This is Addendum No. 2 to Invitation for Bid (IFB) No. B108440-EY issued by the County of York, Virginia Central Purchasing for the Springfield Road Sanitary Sewer Improvements project. The addendum, issued on March 16, 2026, modifies the original solicitation and consists of 150 pages including questions and responses, a revised bid form, and a revised project manual. Key clarifications address pipe specifications (all piping shall be PVC SDR-26), cleanout standards (Schedule 80, Schedule 40, or PVC SDR-26), and confirmation that full-width mill and overlay of the road is not required as part of this project. The addendum confirms that mobilization and clearing and grubbing are incidental to other bid items and includes revised quantities for multiple pay items including manhole count, gravel road repair, trench repair, four-inch laterals, asphalt driveway repair, and concrete driveway repair, with all revisions detailed on the updated Bid Form (Revised Addendum 2). The bid due date remains March 24, 2026 at 2:30 PM EST, and the substantial completion time remains at 180 calendar days with no extensions permitted. Traffic must be maintained throughout construction, and existing driveway culvert cleaning is required per the pay item description in the project manual, with replacement of culverts in kind being incidental to the project.
No pricing terms, set-asides, or funding information is specified in this addendum document. The addendum serves primarily as a clarification tool to address bidder questions regarding material specifications, work scope definitions, and quantity confirmations that differed between the original bid form and project plans. Contractors must certify receipt and incorporation of Addendum 2 by completing and returning the signed certification form with their bid submittal.
View the file
Other files
Show all 20
On GovTribe
Work with this file
- Download the original file
- Contacts named in this file
- Similar government files
- Ask GovTribe AI about this file
Text version
IFB No. B108440-EY
ADDENDUM NO. 2
ISSUE DATE: 3/16/2026
County of York, Virginia
CENTRAL PURCHASING
120 Alexander Hamilton Blvd.
Yorktown, VA 23690 Phone: (757) 890-3680 https://www.yorkcounty.gov/571/Central-Purchasing
Solicitation Number: B108440-EY
Solicitation Name: Springfield Road Sanitary Sewer Improvements
Due: March 24, 2026 through 2:30 PM EST (Unchanged)
This Addendum supplements or modifies the original Solicitation noted above and is made part of the above identified solicitation. This Addendum consists of one-hundred fifty (150) pages.
o QUESTIONS, RESPONSES, AND NOTICES (FOUR (4) PAGES) o BID FORM (REVISED ADDENDUM 2) (ONE (1) PAGE) o PROJECT MANUAL (REVISED ADDENDUM 2) (ONE HUNDRED FORTY-FIVE (145)
PAGES)
Note the following changes and prepare your submittal accordingly. County Responses and notices appear in bold red below:
1. Question: Contract Time – Would the County be willing to increase the time for Substantial
Completion from 180 calendar days to 365 calendar days?
County Response: The time for substantial completion shall remain at 180 calendar days.
2. Question: Pay Item #5 – 8” Pipe – The bid schedule lists 8” SDR-35 pipe, however the project plans call for SDR-26. Please confirm which pipe specification should be used.
County Response: All piping shall be PVC SDR-26.
3. Question: Pay Item #6 – 6” Pipe – The bid schedule lists 6” SDR-35 pipe, however the project plans call for SDR-26. Please confirm which pipe specification should be used.
4. Question: Pay Item #7 – 4” Pipe – The bid schedule lists 4” Schedule 80, however the plans indicate SDR-26 or Schedule 40. Please confirm which pipe specification should be used.
5. Question: Pay Item #8 – 6” Cleanout – The bid schedule lists 6” Schedule 80 cleanout, however the plans call for Schedule 40. Please confirm which specification should be followed.
County Response: Cleanouts shall be schedule 80, schedule 40, or PVC SDR-26.
6. Question: Reference Bid Items 5 & 6 – 8-inch and 6-inch SDR35 PVC Pipe:
The bid form lists 8-inch and 6-inch SDR35 PVC pipe. However, the plans indicate the sanitary main is to be SDR-26 PVC. Please advise which specification is correct.
County Response: Pipe shall be SDR-26 PVC.
7. Question: Reference Bid Items 7 & 8 – 4-inch and 6-inch SCH80 Lateral Connections:
The bid form specifies SCH80 laterals. However, per Detail S1010 on Sheet C10, all sanitary service lateral piping and fittings shall be SDR-26 or SCH40 PVC. Please clarify the required material.
County Response: Pipe shall be SDR-26 or SCH40 PVC.
8. Question: Full Width Mill & Overlay Requirement:
The plans note that “VDOT Residency – Full Width Mill & Overlay of the Road is required.” However, there is no corresponding bid item listed on the bid form. Please confirm how this work is to be accounted for in the bid.
County Response: Full width mill and overlay of the road is not required as part of this project.
9. Question: Mobilization: There is no bid item listed for mobilization. Please confirm if mobilization is to be considered incidental to other bid items.
County Response: Mobilization shall be considered incidental to other bid items. It has been included in FES-6, Section 1.3, Item B.27 of “PROJECT MANUAL (REVISED ADDENDUM 2)”, published to eVA with Addendum 2.
10. Question: Clearing & Grubbing: No bid item is provided for clearing and grubbing. Please confirm whether this work is considered incidental or if a separate pay item will be added.
County Response: Clearing and Grubbing shall be considered incidental per FES-6, Section 1.3, Item B.2 of “PROJECT MANUAL (REVISED ADDENDUM 2)”, published to eVA with Addendum 2.
11. Question: Fence Repair Quantity: The plan quantity for fence repair does not match the quantity shown on the bid form. Please clarify the correct quantity.
County Response: Quantities have been reviewed and confirmed at 75 LF.
12. Question: Erosion & Sediment Control: The bid form includes an item for erosion and sediment control; however, no erosion control measures are shown on the plans. Please provide clarification.
County Response: This line is to capture the requirements of the DEQ 18 Minimum Standards. The Minimum Standards (MS) are listed in section 560 of the Virginia Erosion and Stormwater Management Regulation (9VAC25-875-560) and state when and where ESC practices must be used for the effective control of soil erosion and sediment deposition.
13. Question: Manhole Quantity: The number of manholes shown on the plans does not match the quantity listed on the bid form. Please confirm the correct count.
County Response: The Bid Form has been revised per Addendum 2. Page 64 of “SOLICITATION DOCUMENT” shall be replaced in its entirety by “BID FORM (REVISED ADDENDUM 2)”, published to eVA with Addendum 2.
14. Question: Gravel Road Repair Quantity: The plan quantity for gravel road repair does not match the bid form quantity. Please clarify.
County Response: The Bid Form has been revised per Addendum 2. Page 64 of
15. Question: Trench Repair (SY): The plan quantity for trench repair does not match the quantity listed on the bid form. Please confirm the correct quantity.
County Response: The Bid Form has been revised per Addendum 2. Page 64 of
16. Question: 4-inch Laterals: The plan count for 4-inch laterals differs from the quantity listed on the bid form. Please clarify.
County Response: The Bid Form has been revised per Addendum 2. Page 64 of
17. Question: Asphalt Driveway Repair: The plan takeoff quantity does not match the bid form quantity. Please confirm the correct amount.
County Response: The Bid Form has been revised per Addendum 2. Page 64 of
18. Question: Concrete Driveway Repair: The plan takeoff quantity does not match the bid form quantity. Please clarify.
County Response: The Bid Form has been revised per Addendum 2. Page 64 of
19. Question: Construction Time: The current construction duration appears limited. Based on our review of the scope of work, we anticipate approximately 9 months to reach final completion.
Would the Owner consider extending the allowable construction duration?
County Response: The Owner cannot extend the construction duration.
20. Question: Construction Entrance – Tranquility Subdivision: While work is being performed in that area, can the existing Tranquility Subdivision construction entrance be temporarily closed for sewer installation?
County Response: It is expected that traffic shall be maintained throughout construction.
21. Question: Existing Driveway Culverts: Several existing driveway culverts appear to be plugged with debris and sediment. Please clarify whether the Contractor will be responsible for cleaning or replacing these culverts when performing driveway repairs or replacements, or if this work will be handled by others or paid under a separate item.
County Response: Grading of the driveways shall be performed in accordance with detail PE-1 on sheet C-10. Grading of the upstream and downstream ditches may be necessary to maintain positive drainage which will require cleaning of the existing culverts per the pay item description in FES-6, Section 1.2, Item A of “PROJECT MANUAL (REVISED ADDENDUM 2)”, published to eVA with Addendum 2. When required, replacement of existing culverts shall be in kind and incidental to the project.
22. The Bid Form has been revised per Addendum 2. Page 64 of “SOLICITATION DOCUMENT” shall be replaced in its entirety by “BID FORM (REVISED ADDENDUM 2)”, published to eVA with Addendum 2.
23. “PROJECT MANUAL”, as originally published to eVA with this solicitation, shall be replaced in its entirety by “PROJECT MANUAL (REVISED ADDENDUM 2)”, published to eVA with Addendum 2.
END OF ADDENDUM CHANGES
To certify the information contained in this Addendum is incorporated in your submittal, this Addendum should be completed and returned sealed to Central Purchasing in the manner as specified in the original solicitation document.
Company Name: ______________________________________________________________________
Print Name: _________________________________Title: ____________________________________
Signature: ________________________________________ Date: ______________________________
This Form Must Be Signed.