Addendum 3 15262.pdf
PDF 56 KB Posted
- Solicitation number
- RFQ 171 180000000684 4
- Issued by
- Bay County, Michigan
About this file
This is Addendum No. 3 issued June 29, 2018, for a Department of Corrections facility monitoring system project at Lakeland Correctional Facility, prepared by Century A&E (Project No. MIS 025.02, File No. 472/15262.SMDG, Index No. 32501). The addendum modifies the original bidding documents dated June 8, 2018, and two prior addenda dated June 22 and June 27, 2018. The addendum clarifies demolition work responsibilities for both the Boiler Controls Contractor and the Electrical Contractor related to the existing monitoring and control panel system. The Boiler Controls Contractor is required to verify and mark all inputs, outputs, wires, sensors, and other control and monitoring points that will remain and those that will be demolished, and prepare a comprehensive list of all wires and points for coordination with the Electrical Contractor, Owner, and Engineer. The Electrical Contractor must selectively demolish portions of the existing monitoring and control panels in a phased approach, including associated controls, non-mechanical sensors, and related power and control conduit and wire, while preserving the existing panel's control of boiler feed water pumps and condensate transfer pumps.
No pricing terms, set-asides, incumbent information, or funding sources are specified in this addendum. The document consists of general clarifications and specification modifications related to work scope and contractor responsibilities for the facility monitoring system upgrade project.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum 1 15262.pdf | ||
| LEIN Request 15262.pdf | ||
| Drawings 15262 Monitor.pdf | ||
| Specs 15262 Monitor.pdf | ||
| Addendum 2 15262.pdf | ||
| Advertisement 15262.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM NO. 3
June 29, 2018
Century A&E, Project No.: MIS 025.02
RE: Department of Corrections
Lakeland Correctional Facility – Facility Monitoring System File No. 472/15262.SMDG, Index No. 32501
TO: PROSPECTIVE BIDDERS
This Addendum forms a part of the Contract Documents and modifies the original Bidding Documents dated June 8, 2018, Addenda No. 1 dated June 22, 2018 and Addenda No. 2 dated June 27m 2018 as noted below. This Addendum consists of two (2) typed pages.
GENERAL CLARIFICATIONS
1. The intent of this addenda is to clarify demolition work required by the Boiler Controls
Contractor relating to the existing monitoring and control panel. Per Addenda No. 2, the Boiler Controls Contractor was to verify and mark all inputs and outputs, wires, etc. of any control items that were to remain. Per Addenda No. 3 and as described here-in, the Boiler Controls Contractor shall verify and mark all inputs and outputs, wires, etc. of all control and monitoring points, both that will remain and that will eventually be demolished by the Electrical Contractor.
SPECIFICATIONS
1. Section 01010 – Summary of Work
a. In Paragraph II, F, 1. – Boiler Controls Contractor, delete item d. regarding demolition work and replace with the following:
d. Verify and properly mark all inputs and outputs, wires, and sensors, etc.
for the exiting control and monitoring panels. Prepare a list of all wires and points. Work with the Electrical Contractor, Owner and Engineer to verify what wires, conduit, etc. are to be demolished by the Electrical Contractor.
Addenda No.3 Thumb Correctional Facility – Facility Monitoring System File No. 472/15262.SMD, Index No. 32501 June 29, 2018
b. In Paragraph II, F, 3. –Electrical Contractor, add the words in bold below at the end of item a. relating to demolition:
a. Selectively demolish in a phased approach portions of the existing monitoring and control panels including all associated controls, non-mechanical sensors and all associated power and control conduit and wire for control and monitoring functions that will be picked up by the new SCADA panel. The existing panel will remain to control the boiler feed water pumps and the condensate transfer pumps. The Boiler Control Contractor will mark all wires, sensors, and gauges are to remain and that will be demolished. Review the list of inputs and outputs created by the Boiler Controls Contractor and selectively demolish those items that will no longer be used as verified by the Owner and Engineer.
DRAWINGS:
1. N/A
END OF ADDENDUM NO. 3
| GENERAL CLARIFICATIONS |
| 1. The intent of this addenda is to clarify demolition work required by the Boiler Controls Contractor relating to the existing monitoring and control panel. Per Addenda No. 2, the Boiler Controls Contractor was to verify and mark all inputs and outp... |
| SPECIFICATIONS |
| 1. Section 01010 – Summary of Work |
| a. In Paragraph II, F, 1. – Boiler Controls Contractor, delete item d. regarding demolition work and replace with the following: |
| b. In Paragraph II, F, 3. –Electrical Contractor, add the words in bold below at the end of item a. relating to demolition: |