the equipment being furnished. All points not provided with the equipment control interface are the responsibility of the TCC.
2.6 The operating system shall be based on a distributed control system in accordance with specifications. All building controllers, application controllers and all input/output devices shall communicate via BACnet MS/TP or BACnet over Arcnet 156 communication protocol.
Network controller shall communicate via BACnet over Ethernet (IP).
2.7 The TCC contractor shall provide access to the system from a location determined by the
Owner and from the Consulting Engineer’s office (CMTA, Inc.). This shall include remote access requirements, set-up, passwords, and any software necessary to access the BAS system.
2.8 The TCC shall all have access to various types of WEB browsers (i.e., Netscape, IE, etc.), which shall be included for access to the Direct Digital Control (DDC) system via the Owner’s Wide Area Network (WAN) and/or Local Area Network (LAN).
2.9 The TCC shall be responsible for coordination with the Owner’s IT staff to ensure that their system will perform in the Owner’s environment without disruption to any of the other activities taking place on that WAN/LAN.
2.10 Operator workstation software, project-specific software, graphic software, database software, and firmware updates which resolve known software deficiencies as identified by the TCC shall be provided and correctly installed at no charge during the warranty period
PART 3 – SPECIAL PROJECT REQUIREMENTS
3.1 The bid for Temperature Controls for this project shall include an allowance of $20,000
(material and labor) for the owner selected contractor to fully integrate the new temperature controls system for this project into the existing Automated Logic Web control server/front-end system. The building control system specified herein shall communicate with the BACnet IP protocol. Interface and graphics generation on the system server is included in the allowance.
3.2 The allowance also includes the following scope of work: (1) scheduling, (2) trending, (3) color graphics, (4) alarming and email notifications, (5) 8 hours of front-end training, (6) start-up/commissioning their work scope.
3.3 It will be the responsibility of the TCC allowance contractor to implement this project onto the Web Control Server at the Boone National Guard Center maintenance services office with no damage to the existing projects. Any computer connected to the WAN, utilizing a web browser, and having the proper password shall be able to communicate with the Owner’s DDC system.
CONTROL - DIRECT DIGITAL (WEB BASED) 250400 - 4
3.4 All new software, graphics, terminology, operation, trending, scheduling etc. is to match any existing systems and any changes needed to accomplish this will be the responsibility of the TCC allowance.
3.5 All new Bacnet IP points shall be compliant with the nomenclature as directed for the
CEMCS program. Coordinate with the TCC contractor.
3.6 If the TCC allowance contractor needs to update or revise any of the existing software, to allow their software to operate seamlessly with the Owner’s existing server, it will be completed by the TCC allowance contractor as a part of this contract.
3.7 Provide licensed electronic copies of all server software. This includes but is not limited to:
project graphic images (editing/modifying/creating), project database, trouble-shooting and debugging programs, project-specific programming code and all other software required to operate and modify the programming code (including software at system level, primary control units, secondary control units, and all communication software).
PART 4 – SUBMITTALS:
4.1 The TCC shall not start the project installation until the shop drawing submittals have been reviewed by the Engineer.
4.2 Submittals shall include hardware, end devices, ancillary control components, a written operating sequence, unitary control wiring, building floor plans showing communication cabling and labels as well as logic flow diagrams. All submittals shall be provided on paper and electronically in PDF format.
4.3 Submittals shall contain one control drawing per specified system and equipment. Drawing shall include point descriptors (DI, DO, AI, AO), addressing, and point names. Each point names shall be unique (within a system and between systems). For example, the point named for the mixed air temperature for OA #1 and OA #2 shall not be MAT but should be named OA#1MAT and OA#2MAT. The point names should be logical and consistent between systems and AHU’s. The abbreviation or shorthand notation (e.g., MAT) shall be clearly defined in writing by the TCC. Coordinate the nomenclature as directed for the CEMCS program.
4.4 Control diagrams shall identify: System being controlled (attach abbreviated control logic text, all digital points, analog points, virtual points, all functions (logic, math, and control) within control loop, legend for graphical icons or symbols, definition of variables or point names and detailed electric connections to all control devices and sensors.
4.5 Points list shall include all physical input/output. Points list shall be provided in both hard copy and in electronic format and shall include Name, address, engineering units, high and low alarm values, and alarm differentials for return to normal condition, default value to be used when the normal controlling value is not reporting, message and alarm reporting as specified, identification of all adjustable points and description of all points.
4.6 Submittals shall contain floor plans depicting DDC control devices (control units, network devices, LAN interface devices, and power transformers as well as static pressure sensor in
CONTROL - DIRECT DIGITAL (WEB BASED) 250400 - 5
duct and temperature sensors in rooms) in relation to mechanical rooms, HVAC equipment, and building footprint.
4.7 Submittals shall contain DDC system architecture diagram indicating schematic location of all control units, workstations, LAN Interface devices, gateways, etc. Indicate address and type for each control unit, Indicate protocol, baud rate, and type of LAN per control unit.
4.8 Electrical wiring diagrams shall include motor start, control, and safety circuits and detailed digital interface panel control point termination diagrams with all wire numbers and terminal block numbers identified. Indicate all required electrical wiring. Provide panel termination drawings on separate drawings. Clearly differentiate between portions of wiring that are existing, factory-installed and portions to be field-installed.
4.9 Show all electric connections of the controls system to equipment furnished by others complete to terminal points identified with manufacturer’s terminal recommendations.
4.10 TCC shall provide one complete drawing that shows the control-wiring interface with equipment provided by others.
4.11 Submittals shall include project specific graphic screens for each system including a picture of the screen with a list of the variables to be placed on the screen.
4.12 Submittals shall include TCC’s hardware checkout sheets and test reports.
4.13 Submittals shall include the agenda for approval by the engineer and owner of the specified training periods. See training section for requirements.
4.14 Provide complete panel drawings that are:
• Clearly labeled and schematic or drawn to scale.
• Show the internal and external component arrangement so that the operators can identify the components by their position if the labels come off.
• Wiring access routes shall also be identified so that Class 1 wiring is separated from Class 2 and 3 and so high voltage wiring is segregated from low voltage wiring.
• Complete identification of all control devices (manufacturer’s type, number, and function).
• Provide details for labeling all wiring, control devices, and controllers.
• Material and equipment descriptive material such as catalog cuts, diagrams, performance curves, and other data to demonstrate conformance with specifications shall be provided.
4.15 Include room schedule including a separate line for each terminal unit, heat pump, etc.
indicating location and address.
4.16 Include control valve schedules including a separate line for each valve provided under this section and a column for each of the valve attributes: code number, configuration, fail position, pipe size, valve size, body configuration, close-off pressure, capacity, valve Cv, design pressure, and actuator type.
CONTROL - DIRECT DIGITAL (WEB BASED) 250400 - 6
4.17 Include control damper schedule including a separate line for each damper provided under this section and a column for each of the damper attributes, including code number, fail position, damper type, damper operator, duct size, damper size, mounting, and actuator type.
PART 5 – O&M MANUALS AND CLOSEOUT DOCUMENTS:
5.1 Refer to Mechanical Specification Section – REQUIRED SHOP DRAWINGS, ETC. for additional requirements.
5.2 Operating instructions, maintenance procedures, parts and repair manuals shall be supplied. Repair manuals shall include detailed instructions in the setup, calibration, repair, and maintenance of all equipment furnished. Also supplied with these manuals will be a complete parts listing of all devices supplied which is to include part numbers and model numbers of all parts and component parts along with exploded views of devices.
5.3 All as built drawings (wiring diagrams, flowcharts, floor plans, etc.) shall also be supplied to the owner electronically in PDF format.
5.4 System specific wiring, control diagrams, sequence of operation and points lists shall be as installed in each control panel. This means as-built drawings, not design (submittal)
5.5 Supply all software necessary for configuration of, modification, editing or communicating to any of the unitary devices. Software shall be capable of uploading and down-loading the entire unitary data base or any part of the automated system for backup or archiving.
5.6 Supply one copy of the software programming manual (hard copy and PDF format). The manual shall describe all furnished software. The manual shall be oriented to programmers and shall describe calling requirements, data exchange requirements, data file requirements, and other information necessary to enable proper integration, loading, testing, and program execution.
5.7 Provide a Bill of Materials with each schematic drawing. List all devices/equipment and match to schematic and actual field labeling. Provide quantity, manufacturer, actual product ordering number, description, size, accuracy, operating ranges (voltage, temperature, pressure, etc.), input/output parameters, etc.
5.8 Maintenance manual shall include copies of signed-off acceptance test forms, commissioning reports, start-up reports, etc.
5.9 The TCC shall turn over to owner two (2) sets of computerized back-ups of the complete temperature control system.
PART 6 – WARRANTY & SOFTWARE LICENSES:
6.1 Labor and materials for the control system specified shall be warranted free from defects for a period of 24 months after substantial completion and acceptance. Control system failures during the warranty period shall be adjusted, repaired, or replaced at no additional cost or
CONTROL - DIRECT DIGITAL (WEB BASED) 250400 - 7
reduction in service to the Owner.
6.2 The TCC shall respond to the Owner's request for warranty service within 24 hours during normal business hours. The TCC shall respond to the Owner's request for Emergency service (defined as life-threatening or creating the potential to cause property damage) during the warranty period within 4 hours.
6.3 The TCC shall provide technical phone support to the owner during the warranty period for warranty related issues and for two years after the warranty period. If the technical support location of the TCC is outside of the toll free calling area for the customer, the TCC shall have a toll free number or accept collect calls for the purpose of providing technical support.
6.4 During the warranty period, standard parts for the DDC system shall arrive at the facility within 48 hours of placing an order. Non-standard parts (requiring re-manufacturing or ordering from another supplier) shall be shipped within 96 hours.
6.5 Project-specific software, database software, and firmware updates which resolve known software deficiencies as identified by the TCC shall be provided and correctly installed at no charge during the warranty period.
6.6 Provide licensed electronic copies of all software for each network controller, workstation, and laptop. This includes but is not limited to project graphic images (editing/modifying/creating), project database, trouble-shooting and debugging programs, project-specific programming code and all other software required to operate and modify the programming code (including software at system level, primary control units, secondary control units, and all communication software). Any hardware devices (cables, protection devices) required to operate the software/hardware shall also be provided.
6.7 If Tridium network control products are utilized the owner shall hold the software and firmware Tridium licensing. Software license shall not expire or utilize any sort of protection hardware device for its use. This is to include the following the Niagara Compatibility Statement (NiCS) for all network controllers and unitary controllers shall allow open access and set as follows:
Accept Station In = All Accept Station Out = All Accept Tool In = All Accept Tool Out = All
6.8 In any case owner shall be free to direct the modification of any software license, regardless of supplier, to allow open access to all controllers.
6.9 All additional licensing needed for this project shall be supplied by TCC. Software license shall not expire or utilize any sort of protection hardware device for its use. In any case owner shall be free to direct the modification of any software license, regardless of supplier to allow open access to all controllers. Owner shall hold the software and firmware licensing. Software license shall not expire or utilize any sort of protection hardware device for its use.
6.10 System software shall be the latest version available with upgrades provided at the end of the warranty period and shall be fully licensed to the Owner for the entire system. Supply all
CONTROL - DIRECT DIGITAL (WEB BASED) 250400 - 8
software necessary for configuration of, modification, editing or communicating to any of the unitary devices. Software shall be capable of uploading and down-loading the entire unitary data base or any part of the automated system for backup or archiving. Software shall be "IBM compatible".
PART 7 – TRAINING:
7.1 A formal on-site "Hands On" training session shall be conducted for the owner's maintenance personnel. This session shall be a minimum of one (1) eight (8) hour days to train the staff on setup, operation, and maintenance of all system(s) and/or devices. This will be at a time and location selected by the owner. One (1) additional eight (8) hour session shall be provided as “opposite season” training – generally 6 months into the warranty period. One (1) additional eight (8) hour session shall be provided at a later date.
(This may be requested any time during the warranty period.) All training materials and books shall be provided. Both sessions shall be given by the manufacturers "factory" technical representative. (This is defined as someone other than the installing contractor’s representative.) All expenses are to be provided by the TCC. All training sessions shall be scheduled at owner’s request.
7.2 TCC shall conduct training courses for designated personnel in operation and maintenance of system. Training shall be oriented to specific system being installed under his contract and shall be digitally recorded and submitted on DVD by the TCC.
7.3 Training shall be a mix of, test exercises, and actual keyboard entry and screen viewing at the operator’s terminal. A curriculum shall be discussed and implemented based on the level of expertise of the employees. Hands-on experience and problem solving shall be emphasized.
7.4 If during any training session, the trainer/owner finds more than three (3) items that need repair, the training session will be immediately terminated. The session will be rescheduled for another date. The re-scheduled training session will be carried out at no additional cost to the Owner.
7.5 The training shall be oriented to making the owner self sufficient in the day-to-day use and operation of the DDC system.
7.6 Additionally, the training shall include:
• System start-up, shutdowns, power outage and restart routines, alarms, security levels, changing setpoints, changing schedules and other parameters, overrides, freeze protection, manual operation, return to automatic operation, and resetting equipment.
• All screens shall be discussed, allowing time for questions.
• Information specifically focused on showing the owner methods of troubleshooting the mechanical systems using the DDC.
• Use of laptop and hand-held operator interface device, if applicable.
• Creating, modifying, viewing, downloading, and reloading, trend logs.
• Remote access to the system.
• The other training sessions shall be oriented toward answering specific questions from Owner’s staff.
• The trainer must be well grounded in both DDC system operation and in mechanical
CONTROL - DIRECT DIGITAL (WEB BASED) 250400 - 9
systems service and shall be the programmer.
PART 8 – COMMISSIONING & VERIFICATION, FUNCTIONAL PERFORMANCE TESTING &
CHECKLISTS:
8.1 100% compliance with the requirements of this section is a condition of the Owner’s acceptance and start of the warranty period.
8.2 The TCC shall be responsible for completion of (1) their hardware checkout sheets and test reports, (2) Point-by-point confirmations of ALL points – this includes visual inspection of installed components, and (3) sequence of operation confirmation.
8.3 This documentation and process shall be complete, approved and accepted by Engineer and Owner prior to acceptance. This information shall be documented as completed. A copy shall be delivered to the Engineer and Owner and included in the O&M manuals. Each subcontractor shall be responsible for completion of their own System Verification Checklists/Manufacturer’s Checklists. Sample checklists shall be submitted to the Engineer and Testing Agent for approval.
8.4 Air and water balancing shall be completed (and discrepancies resolved) before the TCC’s final system check and before the acceptance test to be conducted in the presence of the Engineer.
8.5 Refer to Mechanical Specification Section – GENERAL PROVISIONS for additional information and requirements.
PART 9 – WIRE MANAGEMENT, ELECTRICAL POWER, ETC:
9.1 Refer to CABLING section of this specification for additional requirements.
9.2 Electrical work required for system interlock and installation of the temperature control system shall be included in the bid and installed per all applicable codes. Coordinate with other trades as required for installation of a complete system.
9.3 All wiring and cabling in mechanical and electrical rooms shall be in conduit. No wiring or conduit can be exposed to view in any other area. Conceal all wiring and cabling in conduit in wall from thermostats or other controls devices to above ceiling. Install conduit in wall from wall thermostats to above ceiling for cabling. Route wiring directly to cable tray from control points above the ceiling. Rough-in for control devices shall be in compliance with the requirements of the ELECTRICAL SPECIFICATIONS.
9.4 Any power for controls shall be fed from dedicated circuits in emergency electrical panels, when provided for a project, and shall not be obtained from receptacles, lighting, or equipment circuits. Unitary control power may be obtained from the equipment served. If power is obtained from the equipment served, the power may not be interrupted to the electronics if the equipment is off for any reason.
9.5 The TCC shall be responsible for the power source to any control panels, unitary controllers, etc. on any controlled equipment and all other control power requirements. This includes circuit breakers, wiring, conduit, etc. installed in strict accordance with NEC. The TCC may
CONTROL - DIRECT DIGITAL (WEB BASED) 250400 - 10
contract with the electrical contractor for the power wiring installation.
9.6 Prior to installation, insure through coordination with all trades, that appropriate clearances (36” minimum) as required by the N.E.C. are maintained at all control panels, including unitary controllers for VAV terminals, heat pumps, etc.
9.7 The TCC shall provide all CAT6 cabling network cabling for a complete system. This shall include cabling to the Owner’s data drop. The main system data drop will be provided by others.
9.8 All control circuits within the electrical panels shall be marked to indicate equipment served.
9.9 The TCC shall perform all temperature control interlock wiring. This shall include control valves, dampers, thermostats, indoor/outdoor HVAC systems, etc. Electrical work required for system interlock and installation of the temperature control system shall be included in the bid and installed per all applicable codes. Coordinate with other trades as required for installation of a complete system.
9.10 The TCC shall be responsible for any power required for the unitary controls or control panels. This includes circuit breakers, wiring, conduit, etc. installed in strict accordance with NEC. The TCC may contract with the electrical contractor for the power wiring installation.
9.11 Provide one duplex outlet mounted inside the control panel and separately fused with a non-time delay fuse at 15 A at any panel location containing electronic control components. This receptacle may be served from the control panel 120 VAC power source.
9.12 All wiring shall be continuous runs. Any junctions must be made in metal enclosure.
9.13 Grounding terminals shall be color coded green and yellow and shall be compatible with the other specialty terminals specified above and shall mount on the same DIN rail system.
Units shall be arranged so that the wiring connected to them is grounded to the enclosure via the mounting rail. These terminals shall be provided for grounding cable shields at the points where the cables enter a control panel and terminate on the control panel terminal strip. Terminals shall be Entrelec M 4/5.3A. PI or equivalent by Weidmuller, Phoenix, or Allen Bradley.
9.14 The Department of Housing, Building and Construction’s Electrical Division requires that all new lighting control panels, new Building Automation Systems control panels, and new conventional HVAC control panels be certified as being constructed and wired in accordance with NFPA 70 110.3 (a) (1) and article 409.
9.15 Contractor shall insure control panels have an identification label stating the “Certification
Agency” such as UL, CSA, CE, etc. or a label of certification for each control panel by a Professional Engineer (P.E.) registered in the State of Kentucky, stating that the design of the control panel was under their direct supervisory control. Include with shop drawings.
9.16 The Electrical Advisory Council for the State of Kentucky requires that only an electrical contractor licensed by the State of Kentucky with a licensed Master Electrician and a licensed on-site electrician can install the electrical wiring for lighting controls systems or Building Automation Systems (BAS).
CONTROL - DIRECT DIGITAL (WEB BASED) 250400 - 11
PART 10 – CABLING:
10.1 Refer to WIRE MANAGEMENT section of this specification for additional requirements.
10.2 ALL CONTROL WIRING SHALL BE INSTALLED IN A WIRE MANAGEMENT SYSTEM TO
INCLUDE CABLE TRAYS, BRIDLE RINGS, & CONDUITS. NO EXCEPTIONS!
COORDINATE WITH ELECTRICAL CONTRACTOR TO INSURE A COMPLETE WIRE
MANGEMENT SYSTEM.
10.3 Acceptable cable manufacturers are Belden, West Penn, or Alpha.
10.4 All TCC cabling shall be green or white with a green stripe. “No Exceptions!”
10.5 A complete cabling system shall be furnished and installed, which shall adhere to the highest workmanlike standard of quality and appearance. Cabling shall be installed square with building lines and contained within a wire management system.
10.6 All sizing of cabling shall be according to manufacturer’s recommendations but shall be a minimum of 18 AWG for devices and 22AWG for communication cabling.
10.7 Furnish a floor plan of the building indicating communication cable labeling and routing as well as addresses and branch wiring from the unitary devices. All cabling shall be labeled on both ends.