Addendum 2_Submersible Groundwater Pumps.pdf
PDF 283 KB Posted
- Attached to
- Submersible Groundwater Pumps
- Solicitation number
- ITB-13655
- Issued by
- Polk County, Florida
About this file
This document is an Addendum (#2) issued by the St. Johns River Water Management District for Invitation for Bids (IFB) #41542, specifically for the Purchase of Submersible Groundwater Pumps. The addendum is dated August 27, 2025, and addresses a technical clarification regarding motor lead specifications. The bid due date remains unchanged at 2:00 p.m. on September 2, 2025, and prospective respondents are instructed to acknowledge receipt of this addendum on the provided bid form.
The addendum specifically clarifies a question about motor leads for the Grundfos GEOFlo3 submersible pump, stating that the installed motor leads must be continuous for the length specified in the cost schedule. As an example, the document references "Item #2, Grundfos GEOFlo 3 Submersible pump and 50' Jacketed Santoprene Motor lead (Installed)" which requires 50 feet of continuous motor lead without splices. Potential bidders with questions are directed to contact LaDonna Johnson, the Procurement Specialist, via email at ljohnson@sjrwmd.com.
View the file
Other files
| File | Type | Posted |
|---|---|---|
| Addendum 1_Submersible Groundwater Pumps.pdf | ||
| 41542_IFB_Submersible Groundwater Pumps.pdf |
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
DATE: August 27, 2025
TO: Prospective Respondents
FROM: LaDonna Johnson, Procurement Specialist
SUBJECT: Addendum #2 to Invitation for Bids, 41542 - Purchase of Submersible Groundwater Pumps
As a result of an inquiry received regarding the above-referenced solicitation, the following clarification is provided for your information.
Q1: Do the RediFlo 3 motor leads need to be continuous without a splice?
A1: The GEOFlo3 installed motor leads should be continuous for the length specified in the table on the cost schedule. For example: “Item # 2, Grundfos GEOFlo 3 Submersible pump and 50’ Jacketed Santoprene Motor lead (Installed)” shall have 50 ft of continuous motor lead.
NOTE: The Bid Due Date remains 2:00 p.m., September 2, 2025.
Please acknowledge receipt of this Addendum on the BID FORM provided in the bid package.
If you have any questions, please e-mail me at ljohnson@sjrwmd.com.
File details come from the government source that posted it. Updated .