This is Addendum 2 to RFP# 26-02-010 issued by the Oconee County Board of Commissioners regarding a Design/Build OVP Tennis Court Expansion project. The addendum, dated March 23, 2026, modifies the original solicitation documents dated February 27, 2026, and addresses clarifications submitted by prospective bidders prior to the March 19, 2026, question deadline at 5:00 pm. All inquiries should be directed to Ms. Jessica Ellis, Procurement Officer, at ocbids@oconee.ga.us. The document confirms that the submission page limit remains at thirty pages, with tabs excluded from the page count calculation.
The addendum establishes specific project requirements including that tennis fencing must meet United States Tennis Association (USTA) standards and that contractors must follow the standard Oconee County permit process for all required permits and timing. Regarding existing lighting infrastructure, only light fixture heads require replacement; existing poles are to remain in place. These clarifications ensure bidders have consistent guidance on technical specifications, permitting procedures, and submission formatting as they prepare their proposals for the tennis court expansion project.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
Oconee County Board of Commissioners
Addendum 2
DATE: March 23, 2026
TO: All Prospective Bidders
FROM: Procurement Officer
RE: RFP# 26-02-010 Design/Build OVP Tennis Court Expansion
The following changes are to be incorporated into the solicitation documents dated February 27, 2026. All those receiving this addendum should modify their documents to show the below described changes.
Responses to questions received prior to the deadline of 5:00 pm on March 19, 2026.
All questions shall be directed to Ms. Jessica Ellis, Procurement Officer via email at ocbids@oconee.ga.us
1. Can the page limit be increased to 40 pages?
Page limit will remain thirty (30) pages.
2. Are Tabs excluded from page count limit?
That is correct. Tabs do not count towards the page limit.
3. What will Permit process look like with respect to required permits and timing?
Contractor will follow the standard Oconee County permit process.
4. Are there any specific requirements pursuant to fencing, site furnishings, etc.?
Tennis fencing should meet USTA standards.
5. Are the existing light fixture heads only to be replaced or the poles also?
Only the light fixtures need to be replaced on existing lighting.