About this file

This Addendum 2 was issued by Frederick Water on November 15, 2024, for the Request for Qualifications (RFQ) for the Henry F. Sliwinski WTP East Pit Advanced Treatment Project. The document addresses three questions from potential proposers regarding as-built drawings, water quality studies, and plant operations. The agency indicates that record drawings will be posted when available, and the treatability study and water quality data will be released as part of the RFP.

Regarding current operations, the document reveals that the Sliwinski WTP operates weekly but is not currently producing water for distribution. By early December, the WTP will begin treating water from Pit 2 and distributing to customers. Frederick Water plans to minimize future downtime but can utilize the Anderson WTP as needed to allow for Sliwinski WTP shutdowns. The addendum requires acknowledgment from proposers through a signed and dated form that must be included with their proposal submission.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

November 15, 2024

ADDENDUM 2

Request for Qualifications

Henry F. Sliwinski WTP East Pit Advanced Treatment Project

The following hereby amends and/or modifies the Proposal Documents and Attachments as originally issued for this project. All proposers are subject to the provision of this Addendum.

This Addendum consists of:

Change Items

Receipt of Addendum 1 must be acknowledged in the submitted Proposal. It is the Proposer’s ultimate responsibility to ensure they have all applicable Addenda prior to Proposal submittal.

This acknowledgment must be signed, dated, and included with the submitted Proposal.

Company Name Date

Signature Printed Name

QUESTIONS FROM PROPOSERS

1. Question: Please provide the as-builts for the existing facility/project.

Response: Record drawings will be posted when they are available.

2. Question: Please provide the information related to the previously water-quality studies for the Plant as well as records/information from the current pilot study.

Response: Frederick Water will release the treatability study and water quality data as part of the RFP.

3. Question: Please advise as to the current status of the Plant Operations as well as plans for the Plant Operations in the future (i.e. servicing of customers from the water produced).

Response The Sliwinski WTP is operating on a weekly basis but the facility is not producing water for distribution. By early December the WTP will be begin treating water from Pit 2 and distributing to customers. In the future, Frederick Water desires to minimize downtime, but can produce water at the Anderson WTP if needed to allow shutdowns of the Sliwinski WTP.