Addendum_2__ITB2026091701_DEMO_EFSC_261009.pdf
PDF 552 KB Posted
- Attached to
- Classroom & Hangar Demo
- Solicitation number
- ITB 2026-0917
- Issued by
- Brevard County, Miramar Beach CDP, Florida
About this file
This addendum document pertains to the Melbourne Airport Authority's demolition and site clearance project for classroom and hangar buildings formerly occupied by Eastern Florida State College. The project is structured as a lump sum contract with sealed proposals due October 20, 2026 at 2:00 p.m. EDT. A non-mandatory pre-bid conference with site visit is scheduled for September 24, 2026 at 11:00 a.m. EDT at the Melbourne Airport Authority Board Room, and additional site visits may be arranged between September 29 and October 8 on Tuesdays or Thursdays with 24 to 48 hours advance notice. Written questions must be submitted by 2:00 p.m. on October 13, 2026, with responses provided by addendum. The successful bidder will be responsible for maintenance of traffic, coordination with concurrent contractors and airport operations, scheduling, permitting, subcontractor management, work supervision, document control, inspection coordination, and project closeout. Bids may not be withdrawn for 60 calendar days following the bid deadline.
Bidders must submit a Bid Bond or Certified Check equal to 5% of the total bid amount, and the successful bidder will be required to obtain a Public Construction Bond equal to 100% of the contract award amount prior to contract execution. Upon request within five business days after bid opening, the successful bidder must provide evidence of financial responsibility, experience, qualifications, and documentation of satisfactory completion of similar previous projects. The Melbourne Airport Authority emphasizes high expectations for coordination and professionalism given the operational constraints of conducting work while the airport remains active. Bid packages are available from demandstar.com, myvendorlink.com, and Sandra Acevedo at 321-723-6227 ext. 123 or sacevedo@mlbair.com.
View the file
Other files
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
ADDENDUM 2/PAGE 1 OF 3
ADDENDUM 2
FOR
INVITATION TO BID
For
CLASSOOM AND HANGAR DEMOLITION
EASTERN FLORIDA STATE COLLEGE
At
MELBOURNE ORLANDO INTERNATIONAL AIRPORT
ITB20260917-01
October 9, 2026
This addendum is issued as part of the Bidding Documents for the above described project. The changes incorporated in this addendum shall be considered as a part of the documents and shall supersede, amend, add to, clarify, or subtract from those conditions shown in the original documents. The Bidder shall take care to coordinate modifications herein with all trades and disciplines related to the work. The Bidder shall acknowledge receipt of this addendum in their Bid Package by addendum number and date. Failure to do so may subject Bidder to disqualification.
SENT VIA EMAIL – 6 PAGES TOTAL (including attachments)
________________________________________(NAME OF YOUR COMPANY)
NOTE:
PLEASE SIGN_______________________________AND RETURN THIS FIRST SHEET ONLY VIA
E-MAIL OR FAX to SANDRA ACEVEDO, sacevedo@mlbair.com or (321) 723-1194 Fax
THIS VERIFIES THAT YOU HAVE RECEIVED THE ADDENDUM.
GENERAL
1. THE BID DATE REMAINS TUESDAY, October 20, 2026, at 2:00 PM (EDT).
SPECIFICATIONS
1. See attached sign-in sheet for added site visit on 10/1/26 (1 page).
2. See attached sign-in sheet for added site visit on 10/8/26 (1 page).
DRAWINGS
1. Appendix D (No changes). Added per request.
QUESTIONS AND RESPONSES:
1. CIF-005: in the table of contents, 00 62 33 Buy American certification is listed but was not provided. Please provide section 00 62 33 Buy American Certification section.
RESPONSE: Delete reference to 00 62 33. This is not a Federal grant project.
2. CIF-006: in the table of contents, appendix D is referenced, but was not provided. Please provide appendix D – EFDC Demo Floor Plan Sheet mailto:sacevedo@mlbair.com
REQUEST FOR BID for CLASSROOM AND HANGAR DEMOLITION at the MELBOURNE ORLANDO INTERNATIONAL AIRPORT
RFB20260917-01
ADDENDUM 2/PAGE 2 OF 3
RESPONSE: Appendix D should be page 181 of 202 within the Bid Documents.
3. CIF-007: section 01 32 13 states N/A in the table of contents, but is referenced in the contract documents. Please confirm this is excluded.
RESPONSE: Confirmed. Section 01 32 13 is not applicable to this project.
4. CIF-008: Specification Section 00 21 16 - 2.02B states: "The Prime Contractor must have experience working on an active airfield project". Since the scope of this project generally consists of demolition only, and does not include any new construction that requires specific airfield expertise; and since the work is happening on a property that is nearby the airfield but would not directly impact any runway, taxiway, or other flight activities; would the Melbourne Airport Authority be willing to eliminate this requirement as a qualification for bidders?
Eliminating the requirement could allow one of the many local contractors that attended the pre-bid meeting to gain some experience on a relatively simple project, so they would be eligible to bid on one of your future projects that may be more complicated or in a more sensitive area.
RESPONSE: No. This project is within the SIDA area when the masonry wall is removed.
Commercial aircraft will be within 50 yards of this project. Since demo creates a significant amount of FOD, the Prime Contractor needs to have the experience to access the SIDA area when FOD is present and an active commercial aircraft is parked at Gate 9.
5. CIF-009: Please clarify the demolition limits shown in Appendix F: does the red "Limits of Demolition" boundary require removal of all pavement, curbing, landscaping, and other improvements within the boundary, or only the items specifically called out in the specifications and Appendix F? Please identify any items within the boundary that are to remain
RESPONSE: Scope of demolition in reference to Appendix F include the removal of all landscaping, asphalt pavement, concrete pavement and sidewalks, all site appurtenances (except FPL vault/transformer, water meter, gas meter, fencing (identified in blue), and tie down anchors (within the aircraft apron). Underground fuel tank to be removed under a separate contract.
6. CIF-010: Please confirm whether all footings, grade beams, column pads, and other below-grade structural concrete are to be removed in addition to the slabs on grade and, if so, the required removal depth.
RESPONSE: All footings, grade beams, column pads and other below-grade structural concrete to be removed. As no plans exist for the buildings, assume 2’x1’ for exterior wall footings, 3’x3’x1’ for column pads within the classroom building. Since the hangar is a PEMB, assume thickened slab at column locations of 5’x5’x2’.
7. CIF-011: Please define the required termination/capping points for underground utilities within the building footprints and confirm whether any underground utilities outside the building footprints are included in the demolition scope
RESPONSE: All underground utilities will be removed back to the point of service connections that are within the limits of construction.
8. CIF-012: Can you provide the sign in sheets for any additional contractors that visited the site
REQUEST FOR BID for CLASSROOM AND HANGAR DEMOLITION at the MELBOURNE ORLANDO INTERNATIONAL AIRPORT
RFB20260917-01
ADDENDUM 2/PAGE 3 OF 3
after the initial pre-bid conference on 9/24/26, since today is the last day to have access to look at the site. I know the pre-bid was not mandatory but the site visit is and that required a sign in.
RESPONSE: Refer to Specification section above for 2 pages of additional sign in sheets from site visits on 10/1/26 and 10/8/26.
END OF ADDENDUM #2
Issued by
Melbourne Airport Authority dperley Text Box
APPENDIX D
| Addendum 2 - ITB20260917-01 DEMO EFSC 261013 |
| Site Visit Sign in Sheet 10.01.26 |
| Site Visit Sign in Sheet 10.08.26 |
| APPENDIX D - EFSC DEMO FLOORPLAN |