This is Addendum No. 6 to Invitation for Bid (IFB) 26-005-HG for the Beecher Street Sidewalk Project, issued by the City of Leesburg, Florida on February 11, 2026. The addendum modifies the original solicitation for a sidewalk construction project on West Beecher Street from Johns Avenue to the Berry Park entrance, funded through the Community Development Block Grant (CDBG). The original project scope requires a Florida-licensed certified General Contractor or certified Building Contractor to construct a 5-foot wide, 4-inch thick sidewalk (6 inches at vehicle crossings) with ADA-compliant curb ramps and detectable warning strips. The addendum establishes material separation requirements, concrete specifications, surveying and documentation standards, dust control measures, clearing and site cleanup protocols, and traffic management and temporary traffic control (TTC) requirements. All bidders must acknowledge receipt of this addendum on their Proposal Bid Form, with the submission of a bid constituting acknowledgment of receipt.
The addendum specifies pricing for roll-off containers ranging from $225.00 for 20 cubic yards to $400.00 for 40 cubic yards and establishes concrete mix requirements of 3,000 PSI with fiber reinforcement and 10-foot expansion joints. Concrete placement must be continuously supervised until fully set, with vandalism occurring before full concrete set being the contractor's responsibility to repair at their own expense. Material separation requirements mandate that organics and soils be placed together in one container while concrete waste and construction debris are placed in a separate container. Additional requirements include submission of certified payroll documentation, as-built records upon completion, dust control measures throughout construction, proper securing of exposed hazards including stakes, forms, and rebar with barricades, caution tape, and warning signs, and submission of a MOT plan for approval prior to construction. Traffic lane closures are prohibited one hour before and after school intake and discharge times, and all contractors must hold Intermediate TTC/MOT Certification or engage a certified subcontractor. Water service from the City of Leesburg Water Distribution Department is available at a $50 deposit plus a $50 service fee and usage charges.
View the file
Other files
Show all 15
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DATE: February 11, 2026 TO: All Interested Bidders and Other Interested Parties FROM: Lissandra Kmoch, Buyer
The City makes the following changes, additions, deletions, information, and/or clarifications and now considers the addendum a part of the IFB Document. Bidders must acknowledge receipt of this addendum by indicating receipt in the space provided on the Proposal Bid Form.
If the bidder has already submitted the Proposal Bid Form to the City’s Procurement Division, the Bidder should revise their electronic submission to include this addendum. In any case, the submission of a bid is an acknowledgment of receipt of the addendum. The City will construe all bids received as though the Bidder has received and acknowledged the addendum.
The following information is hereby made part of the solicitation.
1- Roll Off Containers
• 20 cubic yard container: $225.00
• 30 cubic yard container: $312.50
• 40 cubic yard container: $400.00
2- Material Separation Requirements
To comply with City of Leesburg Solid Waste Department guidelines.
• Debris May not be mixed.
• Organics and soils must be placed together in one container only.
• Concrete waste and construction debris must be placed together in a separate container.
Proper separation ensures compliance with disposal regulations and prevents contamination fees.
3- Certified Payroll
Contractor must provide certified payroll documentation in accordance with project and regulatory requirements.
IFB 26-005-HG
Beecher Street Sidewalk Project (CDBG)
Addendum No. 6
4- Surveying Layout and Documentation
• Sidewalk layout and survey must be completed prior to construction.
• Contractor must provide as-built records upon completion.
• Right-of-way maps and plats must be referenced and followed.
5- Concretes Requirements
• Concrete mix shall be 3,000 PSI with fiber reinforcement.
• All load tickets must be submitted to Tim Smith.
• 10' expansion joints must be saw-cut as required.
• Inspections include:
o Layout and forms o Final inspection
6- Dust Control
Appropriate dust control measures must be in place at all times during construction activities.
7- Clearing, Grubbing, and Site Clean-Up
• Contractor is responsible for project clean-up, including removal of debris, dirt, and organic matter.
• Organic material must be separated from all other debris or waste.
• No hazardous or unsafe conditions may be left on-site, including:
o Exposed stakes o Open forms o Vertical rebar
• All exposed hazards must be secured with:
o Barricades o Caution tape o Warning signs
8- Concrete Placement Supervision
• All poured concrete must be continuously supervised until fully set.
• Any vandalism occurring before concrete has set is the contractor’s responsibility to remove and replace at their own expense.
9- MOT and TTC Requirements
• No street or travel lane closures may occur 1 hour before school intake or 1 hour after school discharge.
• Any blocked travel lane must have:
o A detour, or o Flaggers present at all times.
• A MOT plan must be submitted for approval.
• Contractor must hold an Intermediate TTC/MOT Certification, or the MOT/TTC plan must be submitted by a certified subcontractor.
• All MOT/TTC equipment must be MUTCD-approved.
10- Concrete Washout and Waste
• Concrete washout berms must be used.
• All concrete waste must be disposed of in accordance with project and environmental requirements.
11- Water Usage – Fire Hydrant Access
Water is available from the City of Leesburg Water Distribution Department.
• $50 deposit
• $50 service fee
• Service Fee + Usage charges
ACKNOWLEDGMENT - Addendum No. 6
Company Name
Signature of Officer
Type/Print Officer's Name & Title
File details come from the government source that posted it. Updated .