Addendum 3_08-05-24.pdf

PDF 9 KB Posted

Attached to
Breckenridge Riverwalk Structures Design
Solicitation number
17-06-102-002
Issued by
Summit County, Colorado

About this file

This document is Addendum No. 3 to a Request for Proposals (RFP) issued by the Town of Breckenridge for the Breckenridge Riverwalk Structures Design project, solicitation number 17-06-102-002. The addendum, dated August 5, 2024, modifies the original RFP by changing the proposal due date to August 16, 2024 at 10:00 a.m. local time. Bidders are required to acknowledge receipt of this addendum using Attachment A of the original RFP.

The project is partially funded by the Colorado Department of Transportation (CDOT) through the Multimodal Transportation and Mitigation Option Fund, which originates from Federal ARPA funds. A Disadvantage Business Enterprise (DBE) goal of 10% has been established for the project. The design must comply with all CDOT and Town design and construction standards, and project documents will be reviewed by a CDOT representative to ensure compliance. The project aims to improve safety, accessibility, and usability of the Blue River Recreational Path in downtown Breckenridge by creating grade-separated crossings and connecting disjointed pathway sections.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Addendum to Request For Proposals 17-06-102-002 Breckenridge Riverwalk Structures Design August 5, 2024

Addendum No. 3

This addendum summarizes additions and/or changes made to the Request for Proposals (RFP).

Receipt of all addenda shall be acknowledged on the form included as Attachment A of the RFP.

The following additions and/or changes shall be made:

CHANGE IN PROPOSAL DUE DATE:

The due date of the proposals shall be changed to August 16, 2024 at 10:00 a.m. local time.