This Addendum No. 1 is issued by the Pennsylvania Game Commission for Solicitation No. 6100066764, Project PGC-SGL-139-2026, pertaining to demolition and debris removal services at State Game Lands 139. The solicitation seeks lump-sum bids for complete demolition and removal of structures, vehicles, debris, and site restoration at the Handschin property in Bucks County. Bids are due November 20, 2026, at 2:00 PM, with a mandatory site inspection scheduled for November 6, 2026. The contract term begins upon receipt of the approved Purchase Order and performance bond, with work commencing January 4, 2027, and all work required to be completed by June 30, 2027.
Addendum No. 1 introduces significant pricing modifications regarding asbestos abatement and removal. The Pennsylvania Game Commission will conduct an asbestos determination at no cost to the vendor following bid opening. All bidders must submit unit pricing on a per-ton basis for the abatement and removal of forty tons of suspect asbestos material. This unit pricing establishes the cost structure for any asbestos removal activities identified during the project; vendors will be compensated only for actual asbestos abatement and removal work performed. A performance security bond of $1,500 is required, along with comprehensive insurance coverage including Workers' Compensation and General Liability Insurance with minimum limits of $300,000 per occurrence for bodily injury and property damage, naming the Commonwealth as an insured party. Contractors must certify compliance with all applicable Pennsylvania labor, workforce safety, and prevailing wage statutes.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| TermsConditions.pdf | ||
| GSPUR-89 Reciprocal_Limitations_Act_Reqirements.docx | DOCX document | |
| Worker Protection Form .docx | DOCX document | |
| SGL 139 Demolition Project Bid Packet.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
May 2, 2025
SOLICITATION NO. 6100063516
WHM - PGC-HQ-25-01
ADDENDUM NO. 1
COMMONWEALTH OF PENNSYLVANIA
PENNSYLVANIA GAME COMMISSION
November 6, 2026
ADDENDUM NO. 1
SOLICITATION NO.
6100066764
PROJECT:
PGC-SGL-139-2026
Demolition and Debris Removal- No.1
OPENING DATE/TIME:
November 20th, 2026 2:00 PM
This Addendum is hereby made a part of Solicitation No. 6100066764. Please note the changes, information, and instructions contained herein and prepare and submit Bids accordingly.
Bids will still be received and opened on the date and time as stated in the Solicitation.
Addendum No. 1 summary of changes, information, and instructions:
General Contract No. 1
1. Asbestos: The PGC will do a determination of possible asbestos materials of the components within the scope of the demolition/debris removal project, at no cost to the vendor. This determination will occur post bid opening. All bidders are encouraged to anticipate some level of abatement activity and removal of asbestos to approved disposal sites.
2. All bidders will be asked to submit their unit pricing for abatement and removal of 40 (forty) tons of suspect material. This unit pricing will be used to establish a price point for removal of asbestos material. If no asbestos is found, these activities will not be paid to the vendor. All asbestos abatement and removal costs should be included in these bid line items on a per ton basis. The vendor will be paid for any applicable abatement and removal of asbestos material on a per ton unit.
Any questions concerning this project should be directed to PGC Contracts and Procurements Division at 717-787-6594.
Thank you, Austin Kieffer, P.E. Chief of Engineering Bureau of Habitat Management