Addendum No. 2, issued August 19, 2026, by The Design Studio, Inc. on behalf of the Department of State Parks & Cultural Resources, Division of State Parks, Historic Sites & Trails, provides clarifications and revisions to the bid documents for the Historic Governors' Mansion Envelope Rehabilitation Project located at 300 East 21st Street, Cheyenne, Wyoming. The project encompasses exterior envelope rehabilitation of the Historic Governors' Mansion and Carriage House, including exterior brick repair and tuckpointing, copper roofing and flashing replacement, wood window repair and replacement, synthetic shingle roofing replacement, membrane roofing replacement, and copper edge metal, gutters, and downspouts replacement. A non-mandatory pre-bid meeting with walk-through was held on August 5, 2026, at 11:00 a.m., with the agenda and sign-in sheet attached to the addendum. Bids are due August 26, 2026, at 1:00 p.m. Mountain Daylight Time through Public Purchase Online. Award is anticipated September 2, 2026, with work anticipated to begin October 7, 2026, and substantial completion targeted for June 30, 2027.

Addendum No. 2 addresses specific questions and clarifications regarding project execution, including requirements that windows be pre-primed, contractors are responsible for painting both interior and outside of all windows while protecting existing wallpaper, and interior trim that cannot be salvaged shall be replaced in kind. Twenty-four-hour over-the-counter permits are required from the City of Cheyenne for roofing and siding and window replacement. The building will remain open to the public during construction, requiring the contractor to install and maintain safe and code-compliant temporary measures at public entries, exits, and ADA access corridors. The contractor is responsible for providing all necessary utilities and winter protection to maintain the project schedule. The addendum confirms that neither lead-based materials nor asbestos-containing building materials are anticipated within the designated scope of work, though contractors must immediately cease operations and notify the owner's representative if such materials are encountered. Revised Project Drawings dated August 19, 2026, replace sheets A-211 through A-215, with detailed window repair and screen repair schedules provided for all four elevations of the mansion and carriage house.

View the file

Other files

On GovTribe

Work with this file

  • Download the original file
  • Contacts named in this file
  • Similar government files
  • Ask GovTribe AI about this file

Text version

1610 Pioneer Avenue Cheyenne, Wyoming 82001 T ) 307.775.9970 www.tdsi.us

ADDENDUM #2

DATE: August 19, 2026 APN: 23.2.452c

OPN: NO. 27-0670

PROJECT: HISTORIC GOVERNORS’

MANSION

ENVELOPE REHAB PROJECT

300 E 21 Street Cheyenne, Wyoming 82001

OWNER: Department Of State Parks & Cultural Resources Division Of State Parks, Historic Sites & Trails 2301 Central Avenue Cheyenne, Wyoming 82002

BID OPENING

TIME/DATE:

August 26, 2026, at 1:00 P.M.

Mountain Daylight Time

LOCATION:

Public Purchase Online

Bidders are hereby notified of the following adjustments, corrections, additions or clarifications for the Bid Documents.

Where provisions of the following items differ from those of the original Bid Documents, provisions of this addendum shall govern and take precedence. This addendum shall be considered part of the Contract Documents for this Project and must be returned with all other contract documents after the bid date.

Bidders shall acknowledge receipt of all addenda on the Bid Form.

PRE-BID MEETING

A non-mandatory Pre-Bid meeting, including walk-through was held on August 5, 2026 at 11:00 a.m. The Agenda and Sign-in Sheet from the meeting is attached to this addendum.

QUESTIONS AND CLARIFICATIONS

1. Windows shall be pre-primed.

2. Contractors are responsible for painting both the inside and outside of all windows, being careful not to disturb the existing wallpaper adjacent to windows. Any wallpaper damaged due to contractor negligence, shall be replaced in kind by contractor.

3. Any interior trim that cannot be salvaged for reinstallation shall be replaced in kind by the contractor.

4. What permits would need to be acquired from the city for this project?

a. 24-hr over-the-counter permits are needed for Roofing and Siding & Window Replacement, per phone call with permit technician on 2026.08.14.

5. Will the building be open and operating for the duration of the project?

a. The building will remain open to the public. Contractor is responsible for installing and maintaining safe and code compliant temporary measures at public entries, exits, and ADA access corridors.

6. Will power and water be available to the GC for this project?

a. Contractor is responsible for providing all necessary utilities for completion of the project.

7. Should the GC plan for winter protection on the project? If not, will additional days be added to the project where cold or inclement weather prevent work?

a. The contractor is responsible for all required winter protection necessary to maintain the project schedule.

8. Please confirm that no lead or asbestos abatement is required as part of this project.

a. Neither lead-based materials nor asbestos-containing building materials are anticipated within the designated scope of work. If the contractor suspects or encounters material reasonably believed to be lead, asbestos, or any other hazardous substance, the contractor shall cease operations in the affected area and immediately notify the owner’s representative.

DRAWINGS

1. Sheets A-211 through A-215 – Project Drawings-Windows – REPLACE with the attached Revised Project

WSP HGM Envelop Rehab Project Addendum #2

2026.08.19

TDSi 1610 Pioneer Avenue Cheyenne, Wyoming 82001 T ) 307.775.9970 www.tdsi.us

Drawings (dated 8/19/26 – 5 pages).

ATTACHMENTS

1. Pre-Bid Agenda

2. Pre-Bid Sign-In Sheet

3. Revised Project Drawings Dated 8/19/26 – 5 pages

PRE-BID AGENDA

300 E. 21st STREET, CHEYENNE, WY 82001 – MANSION ENVELOPE

REHABILITAION PROJECT, AUGUST 5, 2026 – 11:00 AM

RFB NO. 27-0670

1. INTRODUCTION

Project Manager: Jeremy Deuto P.E. (CO), PG, Construction Project Manager

Phone: 307-757-5158 Email: jeremy.deuto@wyo.gov

Site Superintendent: Alexis Pratt

Bid Opening: August 26, 2026 1:00 PM MST Public Purchase Online

2. CALL FOR BIDS

Bids may not be withdrawn for 30 days after bid opening.

10% bid deposit must accompany each bid.

Performance and Payment Bond required for 100% of contract amount when the bid exceeds $150,000.

Liquidated damages - Based on contract value as provided in the table in Section 8.O(i) of the sample contract.

State funds, therefore a 5% preference will be given to resident contractors bidding this project. Non-residents must register with the Secretary of State. Resident contractors must have a Resident Certification Number. Contact the Dept. of Workforce Services – Labor Standards (307)777-7261

Per Wyoming Statute, Wyoming resident labor shall be used on this project.

A formal contract will be executed.

3. KEY DATES

4. INSURANCE REQUIREMENTS

Worker’s Comp & Employees Liability

(a) Bodily Injury by Accident: $1,000,000.00 each accident;

(b) Bodily Injury by Disease: $1,000,000.00 each employee; and

(c) Bodily Injury by Disease: $1,000,000.00 policy limit.

Commercial General Liability Insurance. Commercial general liability insurance (CGL) coverage, occurrence form, covering liability claims for bodily injury and property damage arising out of premises, operations, products and completed operations, and personal and advertising injury, with minimum limits as follows:

(a) $1,000,000.00 each occurrence;

(b) $1,000,000.00 personal injury and advertising injury;

(c) $2,000,000.00 general aggregate; and

(d) $2,000,000.00 products and completed operations.

The CGL policy shall include coverage for Explosion, Collapse and Underground property damage. This coverage may not be excluded by endorsement.

Unemployment Insurance – as required by Department of Workforce Services Business Automobile Liability- $1,000,000 each occurrence.

Builder’s Risk Insurance – 100% Contract Amount

5. WYOMING PREVAILING HOURLY WAGES

Applies to contracts over $100,000.00

6. LAWS TO BE OBSERVED

All local, State and Federal laws, rules & codes shall be followed.

7. LICENSES, PERMITS & TAXES

Discuss any and all permits, etc. The contractor is responsible for all other plan reviews, permits, licenses, fees & taxes. The contractor shall schedule and request all required inspections.

8. FORTY HOUR WORK WEEK

Per State Statute, time and a half overtime must be paid.

9. GUARANTEE AND WARRANTY

Any portions of work needing replacement or repair within one (1) YEAR FROM THE

DATE OF WRITTEN ACCEPTANCE BY THE Department of State Parks and Cultural Resources shall be completed by the Contractor at his expense. All product warranties over one year shall carry over to the State.

10. CONSTRUCTION MANAGEMENT

The Design Studio, inc State Parks personnel

11. COORDINATION OF WORK

Contractor will coordinate work with the Construction Manager.

12. PRESERVATION OF VEGETATION

Contractor shall protect vegetation from destruction, scarring, ruts, damage or defacing.

13. CLEAN UP

Contractor responsible for all clean up to the satisfaction of the site Superintendent.

14. PROTECTION OF FACILITIES

Contractor damage to any park facility will be repaired at contractor expense.

15. CONTRACTOR RESPONSIBILITY

Not addressing any particular item of the Contract Documents, Specifications or

Construction Drawings during the Pre-bid Meeting, in no-way eliminates the responsibility of the Contractor from completing all work in accordance with the Contract Documents, Specifications and Construction Drawings.

16. DESCRIPTION OF WORK

A. Site:

1. Access to the site shall be at the existing streets and alley.

2. On-site staging and storage areas shall be limited to an area designated by the Site Superintendent and disclosed during the pre-bid meeting.

B. General Description:

1. Obtain all City of Cheyenne, Laramie County, State of

Wyoming, and other permits required for the project.

C. The Project includes, but is not limited to the following:

1. The renovation of the exterior of the Historic Governors' Mansion and

Carriage House.

2. Work will include, but not limited to:

a. Exterior brick repair and tuckpointing;

b. Replacement of copper roofing and flashing;

c. Wood window repair/replacement;

d. Painting of wood windows and wood trim;

e. Replacement of synthetic shingle roofing;

f. Replacement of membrane roofing;

g. Replacement of copper edge metal, gutters and downspouts.

3. Selective demolition associated with the above work.

17. QUESTIONS?

Name

Curtis Humlicek

Soshuc Meseley

Company

Richordson Canstruction

300 E. 21st STREET, CHEYENNE, WY 82001

MANSION ENVELOPE REHABILITAION PROOJECT PRE-BID MEETING

AUGUST 5, 2026

Address

101 Lexingten Ave. Suile a Cheyenne, WY 82001

Phone/Cell Fax/Email

307-345-sa4a bidlist@rciwyo.com

Capitel Rochisa 80s F Fox Farm D (eyese WY E2O-T 307-287-1390

Relly Fischer iBeild Construstias 970888 1666 jash@(apitalacfingin.co thiBuildegmonl com

681 $. 4050 W. SALT LAKE CITY, UTAH 84104

CASEY SullIVAN ABSTRACT MASOURY RESTORATION (901)509-4802 Casey@masonry-rectoration. oih

Matt Corten

INes Hanzyen egacy Cored: GenepHydre Tech chrugoue Wy 307 421 3524 MaAlegalywyomine.com

1313 N 300W Lehi UTah

Shann Loga CMc LootmEnd

Haruld F. Jchnsin Mascary PU Bcy Z697 Cheyenne WY 8203

Allied Constructioa Jake Jahnson

Jon Schacser

Iwke Christensenbastesca Rich DerMatteo

American Contrncting 1L6

Elite

Sampson Constiuction

801 372 5148

3801 E soth Dovaer 80216 720 537

1tls w Jackson Blvd Spearfish sD

1657 Carey Ave suite4 Cheyenne W782001

800 E 64K A Acnv, Coge02

1321 wilhins Cic, (asperuy, 8710

307-632-9231

6003-645-3464

307-631-5730

720-207-3932

970-682-5733Matthew Petrote

DAVIO STASSI BorMOAON RRDs 12235 S. JASON ST., DENUER, C0 P0203 (720)272-0514

Jin Satkoa Pella Dar & Windous

Justin Byra ES Services 1102

Swert wder Cloyean

Lyn Are Cheyene

307-2-162.1915 307.655.6630 fom

Shawn Logan@mpotry.co

"pkee hijmasany.yon jons@alliedconstcuution.coa Lukcichristensen@ american contracting 11C. vom nich@elitescinet Sanpsen matthew. PetrotHa @ construwtionce

JAVIDRM-REpS.com

-jsottey a follaidl.com ej-semices@ blapridtabad-ces

Wells@ HT resloration.

MAIN LEVEL

100' - 0"

SECOND FLOOR

112' - 3"

LOWER LEVEL

91' - 8"

ATTIC

123' - 9"

011010

214213211210

112110

BIS

RB

IJ

RB

BIS

RB

TSM

RG

SSS

UCB

BOB

RSG

BOB

TSM

TSL

RSG

TSL

SLP

PMS

RSG

SLP

BOB

RSG

COB

COS

BOB

RSG

RG

SP

CWS

TUG

AFP

BIS

RB

A-171

E11 Sim

B8

A-171

B6

A-171

LSM LSM

GENERAL NOTES:

1. EXTERIOR TRIM, ENTABLATURE, AND PEDIMENT DETAIL, QUOINS, WINDOW

SURROUNDS, DECORATIVE BALCONIES AND OTHER ARCHITECTURAL DETAILS

HAVE NOT BEEN SHOWN FOR CLARITY AND ARE NOT PART OF THIS PROJECT.

2. APPROXIMATE SURFACING BASED ON PHOTOS.

3. REMOVE AND REPLACE FIXED / CASEMENT ALUMINUM & WOOD WINDOWS IN

BREAKFAST NOOK (119, 130) AND CASEMENT ALUMINUM & WOOD WINDOWS IN

SUNROOM (215-219, 226-234, 239-242).

LEGEND:

NOTES REGARDING THE SCREEN OR STORM UNIT ONLY

NOTES REGARDING THE WINDOW UNIT ONLYCOB

TSM

C -1

LIC

E

N S

E D

A R

C H

IT

E

C T

RAN

D

Y L

B

Y E

R S

S T

A T

E O

F W

Y O

M

IN

G

D a te

APN: Date Issued:

Drawn By: Checked By:

Sheet Title:

Sheet Number:

T D S

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

A

B

C

D

E

F

G

H

I

J

K

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

T h e D e si g n

S tu d io in c

A rc h it e c tu re

I n te ri o r D e si g n

P io n e e r

A v e n u e

C h e y e n n e

W y o m in g

T

.7

.9

W t d s i.

u s

NOTE: THE ORIGINAL DRAWINGS FOR THIS PROJECT ARE 36" X 24". IF YOU HAVE A SMALLER SET, IT HAS BEEN

REDUCED AND DRAWING SCALES ARE NOT VALID.

i

/1

/2

:5 :3

P

M

A-211

EXTERIOR

ELEVATIONS

WINDOWS

SLL

23.2.452c 2026.07.17

.0

.1

P ro je c t S ta tu s

H

IS

T O

R

IC

G O

V E

R N

O R

S ' M

A N

S

IO

N E

X T

E R

IO

R

R E

N O

V A

T

IO

N

E

A S

T s t S

T R

E E

T C

H E

Y E

N N

E

W Y

O M

IN

G

1/4" = 1'-0" A-211

K1 SOUTH ELEVATION

WINDOW REPAIR SCHEDULE

Window Number KEY DESCRIPTION

10 LSM Replace lower screen mesh.

11 LSM Replace lower screen mesh.

110 BIS Remove and replace bottom interior stop.

110 IJ Ensure interior jamb is not separating from frame, repaint to match.

110 RB Remove and replace bottom rail to match.

112 BIS Remove and replace bottom interior stop.

112 RB Remove and replace bottom rail to match.

112 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

112 SSS Each side stile needs lower wood removed to sound wood and new wood sistered in to match existing.

210 BOB Apply consolidant to bottom of bottom rail. Apply paint to match existing.

211 BOB Apply consolidant to bottom of bottom rail. Apply paint to match existing.

211 TSL Tighten sash lock to lower sash and ensure it aligns with upper sash keeper.

212 PMS Attempt to remove plaster (?) materials from middle sash.

213 BOB Apply consolidant to bottom of bottom rail. Apply paint to match existing.

213 COB Strip paint and apply consolidant on exterior of bottom rail to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

213 COS Strip paint and apply consolidant on exterior of side stiles to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

214 BOB Apply consolidant to bottom of bottom rail. Apply paint to match existing.

310 AFP Apply fresh paint to match existing finishes.

310 CWS Check wood soundness. If not in good condition, replace in kind. If in stable condition, apply consolidant.

310 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

310 SP Strip all paint/stain; apply fresh to match existing.

310 TUG Tighten screws to reduce gaps in frame.

WINDOW SCREEN REPAIR SCHEDULE

Window Number KEY Description

110 RB Replace bottom rail to match.

112 TSM Remove bottom parting stop (and side stops if necessary) to tighten screen mesh and replace bottom parting stop.

112 UCB Upper storm window unit bottom rail needs paint stripped and consolidant applied.

210 RSG Remove all parting stops and screen mesh. Replace with new glass to match upper portion; place new parting stops to secure glass.

211 TSM Remove bottom parting stop (and side stops if necessary) to tighten screen mesh and replace bottom parting stop.

212 RSG Remove all parting stops and screen mesh. Replace with new glass to match upper portion; place new parting stops to secure glass.

212 SLP Scrape loose paint along all glass edges, touch up paint.

212 TSL Tighten sash lock to lower sash and ensure it aligns with upper sash keeper.

213 RSG Remove all parting stops and screen mesh. Replace with new glass to match upper portion; place new parting stops to secure glass.

214 RSG Remove all parting stops and screen mesh. Replace with new glass to match upper portion; place new parting stops to secure glass.

SECOND FLOOR

112' - 3"

LOWER LEVEL

91' - 8"

ATTIC

123' - 9"

113 114 115

118117116

016015014

222220

219218217216215 221

RG RG

LSM

USM

LSM LSM

SP

RG COB

COS

SP

RG COB

COS

RB

SM

RM

COB

RS

SM

MR

RB

RS

COS

BIS

RB

RB BIS

RB

RG

UCB

TSM BIS

RB

RG

RSG

COB

TUPSWF

SPF

RGTSM

CWS

SPF

RG

TSM

SP

RG

CWS

PWS

RS

COB

RXS

SM

A-171

B8 Sim

A-171

B6 Sim

A-171

B11 Sim

E11

A-171

Sim

RAMP NOT SHOWN FOR CLARITY -

NOT PART OF SCOPE

REMOVE AND REPLACE ALL

CASEMENT ALUMINUM &

WOOD WINDOWS IN SUNROOM

LEGEND:

NOTES REGARDING THE SCREEN OR STORM UNIT ONLY

NOTES REGARDING THE WINDOW UNIT ONLYCOB

TSM

GENERAL NOTES:

1. EXTERIOR TRIM, ENTABLATURE, AND PEDIMENT DETAIL, QUOINS, WINDOW

SURROUNDS, DECORATIVE BALCONIES AND OTHER ARCHITECTURAL DETAILS

HAVE NOT BEEN SHOWN FOR CLARITY AND ARE NOT PART OF THIS PROJECT.

2. APPROXIMATE SURFACING BASED ON PHOTOS.

3. REMOVE AND REPLACE FIXED / CASEMENT ALUMINUM & WOOD WINDOWS IN

BREAKFAST NOOK (119, 130) AND CASEMENT ALUMINUM & WOOD WINDOWS IN

SUNROOM (215-219, 226-234, 239-242).

C -1

LIC

E

N S

E D

A R

C H

IT

E

C T

RAN

D

Y L

B

Y E

R S

S T

A T

E O

F W

Y O

M

IN

G

D a te

APN: Date Issued:

Drawn By: Checked By:

Sheet Title:

Sheet Number:

T D S

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

A

B

C

D

E

F

G

H

I

J

K

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

T h e D e si g n

S tu d io in c

A rc h it e c te ri o r D e si g n

P io n e e r

A v e n u e

C h e y e n n e

W y o m in g

T

.7

.9 t d s i.

NOTE: THE ORIGINAL DRAWINGS FOR THIS PROJECT ARE 36" X 24". IF YOU HAVE A SMALLER SET, IT HAS BEEN

REDUCED AND DRAWING SCALES ARE NOT VALID.

i

/1

/2

:5 :3

P

M

A-212

EXTERIOR

ELEVATIONS

WINDOWS

SLL

23.2.452c 2026.07.17

.0

.1

P ro je c t S ta tu s

H

IS

T O

R

IC

G O

V E

R N

O R

S ' M

A N

S

IO

N E

X T

E R

IO

R

R E

N O

V A

T

IO

N

E

A S

T s t S

T R

E E

T C

H E

Y E

N N

E

W Y

O M

IN

G

1/4" = 1'-0" A-212

K1 WEST ELEVATION

WINDOW REPAIR SCHEDULE

Window Number KEY DESCRIPTION

12 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

13 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

14 LSM Replace lower screen mesh.

14 USM Repair upper screen frame and replace screen mesh with new.

15 LSM Replace lower screen mesh.

16 LSM Replace lower screen mesh.

113 COB Strip paint and apply consolidant on exterior of bottom rail to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

113 COS Strip paint and apply consolidant on exterior of side stiles to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

113 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

113 SP Strip all paint/stain; apply fresh to match existing.

114 COB Strip paint and apply consolidant on exterior of bottom rail to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

114 COS Strip paint and apply consolidant on exterior of side stiles to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

114 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

114 SP Strip all paint/stain; apply fresh to match existing.

116 BIS Remove and replace bottom interior stop.

116 RB Remove and replace bottom rail to match.

117 BIS Remove and replace bottom interior stop.

117 RB Remove and replace bottom rail to match.

117 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

118 BIS Remove and replace bottom interior stop.

118 RB Remove and replace bottom rail to match.

118 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

220 TUP Touch up paint where needed.

221 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

221 SPF Strip all paint from entire window and frame; apply fresh to match existing.

222 CWS Check wood soundness. If not in good condition, replace in kind. If in stable condition, apply consolidant.

222 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

222 SPF Strip all paint from entire window and frame; apply fresh to match existing.

311 COB Strip paint and apply consolidant on exterior of bottom rail to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

311 CWS Check wood soundness. If not in good condition, replace in kind. If in stable condition, apply consolidant.

311 PWS Scrape loose paint between window and storm sash, repaint to match existing.

311 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

311 RXS Replace exterior wood sill in kind.

311 SP Strip all paint/stain; apply fresh to match existing.

WINDOW SCREEN REPAIR SCHEDULE

Window Number KEY Description

113 RB Replace bottom rail to match.

113 RM Replace middle rail to match.

113 SM Install new screen mesh.

114 COB Strip paint and apply consolidant on exterior of bottom rail to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

114 MR Strip paint and apply consolidant on exterior of middle rail to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

114 RS Remove and replace parting stop on exterior.

114 SM Install new screen mesh.

115 COS Strip paint and apply consolidant on exterior of side stiles to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

115 RB Replace bottom rail to match.

115 RS Remove and replace parting stop on exterior.

116 RB Replace bottom rail to match.

117 TSM Remove bottom parting stop (and side stops if necessary) to tighten screen mesh and replace bottom parting stop.

117 UCB Upper storm window unit bottom rail needs paint stripped and consolidant applied.

118 COB Strip paint and apply consolidant on exterior of bottom rail to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

118 RSG Remove all parting stops and screen mesh. Replace with new glass to match upper portion; place new parting stops to secure glass.

220 SWF Reinstall storm window into frame.

221 TSM Remove bottom parting stop (and side stops if necessary) to tighten screen mesh and replace bottom parting stop.

222 TSM Remove bottom parting stop (and side stops if necessary) to tighten screen mesh and replace bottom parting stop.

311 RS Remove and replace parting stop on exterior.

311 SM Install new screen mesh.

SECOND FLOOR

112' - 3"

LOWER LEVEL

91' - 8"

ATTIC

123' - 9"

121120

126125124123

223 235

312 314313

234233232231230229228227226

SLPRSG

RG

SP

RMSTSM

MR

RG

SP

RMS

TSM

SLP

SS

RSG

RG COB

RSG

COS

TSL

SWF

RSG

CWS

TSM

RG

SP

CWS

PWS

RW

B8

A-171

B11

A-171

RG

SP

RG

SP

RG

SP

RAMP NOT SHOWN FOR CLARITY -

NOT PART OF SCOPE

REMOVE AND REPLACE ALL

CASEMENT ALUMINUM & WOOD

WINDOWS IN SUNROOM

REMOVE AND REPLACE FIXED

/ CASEMENT ALUMINUM &

WOOD WINDOWS IN

BREAKFAST NOOK

GENERAL NOTES:

1. EXTERIOR TRIM, ENTABLATURE, AND PEDIMENT DETAIL, QUOINS, WINDOW

SURROUNDS, DECORATIVE BALCONIES AND OTHER ARCHITECTURAL DETAILS

HAVE NOT BEEN SHOWN FOR CLARITY AND ARE NOT PART OF THIS PROJECT.

2. APPROXIMATE SURFACING BASED ON PHOTOS.

3. REMOVE AND REPLACE FIXED / CASEMENT ALUMINUM & WOOD WINDOWS IN

BREAKFAST NOOK (119, 130) AND CASEMENT ALUMINUM & WOOD WINDOWS IN

SUNROOM (215-219, 226-234, 239-242).

LEGEND:

NOTES REGARDING THE SCREEN OR STORM UNIT ONLY

NOTES REGARDING THE WINDOW UNIT ONLYCOB

TSM

C -1

LIC

E

N S

E D

A R

C H

IT

E

C T

RAN

D

Y L

B

Y E

R S

S T

A T

E O

F W

Y O

M

IN

G

D a te

APN: Date Issued:

Drawn By: Checked By:

Sheet Title:

Sheet Number:

T D S

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

A

B

C

D

E

F

G

H

I

J

K

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

T h e D e si g n

S tu d io in c

A rc h it e c te ri o r D e si g n

P io n e e r

A v e n u e

C h e y e n n e

W y o m in g

T

.7

.9 t d s i.

NOTE: THE ORIGINAL DRAWINGS FOR THIS PROJECT ARE 36" X 24". IF YOU HAVE A SMALLER SET, IT HAS BEEN

REDUCED AND DRAWING SCALES ARE NOT VALID.

i

/1

/2

:5 :3

P

M

A-213

EXTERIOR

ELEVATIONS

WINDOWS

SLL

23.2.452c 2026.07.17

.0

.1

P ro je c t S ta tu s

H

IS

T O

R

IC

G O

V E

R N

O R

S ' M

A N

S

IO

N E

X T

E R

IO

R

R E

N O

V A

T

IO

N

E

A S

T s t S

T R

E E

T C

H E

Y E

N N

E

W Y

O M

IN

G

1/4" = 1'-0" A-213

K1 NORTH ELEVATION

WINDOW REPAIR SCHEDULE

Window Number KEY DESCRIPTION

120 SLP Scrape loose paint along all glass edges, touch up paint.

121 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

121 RMS Replace middle stile to match.

121 SP Strip all paint/stain; apply fresh to match existing.

123 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

123 SP Strip all paint/stain; apply fresh to match existing.

124 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

124 SP Strip all paint/stain; apply fresh to match existing.

125 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

125 SP Strip all paint/stain; apply fresh to match existing.

126 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

126 RW Install new rope to window weight on left side.

126 SP Strip all paint/stain; apply fresh to match existing.

223 COB Strip paint and apply consolidant on exterior of bottom rail to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

223 COS Strip paint and apply consolidant on exterior of side stiles to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

223 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

223 TSL Tighten sash lock to lower sash and ensure it aligns with upper sash keeper.

312 CWS Check wood soundness. If not in good condition, replace in kind. If in stable condition, apply consolidant.

312 PWS Scrape loose paint between window and storm sash, repaint to match existing.

312 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

312 SP Strip all paint/stain; apply fresh to match existing.

314 CWS Check wood soundness. If not in good condition, replace in kind. If in stable condition, apply consolidant.

WINDOW SCREEN REPAIR SCHEDULE

Window Number KEY Description

120 RSG Remove all parting stops and screen mesh. Replace with new glass to match upper portion; place new parting stops to secure glass.

121 MR Strip paint and apply consolidant on exterior of middle rail to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

121 TSM Remove bottom parting stop (and side stops if necessary) to tighten screen mesh and replace bottom parting stop.

123 RMS Replace middle stile to match.

123 SLP Scrape loose paint along all glass edges, touch up paint.

123 SS On exterior sloped wood sill, scrape loose paint, apply consolidant and repaint to match existing finishes.

123 TSM Remove bottom parting stop (and side stops if necessary) to tighten screen mesh and replace bottom parting stop.

124 RSG Remove all parting stops and screen mesh. Replace with new glass to match upper portion; place new parting stops to secure glass.

223 RSG Remove all parting stops and screen mesh. Replace with new glass to match upper portion; place new parting stops to secure glass.

312 TSM Remove bottom parting stop (and side stops if necessary) to tighten screen mesh and replace bottom parting stop.

313 SWF Reinstall storm window into frame.

314 RSG Remove all parting stops and screen mesh. Replace with new glass to match upper portion; place new parting stops to secure glass.

SECOND FLOOR

112' - 3"

LOWER LEVEL

91' - 8"

ATTIC

123' - 9"

128 129127

238236

242241240239

LSMLSM

TSM

UCB

RG BIS

SSS

UCB

RG

BIS

RB

COS

COT

UCB

RG

BIS

RB

COS

COS

TSM

RG

SP

RSG

TSM

RG COB

COS

PWS

TSM RG

TSL

BIS

RG

SP

CWS

RSW

COB

RXS

PWS

RZT

CWS

E11

A-171

A-171

B8 Sim

A-171

B6 Sim

REMOVE AND REPLACE ALL

CASEMENT ALUMINUM & WOOD

WINDOWS IN SUNROOM

REMOVE AND REPLACE FIXED /

CASEMENT ALUMINUM & WOOD

WINDOWS IN BREAKFAST NOOK

LEGEND:

NOTES REGARDING THE SCREEN OR STORM UNIT ONLY

NOTES REGARDING THE WINDOW UNIT ONLYCOB

TSM

GENERAL NOTES:

1. EXTERIOR TRIM, ENTABLATURE, AND PEDIMENT DETAIL, QUOINS, WINDOW

SURROUNDS, DECORATIVE BALCONIES AND OTHER ARCHITECTURAL DETAILS

HAVE NOT BEEN SHOWN FOR CLARITY AND ARE NOT PART OF THIS PROJECT.

2. APPROXIMATE SURFACING BASED ON PHOTOS.

3. REMOVE AND REPLACE FIXED / CASEMENT ALUMINUM & WOOD WINDOWS IN

BREAKFAST NOOK (119, 130) AND CASEMENT ALUMINUM & WOOD WINDOWS IN

SUNROOM (215-219, 226-234, 239-242).

C -1

LIC

E

N S

E D

A R

C H

IT

E

C T

RAN

D

Y L

B

Y E

R S

S T

A T

E O

F W

Y O

M

IN

G

D a te

APN: Date Issued:

Drawn By: Checked By:

Sheet Title:

Sheet Number:

T D S

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

A

B

C

D

E

F

G

H

I

J

K

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

T h e D e si g n

S tu d io in c

A rc h it e c te ri o r D e si g n

P io n e e r

A v e n u e

C h e y e n n e

W y o m in g

T

.7

.9 t d s i.

NOTE: THE ORIGINAL DRAWINGS FOR THIS PROJECT ARE 36" X 24". IF YOU HAVE A SMALLER SET, IT HAS BEEN

REDUCED AND DRAWING SCALES ARE NOT VALID.

i

/1

/2

:5 :3

P

M

A-214

EXTERIOR

ELEVATIONS

WINDOWS

SLL

23.2.452c 2026.07.17

.0

.1

P ro je c t S ta tu s

H

IS

T O

R

IC

G O

V E

R N

O R

S ' M

A N

S

IO

N E

X T

E R

IO

R

R E

N O

V A

T

IO

N

E

A S

T s t S

T R

E E

T C

H E

Y E

N N

E

W Y

O M

IN

G

1/4" = 1'-0" A-214

K1 EAST ELEVATION

WINDOW REPAIR SCHEDULE

Window Number KEY DESCRIPTION

18 LSM Replace lower screen mesh.

20 LSM Replace lower screen mesh.

127 BIS Remove and replace bottom interior stop.

127 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

127 SSS Each side stile needs lower wood removed to sound wood and new wood sistered in to match existing.

128 BIS Remove and replace bottom interior stop.

128 COS Strip paint and apply consolidant on exterior of side stiles to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

128 RB Remove and replace bottom rail to match.

128 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

129 BIS Remove and replace bottom interior stop.

129 COS Strip paint and apply consolidant on exterior of side stiles to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

129 RB Remove and replace bottom rail to match.

129 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

131 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

131 SP Strip all paint/stain; apply fresh to match existing.

236 COB Strip paint and apply consolidant on exterior of bottom rail to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

236 COS Strip paint and apply consolidant on exterior of side stiles to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

236 CWS Check wood soundness. If not in good condition, replace in kind. If in stable condition, apply consolidant.

236 PWS Scrape loose paint between window and storm sash, repaint to match existing.

236 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

237 BIS Remove and replace bottom interior stop.

238 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

238 TSL Tighten sash lock to lower sash and ensure it aligns with upper sash keeper.

315 COB Strip paint and apply consolidant on exterior of bottom rail to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

315 CWS Check wood soundness. If not in good condition, replace in kind. If in stable condition, apply consolidant.

315 PWS Scrape loose paint between window and storm sash, repaint to match existing.

315 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

315 RXS Replace exterior wood sill in kind.

315 RZT Remove zip ties.

315 SP Strip all paint/stain; apply fresh to match existing.

WINDOW SCREEN REPAIR SCHEDULE

Window Number KEY Description

127 TSM Remove bottom parting stop (and side stops if necessary) to tighten screen mesh and replace bottom parting stop.

127 UCB Upper storm window unit bottom rail needs paint stripped and consolidant applied.

128 COT Strip paint and apply consolidant on exterior of top rail to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

128 UCB Upper storm window unit bottom rail needs paint stripped and consolidant applied.

129 COS Strip paint and apply consolidant on exterior of side stiles to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

129 TSM Remove bottom parting stop (and side stops if necessary) to tighten screen mesh and replace bottom parting stop.

129 UCB Upper storm window unit bottom rail needs paint stripped and consolidant applied.

131 RSG Remove all parting stops and screen mesh. Replace with new glass to match upper portion; place new parting stops to secure glass.

236 TSM Remove bottom parting stop (and side stops if necessary) to tighten screen mesh and replace bottom parting stop.

238 TSM Remove bottom parting stop (and side stops if necessary) to tighten screen mesh and replace bottom parting stop.

315 RSW Replicate storm window to replace this one.

SECOND FLOOR

112' - 3"

446 447

AFP

RG

SP

AFP

MM

BGP

CUPULA NOT SHOWN FOR CLARITY - NOT PART OF SCOPE

MAIN LEVEL

100' - 0"

SECOND FLOOR

112' - 3"

453452451450

RG

SP

AFP

MM

EPS

RIP

AFP AFP AFP AFP

CUPULA NOT SHOWN FOR CLARITY - NOT PART OF SCOPE

MAIN LEVEL

100' - 0"

SECOND FLOOR

112' - 3"

444441 442440

RIP

EPSTSM

RSG

COBJSC

COS

RGCWS

SP

RG

RSW

COB

RS

COB

COB

RS

CWS

SP

RGRS

CUPULA NOT SHOWN FOR CLARITY - NOT PART OF SCOPE

MAIN LEVEL

100' - 0"

SECOND FLOOR

112' - 3"

454 455

EPS

RIP

COB

COS

EPS

RIP

CUPULA NOT SHOWN FOR CLARITY - NOT PART OF SCOPE

LEGEND:

NOTES REGARDING THE SCREEN OR STORM UNIT ONLY

NOTES REGARDING THE WINDOW UNIT ONLYCOB

TSM

C -1

LIC

E

N S

E D

A R

C H

IT

E

C T

RAN

D

Y L

B

Y E

R S

S T

A T

E O

F W

Y O

M

IN

G

D a te

APN: Date Issued:

Drawn By: Checked By:

Sheet Title:

Sheet Number:

T D S

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

A

B

C

D

E

F

G

H

I

J

K

1 2 3 4 5 6 7 8 9 10 11 12 13 14 15 16

T h e D e si g n

S tu d io in c

A rc h it e c te ri o r D e si g n

P io n e e r

A v e n u e

C h e y e n n e

W y o m in g

T

.7

.9 t d s i.

NOTE: THE ORIGINAL DRAWINGS FOR THIS PROJECT ARE 36" X 24". IF YOU HAVE A SMALLER SET, IT HAS BEEN

REDUCED AND DRAWING SCALES ARE NOT VALID.

i

/1

/2

:5 :3

P

M

A-215

EXTERIOR

ELEVATIONS

CARRIAGE

HOUSE

WINDOWS

SLL

23.2.452c 2026.07.17

.0

.1

P ro je c t S ta tu s

H

IS

T O

R

IC

G O

V E

R N

O R

S ' M

A N

S

IO

N E

X T

E R

IO

R

R E

N O

V A

T

IO

N

E

A S

T s t S

T R

E E

T C

H E

Y E

N N

E

W Y

O M

IN

G

1/4" = 1'-0" A-215

K8 WEST ELEVATION CH

1/4" = 1'-0" A-215

E1 NORTH ELEVATION CH

1/4" = 1'-0" A-215

K1 SOUTH ELEVATION CH

1/4" = 1'-0" A-215

E8 EAST ELEVATION CH

WINDOW REPAIR SCHEDULE

Window Number KEY DESCRIPTION

440 RS Remove and replace parting stop on exterior.

441 CWS Check wood soundness. If not in good condition, replace in kind. If in stable condition, apply consolidant.

441 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

441 SP Strip all paint/stain; apply fresh to match existing.

442 RS Remove and replace parting stop on exterior.

443 CWS Check wood soundness. If not in good condition, replace in kind. If in stable condition, apply consolidant.

443 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

443 SP Strip all paint/stain; apply fresh to match existing.

444 EPS Check condition of exterior parting stop, if stable apply consolidant.

444 RIP Remove and replace interior parting stop.

445 AFP Apply fresh paint to match existing finishes.

446 AFP Apply fresh paint to match existing finishes.

446 BGP Replace broken glass pane.

446 MM Place new middle muntin to match existing.

446 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

446 SP Strip all paint/stain; apply fresh to match existing.

448 EPS Check condition of exterior parting stop, if stable apply consolidant.

448 RIP Remove and replace interior parting stop.

449 AFP Apply fresh paint to match existing finishes.

449 MM Place new middle muntin to match existing.

449 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

449 SP Strip all paint/stain; apply fresh to match existing.

450 AFP Apply fresh paint to match existing finishes.

451 AFP Apply fresh paint to match existing finishes.

452 AFP Apply fresh paint to match existing finishes.

453 AFP Apply fresh paint to match existing finishes.

454 EPS Check condition of exterior parting stop, if stable apply consolidant.

454 RIP Remove and replace interior parting stop.

455 COB Strip paint and apply consolidant on exterior of bottom rail to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

455 COS Strip paint and apply consolidant on exterior of side stiles to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

455 EPS Check condition of exterior parting stop, if stable apply consolidant.

455 RIP Remove and replace interior parting stop.

456 COB Strip paint and apply consolidant on exterior of bottom rail to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

456 COS Strip paint and apply consolidant on exterior of side stiles to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

456 JSC If window does not need to come out of door, joints should be sealed with caulk to help prevent water intrusion into wood.

456 RG Remove and replace all glazing putty. Strip paint as needed; repaint to cover glazing putty.

GENERAL NOTES:

1. EXTERIOR TRIM, ENTABLATURE, AND PEDIMENT DETAIL, QUOINS, WINDOW

SURROUNDS, DECORATIVE BALCONIES AND OTHER ARCHITECTURAL DETAILS

HAVE NOT BEEN SHOWN FOR CLARITY AND ARE NOT PART OF THIS PROJECT.

2. APPROXIMATE SURFACING BASED ON PHOTOS.

WINDOW SCREEN REPAIR SCHEDULE

Window Number KEY Description

440 COB Strip paint and apply consolidant on exterior of bottom rail to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

441 COB Strip paint and apply consolidant on exterior of bottom rail to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

441 RS Remove and replace parting stop on exterior.

442 COB Strip paint and apply consolidant on exterior of bottom rail to repair existing wood, unless wood is too damaged once paint is removed, replace to match.

443 RSW Replicate storm window to replace this one.

444 RSG Remove all parting stops and screen mesh. Replace with new glass to match upper portion; place new parting stops to secure glass.

444 TSM Remove bottom parting stop (and side stops if necessary) to tighten screen mesh and replace bottom parting stop.