About this file

This document is Addendum #2 for the Roof Renovations project at West Virginia State University in Kanawha County, West Virginia. The addendum provides clarifications and responses to questions posed by contractors during the mandatory pre-bid conference held on July 9, 2024. It confirms that existing roof drains should not be changed to overflow drains unless field verification indicates they are not functioning properly. The addendum also clarifies that tapered insulation is not required for the entire roof where the structure provides adequate slope, and should only be used to create crickets at roof penetrations and curbs. Bids for this project are due by 2:30 PM on Wednesday, July 24, 2024.

The addendum does not provide any information about pricing terms, set asides, incumbents, funding requirements, or other salient details beyond the clarifications to the project scope. It simply addresses specific questions raised during the pre-bid conference related to the roof work requirements.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

WEST VIRGINIA STATE UNIVERSITY

KANAWHA COUNTY, WEST VIRGINIA

ROOF RENOVATIONS

ADDENDUM #2

July 17, 2024

THRASHER PROJECT #T60-11251

SOLICITATION NUMBER: ARFQ WSC24*06

TO WHOM IT MAY CONCERN:

A MANDATORY Pre-Bid Conference was held on Tuesday, July 9, 2024, on the above-referenced project. The following are clarifications and responses to questions posed by contractors for the above reference project.

A. GENERAL

1. None

B. SPECIFICATIONS

1. None

C. DRAWINGS

D. QUESTIONS AND RESPONSES

QUESTION

1. Regarding Note #11 – ORD – Could you please confirm that this is to be changed to an overflow drain – appears to be in full use as a roof drain upon field verification?

ADDENDUM #2

July 17, 2024

RESPONSE

Do not change to overflow drain if field verification confirms a roof drain.

E. CLARIFICATIONS

1. Tapered insulation is not required for entire roof where roof structure provides adequate slope. Use tapered insulation to create crickets at roof penetrations, roof curbs, etc.

If you have any questions or comments, please feel free to contact me at your earliest convenience. As a reminder, bids will be received until 2:30 p.m. on Wednesday, July 24, 2024. Good luck to everyone and thank you for your interest in the project.

Sincerely, THE THRASHER GROUP, INC.

AMANDA CHEUVRONT, AIA, NCARB

Project Manager

WVSU Roof Addendum 2.pdf
A. GENERAL
D. QUESTIONS AND RESPONSES
E. CLARIFICATIONS