ADDENDUM NO. 2 to IFB No. B108440-EY for Springfield Road Sanitary Sewer Improvements, issued by York County, Virginia Central Purchasing on March 16, 2026, clarifies and modifies specifications and quantities in the original solicitation. The project involves installation of approximately 2,850 linear feet of 8-inch PVC SDR-26 gravity sewer piping, 14 pre-cast concrete manholes, 135 linear feet of 6-inch PVC SDR-26 piping, 4-inch lateral connections and cleanouts, erosion and sediment controls, traffic control, trench excavation and backfill, pavement restoration, driveway repairs, and fence repairs. The addendum confirms that the deadline for sealed bid submission remains March 24, 2026, at 2:30 PM EST. Key modifications address specification conflicts between the original bid form and project plans, establishing that all piping shall be PVC SDR-26, cleanouts shall be Schedule 80, Schedule 40, or PVC SDR-26, and that full width mill and overlay of the road is not required as part of the project. The addendum revises the bid form and project manual in their entirety to reflect corrected quantities for multiple items including fence repair (75 linear feet), manholes, gravel road repair, trench repair, laterals, and driveway repairs. Mobilization and clearing and grubbing are confirmed as incidental to other bid items, while erosion and sediment control requirements align with Virginia DEQ 18 Minimum Standards.
The addendum maintains the substantial completion deadline of 180 calendar days and final completion within 210 calendar days from Notice to Proceed without extension, with liquidated damages of $300 per calendar day for delays. Award will be made to the lowest responsive and responsible bidder. Contractors must hold a current Virginia Class A Contractors License and demonstrate a minimum of four years in the construction business with at least two similar projects completed within the past four years. A Bid Bond equal to five percent of the total bid amount is required, with Performance and Payment Bonds of one hundred percent of the contract price upon award. Insurance requirements include Commercial General Liability of $2,000,000 general aggregate, Business/Personal Automobile Liability of $1,000,000, Workers' Compensation at Virginia statutory benefits, Excess Third-Party Liability of $5,000,000, and Pollution Liability of $1,000,000 per claim, with York County named as additional insured on a primary and non-contributory basis. Bidders must acknowledge receipt of the addendum by returning the certification page signed and sealed with their bid submission. Final payment will be based on actual quantities determined during contract performance, with unit prices maintained for any change orders resulting from changed conditions.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IFB No. B108440-EY
ADDENDUM NO. 2
ISSUE DATE: 3/16/2026
County of York, Virginia
CENTRAL PURCHASING
120 Alexander Hamilton Blvd.
Yorktown, VA 23690 Phone: (757) 890-3680 https://www.yorkcounty.gov/571/Central-Purchasing
Solicitation Number: B108440-EY
Solicitation Name: Springfield Road Sanitary Sewer Improvements
Due: March 24, 2026 through 2:30 PM EST (Unchanged)
This Addendum supplements or modifies the original Solicitation noted above and is made part of the above identified solicitation. This Addendum consists of one-hundred fifty (150) pages.
o QUESTIONS, RESPONSES, AND NOTICES (FOUR (4) PAGES) o BID FORM (REVISED ADDENDUM 2) (ONE (1) PAGE) o PROJECT MANUAL (REVISED ADDENDUM 2) (ONE HUNDRED FORTY-FIVE (145)
PAGES)
Note the following changes and prepare your submittal accordingly. County Responses and notices appear in bold red below:
1. Question: Contract Time – Would the County be willing to increase the time for Substantial
Completion from 180 calendar days to 365 calendar days?
County Response: The time for substantial completion shall remain at 180 calendar days.
2. Question: Pay Item #5 – 8” Pipe – The bid schedule lists 8” SDR-35 pipe, however the project plans call for SDR-26. Please confirm which pipe specification should be used.
County Response: All piping shall be PVC SDR-26.
3. Question: Pay Item #6 – 6” Pipe – The bid schedule lists 6” SDR-35 pipe, however the project plans call for SDR-26. Please confirm which pipe specification should be used.
4. Question: Pay Item #7 – 4” Pipe – The bid schedule lists 4” Schedule 80, however the plans indicate SDR-26 or Schedule 40. Please confirm which pipe specification should be used.
5. Question: Pay Item #8 – 6” Cleanout – The bid schedule lists 6” Schedule 80 cleanout, however the plans call for Schedule 40. Please confirm which specification should be followed.
County Response: Cleanouts shall be schedule 80, schedule 40, or PVC SDR-26.
6. Question: Reference Bid Items 5 & 6 – 8-inch and 6-inch SDR35 PVC Pipe:
The bid form lists 8-inch and 6-inch SDR35 PVC pipe. However, the plans indicate the sanitary main is to be SDR-26 PVC. Please advise which specification is correct.
County Response: Pipe shall be SDR-26 PVC.
7. Question: Reference Bid Items 7 & 8 – 4-inch and 6-inch SCH80 Lateral Connections:
The bid form specifies SCH80 laterals. However, per Detail S1010 on Sheet C10, all sanitary service lateral piping and fittings shall be SDR-26 or SCH40 PVC. Please clarify the required material.
County Response: Pipe shall be SDR-26 or SCH40 PVC.
8. Question: Full Width Mill & Overlay Requirement:
The plans note that “VDOT Residency – Full Width Mill & Overlay of the Road is required.” However, there is no corresponding bid item listed on the bid form. Please confirm how this work is to be accounted for in the bid.
County Response: Full width mill and overlay of the road is not required as part of this project.
9. Question: Mobilization: There is no bid item listed for mobilization. Please confirm if mobilization is to be considered incidental to other bid items.
County Response: Mobilization shall be considered incidental to other bid items. It has been included in FES-6, Section 1.3, Item B.27 of “PROJECT MANUAL (REVISED ADDENDUM 2)”, published to eVA with Addendum 2.
10. Question: Clearing & Grubbing: No bid item is provided for clearing and grubbing. Please confirm whether this work is considered incidental or if a separate pay item will be added.
County Response: Clearing and Grubbing shall be considered incidental per FES-6, Section 1.3, Item B.2 of “PROJECT MANUAL (REVISED ADDENDUM 2)”, published to eVA with Addendum 2.
11. Question: Fence Repair Quantity: The plan quantity for fence repair does not match the quantity shown on the bid form. Please clarify the correct quantity.
County Response: Quantities have been reviewed and confirmed at 75 LF.
12. Question: Erosion & Sediment Control: The bid form includes an item for erosion and sediment control; however, no erosion control measures are shown on the plans. Please provide clarification.
County Response: This line is to capture the requirements of the DEQ 18 Minimum Standards. The Minimum Standards (MS) are listed in section 560 of the Virginia Erosion and Stormwater Management Regulation (9VAC25-875-560) and state when and where ESC practices must be used for the effective control of soil erosion and sediment deposition.
13. Question: Manhole Quantity: The number of manholes shown on the plans does not match the quantity listed on the bid form. Please confirm the correct count.
County Response: The Bid Form has been revised per Addendum 2. Page 64 of “SOLICITATION DOCUMENT” shall be replaced in its entirety by “BID FORM (REVISED ADDENDUM 2)”, published to eVA with Addendum 2.
14. Question: Gravel Road Repair Quantity: The plan quantity for gravel road repair does not match the bid form quantity. Please clarify.
County Response: The Bid Form has been revised per Addendum 2. Page 64 of
15. Question: Trench Repair (SY): The plan quantity for trench repair does not match the quantity listed on the bid form. Please confirm the correct quantity.
County Response: The Bid Form has been revised per Addendum 2. Page 64 of
16. Question: 4-inch Laterals: The plan count for 4-inch laterals differs from the quantity listed on the bid form. Please clarify.
County Response: The Bid Form has been revised per Addendum 2. Page 64 of
17. Question: Asphalt Driveway Repair: The plan takeoff quantity does not match the bid form quantity. Please confirm the correct amount.
County Response: The Bid Form has been revised per Addendum 2. Page 64 of
18. Question: Concrete Driveway Repair: The plan takeoff quantity does not match the bid form quantity. Please clarify.
County Response: The Bid Form has been revised per Addendum 2. Page 64 of
19. Question: Construction Time: The current construction duration appears limited. Based on our review of the scope of work, we anticipate approximately 9 months to reach final completion.
Would the Owner consider extending the allowable construction duration?
County Response: The Owner cannot extend the construction duration.
20. Question: Construction Entrance – Tranquility Subdivision: While work is being performed in that area, can the existing Tranquility Subdivision construction entrance be temporarily closed for sewer installation?
County Response: It is expected that traffic shall be maintained throughout construction.
21. Question: Existing Driveway Culverts: Several existing driveway culverts appear to be plugged with debris and sediment. Please clarify whether the Contractor will be responsible for cleaning or replacing these culverts when performing driveway repairs or replacements, or if this work will be handled by others or paid under a separate item.
County Response: Grading of the driveways shall be performed in accordance with detail PE-1 on sheet C-10. Grading of the upstream and downstream ditches may be necessary to maintain positive drainage which will require cleaning of the existing culverts per the pay item description in FES-6, Section 1.2, Item A of “PROJECT MANUAL (REVISED ADDENDUM 2)”, published to eVA with Addendum 2. When required, replacement of existing culverts shall be in kind and incidental to the project.
22. The Bid Form has been revised per Addendum 2. Page 64 of “SOLICITATION DOCUMENT” shall be replaced in its entirety by “BID FORM (REVISED ADDENDUM 2)”, published to eVA with Addendum 2.
23. “PROJECT MANUAL”, as originally published to eVA with this solicitation, shall be replaced in its entirety by “PROJECT MANUAL (REVISED ADDENDUM 2)”, published to eVA with Addendum 2.
END OF ADDENDUM CHANGES
To certify the information contained in this Addendum is incorporated in your submittal, this Addendum should be completed and returned sealed to Central Purchasing in the manner as specified in the original solicitation document.
Company Name: ______________________________________________________________________
Print Name: _________________________________Title: ____________________________________
Signature: ________________________________________ Date: ______________________________
This Form Must Be Signed.
Prepared By: Evan Young/Buyer
File details come from the government source that posted it. Updated .