This document is a Bidder Questions & Answers document for Request for Proposal (RFP) 250000003143, issued by the Michigan Department of Natural Resources (DNR) for a MiCO License Stock RFP. The RFP involves the production of 2 to 5 million labels annually, with the specific quantity potentially varying based on customer preference. The contract appears to be a 5-year agreement, with vendors expected to include kitting and shipping costs within their overall bid pricing.

The document reveals key procurement details, specifically addressing two primary vendor inquiries. First, regarding label quantity, the DNR seeks pricing for 5 million labels while acknowledging that annual order volumes may fluctuate between 2-5 million. Second, concerning shipping and kitting, the DNR initially stated that vendors should incorporate these costs into their bids, but later updated the guidance to allow use of the State of Michigan's UPS account for shipping. The pricing structure will require vendors to provide a lump sum cost per year for palletizing, preparing, packaging, and arranging shipping or pickup of the product, including associated labor and materials.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

Michigan.gov/MiProcurement

BIDDER QUESTIONS & ANSWERS

Version 2021-2

RFP 250000003143

DNR - MOD - MiCO License Stock RFP

Q

Document and

Section

Page

Bidder Question Answer

Schedule A

- Section Quanties 34

You have stated that the labels produced each year are between 2 to 5 million labels. We have prepared a quote for 5 million labels. If less than 5 mil labels are ordered the price will have to be requoted. Should we state that on the quotation or are you expecting a price for 2, 3, 4 mill labels

I’d like to see a price for 5 mill labels. Please know that the quantity ordered each year may go up or down based on our customer preference.

Schedule B

- Section Item # 3 47

We do need some clarification on Item# 3, Schedule B Pricing. Can we give a lump sum cost for kitting and a lump sum cost for shipping? If the past we have always used the SOM UPS account, since they get a better rate.

The Michigan DNR does not want to pay for shipping or kitting, so please include those cost into you bid.

Update, The DNR will allow the vendor to use SOM UPS account.