Addendum #3
253 KB Posted
- Solicitation number
- BL046-21
- Issued by
- Gwinnett County, Georgia
About this file
This is Addendum #3 to a bid solicitation issued by the State of Georgia for above-ground pre-stressed concrete tanks inspection and repair services on an annual contract (BL046-22). The contract requires pre-qualification and calls for contractors to provide all supervision, labor, materials, tools, equipment, and incidentals necessary to complete tank inspection, maintenance, repair, and rehabilitation work. Work scope may include interior only, exterior only, or both interior and exterior services, as well as inspection only, repair only, or combined inspection and repair activities. Specific repairs will be determined by the Department of Water Resources (DWR) based on separate inspections and recommendation reports. Multiple tanks at a single site must be performed in one mobilization to minimize costs and operational disruption.
The addendum modifies the pre-qualification requirements on page 6R of the Revised PreQual Application, specifically striking language related to Requirement 2 regarding contractor similar project experiences. Contractors must demonstrate a minimum of five projects completed within the past five-year period for repair of above-ground pre-stressed tanks in accordance with AWWA D110 and/or ACI Standards. Bidders are required to acknowledge this addendum on the Bid Schedule (page 20), and failure to do so may result in the proposal being deemed non-responsive. The addendum was issued on April 20, 2022, by Shelley McWhorter, Purchasing Associate III.
Text of this file
April 20, 2022
ADDENDUM #3
ABOVE GROUND PRE-STRESSED CONCRETE TANKS INSPECTION
& REPAIR ON AN ANNUAL CONTRACT
BL046-22
Note the following changes to the above referenced bid:
• Page 6R of the Revised PreQual Application issued in Addendum #2, strikethrough the last sentence as shown below:
Requirement Met?
Requirement
2. Contractor Similar Project Experiences pass fail a) A minimum of five (5) projects completed in the past 5-year period for repair of above-ground pre-stressed tanks. per AWWA D110 and/or ACI Standards.
This addendum should be acknowledged on the Bid Schedule, page 20. Failure to do so may result in your proposal being deemed non-responsive.
Thank you.
Shelley McWhorter, CPPB Purchasing Associate III
| April 20, 2022 |
| ADDENDUM #3 |
| ABOVE GROUND PRE-STRESSED CONCRETE TANKS INSPECTION |
| & REPAIR ON AN ANNUAL CONTRACT |
| BL046-22 |
| Note the following changes to the above referenced bid: |
| Page 6R of the Revised PreQual Application issued in Addendum #2, strikethrough the last sentence as shown below: |
| Requirement |
| Requirement Met? |
| Contractor Similar Project Experiences |
| 2. |
| A minimum of five (5) projects completed in the past 5-year period |
| a) |
| fail |
| pass |
| for repair of above-ground pre-stressed tanks. per AWWA D110 and/or ACI Standards. |
| This addendum should be acknowledged on the Bid Schedule, page 20. Failure to do so may result in your proposal being deemed non-responsive. |
| Thank you. |
| / |
| Shelley McWhorter, CPPB |
| Purchasing Associate III |
Other files
| File | Type | Posted |
|---|---|---|
| Addendum #1 | — | |
| Addendum #5 | — | |
| Addendum #2 | — | |
| Addendum #4 | — | |
| Invitation to Bid | — | |
| Award Information | — |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file