This document is an Addendum to a Request for Proposals (RFP) issued by the Minnesota Department of Natural Resources (DNR) for the Root River State Trail Houston Area Bank Stabilization project. The DNR is seeking consulting firms to provide final plans, specifications, and technical services during construction to stabilize and reconstruct the riverbank along the Root River State Trail north of Houston in Houston County. The Addendum addresses a question from a prospective respondent regarding the Army Corps of Engineers 404 permitting process, with the DNR clarifying that the design consultant will complete the required wetland forms and documents in consultation with the DNR.
The contract opportunity has been posted on the state procurement system, with Addendums 1-4 attached. The project will be located in Isanti County, Minnesota. No further details on pricing, set asides, incumbents, funding, or other salient information are provided in this Addendum.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Root_River_State_Trail_Bank_Stabilization.pdf | ||
| Sample_Contract.docx | DOCX document | |
| ATTACHMENT_C.docx | DOCX document | |
| RFP_Attachments.docx | DOCX document | |
| Addendum__1.docx | DOCX document | |
| Addendum__2.docx | DOCX document | |
| RFP_Root_River.docx | DOCX document | |
| Addendum__3.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Proposals (RFP) Addendum #04 SWIFT Event #: 2000016401 Agency: Department of Natural Resources Addendum Number: 04 Date of Addendum: November 18, 2024 Title: Root River State Trail Houston Area Bank Stabilization
SCOPE OF ADDENDUM
The following is a question the State received for the subject RFP and the State’s answers.
1. Question: Is the selected design team required to undergo the army corps of engineers 404 permitting process or is the DNR?
A. Answer: The design consultant will complete the required wetland forms and documents with consultation from the DNR.