This document is an Addendum to a Request for Proposals (RFP) issued by the Minnesota Department of Natural Resources (DNR) for the Root River State Trail Bank Stabilization project in Houston County. The addendum addresses questions received from vendors regarding the project, including the availability of a 2021 Preliminary Engineering Report (which does not exist) and whether the project will require trail design (it will not, as the existing trail will not be relocated or altered). The overall project involves providing final plans, specifications, and technical services during construction to stabilize and reconstruct the riverbank along the Root River State Trail north of Houston.
The contract opportunity is open to consulting firms, with no indication of set-asides or incumbents. Funding requirements and sources are not specified, but the project is being managed by the DNR's Operations Services Division and Parks and Trails Division.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Root_River_State_Trail_Bank_Stabilization.pdf | ||
| Sample_Contract.docx | DOCX document | |
| ATTACHMENT_C.docx | DOCX document | |
| RFP_Attachments.docx | DOCX document | |
| Addendum__2.docx | DOCX document | |
| Addendum__4.docx | DOCX document | |
| RFP_Root_River.docx | DOCX document | |
| Addendum__3.docx | DOCX document |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Request for Proposals (RFP) Addendum #01 SWIFT Event #: 2000016401 Agency: Department of Natural Resources Addendum Number: 01 Date of Addendum: November 12, 2024 Title: Root River State Trail Houston Area Bank Stabilization
SCOPE OF ADDENDUM
The following are questions the State received for the subject RFP and the State’s answers.
1) Vendors’ questions to the RFP and the State’s answers are as follows:
1. Question: Can the DNR provide the 2021 Preliminary Engineering Report?
A. Answer: There is no 2021 Preliminary Engineering Report for this project. The initial site visit and scoping for the project was in 2021, but no report was generated.
2. Question: Will this project be required to provide trail design to the impacted segment?
A. Answer: Design needs to include protection of existing trail, but the section of trail will not be relocated or altered from its current location.